Outside the ten incorporated cities, building permits in Ventura County come from the Building and Safety Division of the county Resource Management Agency, at the Government Center, 800 S. Victoria Avenue in Ventura, and at an east county office in Thousand Oaks. Applications, plans and payments go through the VC Citizen Access portal. Under the division’s fee schedule effective July 18, 2026, plan review costs 85% of the valuation-based permit fee, and a first review of new plans takes four to five weeks.
What requires a building permit in unincorporated Ventura County?
Almost every building and structure needs a permit before work begins; public schools, hospitals, utility infrastructure and Public Works projects in the right of way are outside county control. Section 105.2 of the Ventura County Building Code (VCBC) lists the private work that needs no building permit:
No building permit (VCBC 105.2)
- One-story detached tool and storage sheds, playhouses and similar structures accessory to a house, up to 120 square feet and 15 feet tall
- Fences up to 7 feet, except pool barriers; masonry or concrete walls up to 5 feet
- Retaining walls up to 3 feet that carry no surcharge
- Decks, platforms, walks and driveways at one- and two-family homes no more than 30 inches above grade
- Painting, tiling, carpeting, cabinets, counters and similar finish work
- Open animal shade covers up to 12 feet tall and 1,000 square feet of roof
Permit needed
- New buildings, additions, alterations and structural repairs
- Patio covers, decks over 30 inches, carports, garages and retaining walls over the limits
- Re-roofing and window replacements
- Electrical, plumbing and mechanical installations, solar systems, battery storage and EV chargers
- Pools, spas, demolitions and manufactured homes
Section 105.1.2.3 adds that an exemption from Building and Safety does not exempt the work from any other agency, so a shed may still need to meet Planning setbacks. Work done without a required permit carries an investigation fee equal to the permit fee.
What the county decides and what the state holds
The Board of Supervisors adopted the 2025 VCBC as Ordinance No. 4655 on November 18, 2025, effective January 1, 2026. It combines the state codes with county amendments such as the exempt-work list, owner-builder conditions, mobile home rules, post-disaster recovery provisions and relaxed standards for limited-density owner-built rural dwellings; county residential amendments in force on September 30, 2025 carry over. Contractor licenses come from the state.
Ventura County building department: who handles permitting
The county’s FAQ says projects inside a city’s limits are permitted by that city; each of the ten cities runs its own building department:
| Place | Building permits |
|---|---|
| All land outside the ten city limits | Ventura County Building and Safety |
| Ventura (San Buenaventura), Oxnard, Camarillo, Simi Valley, Thousand Oaks | Each city’s own building division |
| Fillmore, Moorpark, Ojai, Port Hueneme, Santa Paula | Each city’s own building office |
Short on time to read all of this?
Get a free quote →To check whether an address is unincorporated, look up its 9- or 10-digit assessor parcel number in Planning’s What’s My Zoning tool or the County View web map, and switch on the Cities layer; the Assessor’s Office (805-654-2181) can supply a missing parcel number.
| Office | Contact |
|---|---|
| Building and Safety, Ventura office | Government Center Administration Building, 3rd floor, 800 S. Victoria Avenue, Ventura, CA 93009; 805-654-2771; building@venturacounty.gov; Monday to Wednesday and Friday 8 a.m. to 4 p.m., Thursday 9 a.m. to 4 p.m. |
| Building and Safety, Newbury Park office (east county) | Ventura County Fire Department headquarters, 2400 Conejo Spectrum Street, Thousand Oaks, CA 91320; 805-582-8064; Monday to Wednesday and Friday 7:30 a.m. to 5 p.m., Thursday 9 a.m. to 5 p.m. |
| Inspection requests | 805-654-2791 (Ventura) or 805-582-8063 (Newbury Park), or by text message |
| Planning Division (zoning clearances, ADUs, coastal zone) | Same Government Center; RMA main line 805-654-2494 |
| Environmental Health (septic systems, water supply) | Hall of Administration, 3rd floor, 800 S. Victoria Avenue; counter 8 a.m. to 4 p.m. weekdays; OWTS inspection hotline 805-477-7136 |
| Portal | VC Citizen Access for building, zoning clearance and septic applications |
Ventura County permit types
Building and Safety issues combination permits for buildings that include trade work, single-trade building permits (patio covers, decks, sheds, re-roofs, window replacements), separate electrical, plumbing and mechanical permits, demolition permits, and annual maintenance permits that cover small repeat jobs at commercial or multi-family sites ($222 for one building plus $178 per inspection).
Residential permits
- Small jobs. Re-roofs, window change-outs and equipment swaps usually need no plans; at the counter many are issued in 20 to 30 minutes.
- Inspector plan check. Non-engineered one-story additions under 1,000 square feet, patio covers, carports, garages, decks and detached one-story granny flats up to 700 square feet are normally checked by a building inspector using handout B-1; two-story or engineered work goes to plan check.
