In Exeter, building permits are issued by the Tulare County Building Department, which the City partners with for plan check, permitting and inspection (5961 S. Mooney Boulevard, Visalia; 559-624-7000). Before the first inspection, pick up an inspection card at Exeter City Hall, 137 North F Street. The City’s own fees for a new single-family home include $3,419 in development impact fees plus water and sewer connection charges under its FY 2024–2025 schedule.
What requires a building permit in Exeter?
The City’s building FAQ says a construction permit is needed for all new construction and, in many cases, for repairing or replacing existing features such as windows. Any addition or change to a building’s plumbing, electrical or mechanical system needs a trade permit; moving or adding a single electrical outlet is the City’s own example. Complete demolition and relocation of a building also need permits. When in doubt, the City sends residents to the Tulare County Building Department to ask whether a project needs a permit.
Permit from Tulare County
- New buildings, additions and remodels (structural or combination permits)
- Plumbing, electrical and mechanical work
- Grading
- Demolition and moving a building
- Fences at new construction, fences over 6 feet and block, brick or concrete walls
Permit from the City of Exeter
- Fence permits for new or like-for-like replacement fences (Exeter Municipal Code 15.36.030)
- Encroachment permits for work in streets and sidewalks
- Permits to drain or refill a pool
- Site plan review, conditional use permits and variances
Most homeowner projects fall under a combination permit, which bundles the structural and trade work. Work done without a required permit violates City codes: the owner must obtain permits, possibly at double fees, and pass inspection, or return the site to its original condition, and may face fines.
What Exeter decides and what the state holds
The City writes its own building and construction rules in Title 15 of the Exeter Municipal Code, including the fence ordinance, and sets zoning, impact fees and utility connection charges. Tulare County reviews plans and inspects work for the City. Contractor licensing is a state matter; a City business license is required of contractors.
Exeter building department: who handles permitting
Because the city’s growth is modest, Exeter partners with the County of Tulare Building Department for plan check, permitting and inspection. Applications and plans go to the County, which issues the permit once plans are reviewed, approved and paid for. The City handles planning through its contract planning firm, Collins & Schoettler (a 4Creeks company), and handles fence, encroachment and pool drain permits through Public Works.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Tulare County Building Department (building permits, plan check) | 5961 S. Mooney Blvd., Visalia, CA 93277; 559-624-7000 |
| Tulare County inspection scheduling | 559-624-7104 (printed on the inspection card) |
| Exeter City Hall (inspection cards, permits, utilities, finance) | 137 North F Street, Exeter, CA 93221; inspection cards 10:00 a.m. to 2:00 p.m. |
| City Planner (Collins & Schoettler) | 559-802-3052 |
| Exeter Public Works (fence, encroachment, pool drain permits) | 350 W. Firebaugh Avenue, Exeter; (559) 592-3318 |
Land outside the city limits is unincorporated Tulare County, permitted by the same County department; the City also posts an urban development boundary map.
Permit types in Exeter
The City lists five kinds of construction permits issued for Exeter projects: structural, plumbing, mechanical, grading and combination permits, plus permits for demolition and building relocation. Plans stamped “APPROVED” must be followed on site, and any change to them needs the department’s approval.
Residential permits
A homeowner project such as an addition or remodel usually takes a combination permit from Tulare County, with a plot plan showing the improvements and the type of construction. Accessory dwelling units carry an $88 City ADU plan check fee in addition to the County permit. New homes in Exeter also pay City impact fees and water and sewer connection charges, although some residential subdivisions have development agreements that set different fees. For fences, the City permits new and replacement fences at existing properties, while fences at new construction, fences over 6 feet, masonry walls and fences with lighting or automatic gates also need a Tulare County permit.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Where zoning calls for it, commercial and industrial projects go through City site plan review ($1,004 on the schedule) or a conditional use permit ($1,153) before County plan check. Restaurants and other food businesses need a permit from the Tulare County Health Department, and the County Building Department tells applicants about such outside approvals when plans are submitted. Commercial and industrial impact fees are calculated by the City engineer from equivalent dwelling units, and complex projects may be sent to an outside firm for plan review.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning and site plan review. The City’s planning firm administers the zoning ordinance and general plan and processes site plan reviews, use permits, variances, parcel maps and subdivisions; the City’s zoning map was last updated in September 2026. A site plan review package needs the application form, the fee, an environmental description form where staff ask for one, and a PDF and one print of a site plan showing parcel dimensions, buildings and their heights and uses, yards, walls and fences, parking and loading, signs, lighting, street improvements and landscaping with irrigation.
- Street work. Driveway approaches, curb and gutter, sidewalks, sewer, water and storm drain connections and utility work in the right-of-way need a City encroachment permit, with a vicinity map, plans and a traffic control plan where needed; a separate form covers non-digging encroachments. Under Exeter Municipal Code Chapter 12.04, a street cut permit must be obtained at least 24 hours before the cut, excavations may stay open no more than 48 hours without the City engineer’s extension, and street cut permits go only to state-licensed contractors or public utilities.
- Utility connections. Water and sewer connections and meters are bought from the City.
- Fences. A City fence permit application stays valid for six months; a property line in many Exeter neighborhoods runs about 10 feet behind the face of the curb, and the owner is responsible for locating it.
Exeter permit fees
Building permit and plan check fees for Exeter projects are Tulare County’s; the City’s fence handout says Tulare County building permit fees apply, and the County quotes them at 559-624-7000. The City’s own charges come from the City of Exeter Rate and Fee Schedule for fiscal year 2024–2025, adopted June 25, 2024 and effective July 1, 2024, with impact fees effective August 26, 2024. All City fees are paid when the approved permit is picked up.
| Fee | Single family / multi-family / mobile home |
|---|---|
| Public facilities | $1,442 / $481 / $1,384 |
| Parks | $785 / $665 / $751 |
| Landscape median | $519 / $370 / $259 |
| Traffic signal | $414 / $296 / $205 |
| Railroad crossing | $216 / $154 / $106 |
| Bike path | $43 / $30 / $20 |
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Water connection | $414 |
| Water capital: single family / multi-family or mobile home | $6,799 / $3,468 |
| Sewer connection and capital: single family / multi-family or mobile home | $958 / $556 |
| Storm drain fee | $1,110 per acre |
| Water meter, 5/8 inch / 1 inch | $296 / $467 |
| Construction meter deposit | $700 |
| Encroachment permit / annual encroachment permit | $147 / $296 |
| Public Works inspection fee | $118 |
| Engineering plan check and inspection | 4% of site value |
| ADU plan check | $88 |
| Site plan review / with zone change | $1,004 / $1,153 |
| Conditional use permit / zone variance | $1,153 / $768 |
| Minor deviation / lot line adjustment / tentative parcel map | $101 / $650 / $828 |
| Parking in-lieu fee | $1,773 per stall |
Worked example. The City’s per-unit charges for a new single-family home outside a development agreement add up to $3,419 in impact fees ($1,442 + $785 + $519 + $414 + $216 + $43), plus $414 for the water connection, $6,799 in water capital and $958 for sewer connection and capital, or $11,590 before the meter and the County’s building permit fees.
The City’s site plan review application, revised in February 2026, lists $1,072 for site plan review and $1,230 with a zone change, above the FY 2024–2025 schedule’s $1,004 and $1,153; the application is the newer document. The fee schedule lists no charge for a fence permit or pool drain permit, while the fence handout says City permit fees will apply; confirm the amount with Public Works when you file. A City business license costs $60 for businesses grossing under $30,000 a year and $80 above that, plus a one-time $10 application fee and the $4 state CASp fee.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them
Plumbing, electrical and mechanical permits for Exeter work are issued by the Tulare County Building Department, alone or within a combination permit. Changing or extending any of those systems, even adding one outlet, takes a permit.
Contractors must hold a valid City of Exeter business license before City Hall will hand over an inspection card, so license the business with the City before the job reaches its first inspection; a home occupation license is $30. Contractor licensing itself is handled by the state.
Work in the public right-of-way, including utility trenching and driveway approaches, needs a City encroachment permit from Public Works whoever does the work.
How to apply for a building permit in Exeter
Call the City Planner (559-802-3052) about setbacks, uses and whether site plan review or a use permit is needed.
Be ready to submit plans and a plot plan showing the improvements and the type of construction you will use.
Submit the application and plans to the Tulare County Building Department, 5961 S. Mooney Blvd., Visalia (559-624-7000).
The County issues the permit only after the plans are reviewed and approved and fees are paid; simple permits can be issued over the counter.
Bring the signed permit, the permit receipt and any plans to City Hall, 137 North F Street, between 10:00 a.m. and 2:00 p.m.
File encroachment and fence applications with Public Works, 350 W. Firebaugh Avenue, and pay City fees when you pick up the approved permit.
Review, corrections and what causes delay
Permit times vary with complexity: some permits are issued over the counter, more complex projects take longer, the plans examiner may ask for corrected plans, and the most complicated projects may go to an outside plan review contractor. A contractor without a valid City business license cannot collect the inspection card.
Inspections in Exeter
Tulare County inspects Exeter projects. After the County issues the permit, pick up the inspection card at Exeter City Hall (10:00 a.m. to 2:00 p.m.) with the signed permit, receipt and plans, then schedule each inspection with the County at 559-624-7104, the number printed at the bottom of the card. Have your permit information ready when you call.
Work must follow the plans stamped “APPROVED,” and any change to them needs the department’s approval first. Public Works inspects encroachment work in City streets and charges a $118 inspection fee under the City schedule.
Want this handled start to finish?
Get a free quote →Building code in Exeter
Exeter’s building and construction rules are in Title 15 of the Exeter Municipal Code, including the fence ordinance in Chapter 15.36. Flood insurance: FEMA lists the City of Exeter as a participating community in the National Flood Insurance Program, with no special flood hazard area mapped in the city.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Frequently asked questions
Who issues building permits in Exeter?
The Tulare County Building Department, at 5961 S. Mooney Blvd. in Visalia (559-624-7000). The City of Exeter partners with the County for plan check, permitting and inspection.
How do I schedule an inspection for an Exeter project?
Pick up the inspection card at Exeter City Hall, 137 North F Street, between 10:00 a.m. and 2:00 p.m., then call Tulare County at 559-624-7104.
Do I need a permit to replace a fence in Exeter?
Yes. Exeter Municipal Code 15.36.030 requires a City fence permit even for like-for-like replacement. Fences over 6 feet, masonry walls and fences at new construction also need a Tulare County permit.
What City fees apply to a new house?
Under the FY 2024–2025 schedule, $3,419 in impact fees, a $414 water connection, $6,799 in water capital and $958 for sewer connection and capital, unless a subdivision’s development agreement sets different amounts. County building permit fees are extra.
Does a contractor need an Exeter business license?
Yes. City Hall gives out inspection cards only to contractors with a valid City business license, which costs $60 or $80 a year depending on gross receipts.
What happens if I build without a permit?
You violate City codes and can be fined, and you must obtain permits, possibly at double fees, and pass inspection, or restore the site to its original condition.
Can a homeowner cut into an Exeter street or sidewalk?
Not under a street cut permit: Chapter 12.04 of the Municipal Code issues those only to state-licensed contractors and public utilities. Driveway approaches, sidewalk and connection work in the right-of-way need a City encroachment permit from Public Works, (559) 592-3318.
Who handles planning in Exeter?
The City contracts with Collins & Schoettler (a 4Creeks company). The Planning page gives 559-802-3052 for the City Planner, and the site plan review packet lists the Planning Department at 559-592-9244.
Inspections are where schedules slip.
Get a free quote →Exeter permit search and official resources
Ask the Tulare County Building Department at 559-624-7000 about the status or history of a building permit on an Exeter property
- City of Exeter building permit FAQs
- Planning and Development: applications, fees and maps
- City of Exeter Rate and Fee Schedule FY 2024–2025 (PDF)
- City permit applications
- