To get a building permit in Fortuna, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Fortuna’s Building Division, in the Community Development Department at 621 11th Street, issues building permits inside the city through its online permit portal and inspects work Monday through Thursday.

Authority: Fortuna Building DivisionFees: Resolution 2026-18Phone: 707-725-7600
Authority
City Building DivisionCommunity Development, 621 11th Street
Counter
Mon–Thu only8–10 a.m. and 1:30–3:30 p.m.
Plan review
65% of permit feeCollected with the application
Surcharges
5.5% + 11%Technology and General Plan, all permits

Inside the City of Fortuna, building permits are issued by the Building Division of the Community Development Department at 621 11th Street (707-725-7600), where Gary Goade is the Building Official. Applications are filed electronically through the city’s OpenGov permit portal, City offices are closed on Fridays, and inspections run Monday through Thursday. Under the FY 2026-27 fee schedule (Resolution 2026-18), plan review costs 65% of the building permit fee and is collected when you apply.

What requires a building permit in Fortuna?

Fortuna’s residential application covers new houses, additions and remodels (living area, garages and carports, decks, covered entries and patios), and the mechanical, electrical, plumbing and re-roofing jobs listed on its second page: panel change-outs and upgrades, electrical systems, water heaters, plumbing change-outs, HVAC, fireplaces and wood stoves, gas lines, water supply lines and roofing. The application warns that work may not start without a permit, and that unpermitted work can lead to penalties and removal of the work at the owner’s cost.

Over-the-counter jobs in the fee schedule

  • Residential re-roofs, priced by roof area
  • Electrical service swaps up to and over 200 amps
  • Temporary power poles
  • Furnace, heat pump and duct work
  • Water heaters, gas outlets, fixtures and water services
  • Residential and commercial solar, and battery backup

City handouts for common projects

  • Accessory dwelling unit handout and project information sheet
  • Deck construction guide
  • Design criteria and common framing problems
  • EV charging station permitting checklist
  • Low impact development stormwater forms
  • Water-efficient landscape (MWELO) forms

For a job that is not on the application, call 707-725-1435 to ask whether it needs a permit before work starts. Work in a street, alley or sidewalk needs a separate encroachment permit.

What Fortuna decides and what the state holds

Fortuna sets its own permit, planning and connection fees each fiscal year, runs its own construction and demolition debris ordinance (Ordinance 2023-762), and controls land use through its Planning Division and a seven-member Planning Commission. The building standards and contractor licenses are state matters.

Fortuna building department: who handles permitting

The Building Division, called the Building & Safety Division on its forms, issues building, electrical, plumbing and mechanical permits for property inside Fortuna. The Planning Division in the same department handles zoning and land use permits, and the city’s Risk Management office lists encroachment permits. Land outside city limits is under Humboldt County. Since June 30, 2025, the city has worked a 34-hour week: Community Development staff work 8.5-hour days Monday through Thursday, and City offices are closed on Fridays.

Short on time to read all of this?

Get a free quote →
Fortuna permit contacts
DetailInformation
OfficeBuilding Division, Community Development Department, 621 11th Street, Fortuna, CA 95540 (mail: P.O. Box 545)
Phone707-725-7600 (City Hall); 707-725-1435 for permit portal questions
Building counterMonday to Thursday, 8 to 10 a.m. and 1:30 to 3:30 p.m.; closed Friday
Building OfficialGary Goade
Online filingCity of Fortuna OpenGov permit portal
Solar fire reviewFortuna Fire Protection District

Fortuna permit types

All building permit applications are filed electronically in the city’s permit portal, although some projects also need hard-copy site plans. The residential application asks for the owner, contractor, architect and engineer, the contractor’s state license and Fortuna business license, workers’ compensation details, the type of construction, plumbing fixture units being kept, added or removed, a written estimate of total labor and material cost, setbacks, and whether the lot is in the business district or the flood plain.

Residential permits

  • New houses and additions list living area, garage or carport, decks and covered entries separately; fire-resistive construction near property lines and fire sprinklers are flagged on the form.
  • ADUs are governed by Fortuna Municipal Code section 17.06.001.5, summarized in the city’s ADU handout dated November 1, 2021. The handout allows an ADU in any zone where houses or apartments are permitted, one per single-family lot, with a detached unit of up to 1,200 square feet and 16 feet high with ministerial approval, 4-foot side and rear setbacks (0 feet next to an alley), no parking requirement, a separate exterior entrance and a permanent foundation. A detached unit of up to 800 square feet and 16 feet needs to meet only the general requirements. The city does not treat an ADU as a new use for water and sewer connection fees unless it is built along with a new house, and a rented ADU cannot be leased for less than 30 days. The planning ADU permit costs $312, and a sample deed restriction is posted with the forms.
  • Roof-mounted solar by a licensed contractor can use SolarAPP+: get the SolarAPP+ approval, have the Fortuna Fire Protection District approve the plans, then apply in the portal and upload both; the permit is issued as soon as fees are paid. Owner-builders and other systems use the regular solar permit.
  • Short-term rentals follow the city’s posted short-term rental requirements and a $600 planning permit.

Commercial permits

Commercial projects use the commercial plan submittal checklist, the disabled access compliance form, the low impact development stormwater control plan for regulated projects, and landscape certification forms where landscaping is installed. Commercial solar is listed at $1,000 for systems up to 50 kW, $7 per kW for 50 to 250 kW and $5 per kW above 250 kW, and nonresidential projects covered by the debris ordinance post a deposit of 0.25% of project cost or $500, whichever is greater.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning clearance ($135) or a discretionary permit such as design review, a conditional use permit or a variance, filed through the same portal.
  • Pre-application meeting with planning staff: the first hour per project is free, then $450 an hour.
  • Encroachment permit for sidewalks, driveways, utility work, scaffolding, tree trimming or equipment in the right-of-way; a contractor must sign the application and provide insurance.
  • Flood plain: if the building is in the flood plain, the application asks for flood plans information.

Fortuna permit costs and fees

Fortuna’s FY 2026-27 fee schedule, adopted by Resolution 2026-18 and posted as effective July 1, 2026, prices building permits on valuation. Plan review is 65% of the building permit fee, collected when you apply, and every permit carries a 5.5% technology surcharge and an 11% General Plan surcharge.

Fortuna building fees, FY 2026-27 (Resolution 2026-18)
ItemFee
Minimum permit fee / permit issuance$130 / $53.85
Valuation $2,001–$25,000$140.95 plus $21.79 per $1,000 over $2,000
Valuation $25,001–$50,000$642.12 plus $14.75 per $1,000 over $25,000
Valuation $50,001–$100,000$1,010.87 plus $9.94 per $1,000 over $50,000
Valuation $100,001–$500,000$1,507.87 plus $7.73 per $1,000 over $100,000
Valuation $500,001–$1,000,000 / over $1,000,000$4,599.87 plus $6.55 per $1,000 / $7,874.87 plus $5.17 per $1,000
Plan review / expedited plan review65% / 100% of the building permit fee
Residential re-roof up to 2,000 / 3,000 / over 3,000 sq ft$215.29 / $269.24 / $322.94
Residential solar up to 15 kW / over 15 kW$400 / $15 per kW
Electrical service swap up to 200 amps / over 200 amps$161.48 / $215.29
Re-inspection or inspection with no listed fee$107.67 per hour, 1-hour minimum
Debris diversion: administrative fee / residential deposit$175 / $500 (deposit refunded on compliance)
Wastewater capital connection$6,321 up to 14 fixture units, plus $452 per added unit
Water capital connection, 5/8 x 3/4 inch meter$3,078.80

Rather talk it over?

Call 1-855-478-4290 →

Worked example from the valuation table: a $200,000 project falls in the $100,001–$500,000 band, so the building permit fee is $1,507.87 plus 100 × $7.73, or $2,280.87, and plan review is 65% of that, $1,482.57. Permit issuance, the 5.5% and 11% surcharges, the state seismic fee and any connection and impact fees are added. New homes on Home Avenue and its connecting streets pay a $4,275 traffic impact fee per dwelling, and on Hillside Drive $2,620. Work started without a permit pays an extra fee equal to the permit fee, and an expired permit or plan review can be renewed for 50% of the original fee if the same codes still apply.

Trade permits and who may pull them

Electrical, plumbing, gas and mechanical work is permitted by the Building Division, either on the main application or as over-the-counter permits priced by estimated inspection time. A new one- or two-family home pays electrical fees of 12.4 cents per square foot of living area.

  • Contractors list their state license number, class and expiration date and their Fortuna business license on the application, and sign the city’s contractor declaration. Contractors without a fixed place of business in Fortuna pay a business license fee of $5 a day, or may choose the gross-receipts license instead.
  • Owner-builders sign the city’s owner-builder acknowledgement; a property owner authorization form is used when someone else applies for the owner.
  • SolarAPP+ is for licensed contractors and installers only.
  • Plumbing fixture units on the application drive the wastewater connection fee: a single-family home with one bathroom, kitchen, dishwasher and washer counts as 14 units.

Rather not deal with the building department?

Get a free quote →

How to apply for a Fortuna building permit

1. Confirm the parcel

Check that the address is inside Fortuna and whether it lies in the flood plain or business district.

2. Clear planning items

File any zoning clearance or discretionary permit, or book a pre-application meeting, through the portal.

3. Gather the forms

Complete the application, contractor declaration or owner-builder acknowledgement, and any ADU, stormwater, landscape or debris forms.

4. Apply in OpenGov

Create an account in the City of Fortuna permit portal and upload the application and plans; deliver hard-copy site plans if asked.

5. Pay plan review

The 65% plan review fee is collected with the application.

6. Receive the permit and book inspections

Once approved and paid, schedule inspections in the portal under the permit record number.

Review, corrections and what causes delay

Fortuna’s application states that an incomplete application cannot be processed, so missing cost estimates, fixture counts or setbacks stop the clock. Changes or additional review after the first review are billed at $107.67 an hour with a half-hour minimum, and a substantial plan redesign is charged 100% of the plan review fee. The counter is open Monday to Thursday only, two hours each morning and afternoon.

Inspections in Fortuna

Book inspections in the OpenGov citizen portal by selecting the building permit record number. Inspections run Monday through Thursday; the building page asks for at least 24 hours’ notice, says notice the day before is preferred, and allows same-day inspections if a message is left before 8 a.m. No final inspections are done after 1 p.m. Re-inspections, after-hours inspections (2-hour minimum) and inspections with no listed fee cost $107.67 an hour.

Single- and two-family remodels and additions do not receive a certificate of occupancy: the inspector signs off the inspection card, and the owner keeps it. A new home gets its certificate once the building is complete, all trades are tested and signed off, Public Works approves the water meter, backflow device and right-of-way improvements, the driveway is paved in asphalt or concrete, the address is posted, site improvements are finished or covered by an agreement, and stormwater measures or landscaping are in place. New multifamily and commercial buildings need a certificate before anyone moves in, on the same checklist plus sign-offs on any other inspection cards from Planning, Public Works, the fire authority or the Humboldt County Health Department; a commercial remodel that changes the occupancy group also gets one on completion. A temporary certificate may be released by agreement. Appeals of a residential certificate inspection go to the Building Official; for multifamily and commercial work, to the director or chief of the department involved.

California building code in Fortuna

Fortuna enforces the state building code through its own Building Division under the city’s municipal code, and its certificate of occupancy rules follow the city’s adopted California Building Code. FEMA’s Community Status Book lists Fortuna (community 060063) as participating in the National Flood Insurance Program, with a current flood map dated November 4, 2016.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Fortuna building permit FAQs

Who issues building permits in Fortuna?

The City of Fortuna Building Division at 621 11th Street (707-725-7600), for property inside city limits.

Is the Fortuna building counter open on Fridays?

No. City offices close on Fridays; the building counter is open Monday to Thursday from 8 to 10 a.m. and 1:30 to 3:30 p.m.

How much is a building permit in Fortuna?

For a $200,000 project the building permit fee is $2,280.87 and plan review $1,482.57, before issuance, the 5.5% and 11% surcharges and state fees.

How much does a re-roof permit cost?

A residential re-roof is an over-the-counter permit: $215.29 up to 2,000 square feet, $269.24 up to 3,000 and $322.94 above that.

Can I get a same-day inspection?

Yes, if you leave a message before 8 a.m. on an inspection day, Monday to Thursday; final inspections are not done after 1 p.m.

Does a remodel get a certificate of occupancy?

No. Single- and two-family remodels and additions get a signed-off inspection card instead; new homes and new commercial buildings get a certificate.

How big can a detached ADU be in Fortuna?

The city’s ADU handout sets 1,200 square feet for a detached ADU, 16 feet high with ministerial approval, with 4-foot side and rear setbacks and no parking requirement.

Who approves rooftop solar plans?

The Fortuna Fire Protection District approves the plans for SolarAPP+ permits before the city issues them; owner-builders apply for a regular solar permit.

Fortuna permit search and official resources

Permit applications, records and inspection requests are handled in the City of Fortuna OpenGov portal. For older building records or questions about an address, call 707-725-7600 during office hours, Monday through Thursday.

Inspections are where schedules slip.

Get a free quote →

Simplify Fortuna permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Fortuna sooner?

Let Alliance prepare, file, and track your Fortuna permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Fortuna permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.