- Standard plans. The county publishes a garage standard plan, handout B-17 for patio covers, and free pre-reviewed ADU and farmworker dwelling plans of 700, 900 and 1,188 square feet with reduced review fees.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
New commercial buildings and tenant improvements get full review for structure, fire and life safety, accessibility, energy and green building, with trade plan review at 85% of each trade fee. A new business in an existing building pays $267 for the review behind its certificate of occupancy. Owner-hired special inspectors are required for work such as concrete over 2,500 psi, structural masonry and field welding.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning clearance. Planning issues ministerial zoning clearances through Citizen Access: $193 for simple structures such as patio covers, decks, pools, sheds and fences over 7 feet, $333 for additions, $444 for new homes and detached residential buildings, and $680 for an ADU, with a $55 application fee credited to the total. ADUs that meet the zoning ordinance’s base standards need only a building permit.
- Coastal zone. Development in the unincorporated coastal zone falls under the county’s Local Coastal Program and Coastal Zoning Ordinance (certified in 2017); Categorical Exclusion Order E-83-1 exempts some categories from coastal development permits.
- Agency clearances. Building and Safety lists the clearances each project needs (Planning, Environmental Health, Fire, Public Works), and proof of each is due before issuance.
- Septic and water. Environmental Health reviews septic designs, repairs and certifications, and any project with domestic plumbing must show a permanent potable water supply.
Ventura County building permit fees
Building and Safety fees come from the division’s fee schedule, originally adopted on December 19, 1995 and most recently revised on May 19, 2026, effective July 18, 2026. The schedule in force when an application is accepted applies. Valuation covers all finish work and permanent equipment, and the Building Official sets the final figure.
| Item | Fee |
|---|---|
| Application fee (projects with plan review) | $74, credited to plan review |
| Issuance: single permit / combination permit | $59 / $133 |
| Building permit, $2,001 to $25,000 valuation | $128.25 plus $24.16 per $1,000 over $2,000 |
| Building permit, $25,001 to $50,000 | $684 plus $20.52 per $1,000 over $25,000 |
| Building permit, $100,001 to $500,000 | $1,881 plus $9.83 per $1,000 over $100,000 |
| Plan review | 85% of the building permit fee, minus the application fee |
| Energy / green building / accessibility review | 10% / 6% / 10% of both the plan review and permit fees |
| Fire hazard zone / flood zone / hillside | 5% / 10% / 10% of both fees |
| Expedited plan review | 35% surcharge on the plan review fee |
| Demolition, per building | $311 |
| Residential solar | $222 for the first 15 kW plus $16 per kW over |
| New house electrical / plumbing / mechanical | $0.36 / $0.14 / $0.08 per sq ft |
| Reinspection | $178 |
| General Plan and technology surcharges | $4.30 and $2.50 per $1,000 of valuation |
| Work without a permit | Investigation fee equal to the permit fee |
Rather talk it over?
Call 1-855-478-4290 →Worked example: a $50,000 remodel falls at the top of the $25,001 to $50,000 band, so the building permit fee is $684 plus 25 × $20.52, or $1,197. Plan review is 85% of that ($1,017.45) less the $74 application fee already paid, so $943.45 is due with the plans. At issuance the combination permit adds the $133 issuance fee, the $1,197 permit fee and the surcharges of 50 × $4.30 = $215 and 50 × $2.50 = $125, bringing the county total to $2,687.45 before trade fees, any energy, accessibility or hazard-zone percentages and the state seismic and Building Standards Commission fees.
The division’s fees page still quotes older surcharge rates ($6.50 and $3.75 per $1,000); the July 2026 schedule is the adopted one. New construction also pays fire and sheriff facility fees at issuance, while school, traffic impact, sewer and water connection fees are collected by those agencies.
Trade permits and who may pull them
Trade work in a new building or addition goes on the combination permit at square-foot rates; stand-alone trade work is priced by unit, such as $89 for a service up to 400 amps, $89 for a subpanel, $30 per plumbing fixture or water heater, $42 for a heating appliance or condenser and $74 for a heat pump, plus the $59 issuance fee. Plumbing and electrical plan review, where plans are needed, adds 85% of that trade’s fee.
VCBC section 107.6.2 limits permits to applicants entitled to do the work under the state Contractors’ License Law, and at issuance the contractor signs the permit documents. An owner may take out an owner-builder permit to build or improve a principal residence that is not offered for sale and that the owner has lived in for the 12 months before the work is finished, or to build with licensed contractors under contract. Tenants may obtain tenant improvement permits with the building owner’s authorization.
The county’s owner-builder handout warns that an owner who pays unlicensed workers can take on an employer’s payroll tax and workers’ compensation duties; it still prints $500, though the state license threshold is now $1,000.
Rather not deal with the Ventura County building department?
Get a free quote →How to apply for a Ventura County building permit
Use What’s My Zoning or the County View map with the Cities layer on; inside a city, apply to that city instead.
Upload the Zoning Clearance Application Packet in Citizen Access, or confirm with Planning that an ADU needs a building permit only.
Create a Citizen Access account and submit the application and plans online, or file at the Ventura or Newbury Park counter; pay the application and plan review fees.
Send plans to each agency on the list (Environmental Health, Fire, Public Works) and upload proof of their clearances.
Plans come back with a correction letter; resubmit the revised set to the resubmittal line until approved.
The contractor signs the permit documents, the remaining fees are paid, and you receive the approved plans, the permit and the inspection record card.
Review, corrections and what causes delay
The Plan Reviews page gives four to five weeks for new submittals and two to three weeks for resubmittals, while the division’s FAQ quotes about three to four weeks for a first review of a complete application and one to two weeks for later rounds; it advises planning for two or three reviews. A new home commonly takes several months. Applications expire 12 months after filing if no permit is issued, with one six-month extension possible; the extension fee is 10% of the plan check or permit fee, capped at $178.
Inspections in unincorporated Ventura County
Request inspections by text message or on the 24-hour voicemail lines, 805-654-2791 (Ventura) or 805-582-8063 (Newbury Park). Requests left before 4 p.m. on a business day are done the next business day; later ones go to the second business day. Inspectors work 8 a.m. to 4 p.m. weekdays; after-hours inspections need three working days’ notice and cost $245.51 an hour, two-hour minimum.
A house moves through foundation, slab, framing with rough trades, insulation, lath and drywall, a final gas test and the final. Footing forms are checked against setbacks and flood elevations, and the county does not accept welded wire fabric as slab reinforcement. Nothing may be covered before approval, and repeat visits caused by work not being ready cost $178 each.
An issued permit expires if work does not start within 12 months or stops for 180 days; renewal costs no more than 50% of the full permit fee. A temporary or partial certificate of occupancy is $355 and a reissued certificate $89.
California building code in Ventura County
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →The county’s amendments also add seismic design rules for hillside buildings, geotechnical report requirements, a grading appendix and optional all-electric design for new buildings. FEMA’s Community Status Book lists unincorporated Ventura County (community 060413) as participating in the National Flood Insurance Program, with maps effective April 11, 2024 and Community Rating System class 5, a 25% premium discount.
Ventura County permit search and official resources
Permit status, plan review comments and fees are in Citizen Access, which needs an account and a permit record number linked to your email; the division adds an email to a record on request at 805-654-2771 or 805-582-8064. Building and Safety searches its archives for a building’s permit history free of charge through its Public Records Search Request page and publishes weekly lists of permits issued since 2018; Environmental Health keeps an online search of septic records.
- Building and Safety permit information
- Building and Safety offices and hours
- VC Citizen Access portal
- Permit types and exempt work
- Plan reviews and review times
- Inspection requests and stages
- Building and Safety fee schedule, effective July 18, 2026
- Building permit fee estimator
- Ventura County Building Code page
- 2025 Ventura County Building Code, Ordinance No. 4655
- Owner-builder handout
- What’s My Zoning parcel lookup
- Zoning clearances and ministerial permits
- Planning Division fee schedule
- Accessory dwelling unit rules
- Local Coastal Program
- Septic system (OWTS) program
- Water well permit restrictions
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Ventura County building permit FAQs
Does Ventura County issue building permits inside cities?
No. The county permits only unincorporated land; Ventura, Oxnard, Simi Valley, Thousand Oaks, Camarillo, Moorpark, Santa Paula, Port Hueneme, Fillmore and Ojai each issue their own.
How big a shed can I build without a permit?
A one-story detached shed of up to 120 square feet and 15 feet tall needs no building permit, though Planning’s setbacks still apply.
How much does a county building permit cost?
It depends on valuation: a $50,000 job carries a $1,197 permit fee plus plan review at 85% of that, less the $74 application fee, and issuance fees and surcharges.
How long does plan review take?
About four to five weeks for a first review and two to three weeks for each resubmittal; plan on two or three rounds.
Can a homeowner pull the permit?
Yes, for a principal residence the owner has lived in for the 12 months before completion and is not selling, or when the owner hires licensed contractors.
Do I need a zoning clearance as well?
Usually. Planning issues zoning clearances for most new structures and additions, from $193 for a patio cover or pool to $444 for a new home.
Simplify Ventura County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Ventura County sooner?
Let Alliance prepare, file, and track your Ventura County permits while your crew stays on the job.
More California permitting guides
Camarillo
Read guide →Fillmore
Read guide →Moorpark
Read guide →Victorville Building Permit Guide
Read guide →Visalia Building Permit Guide
Read guide →Vista Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Ventura County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.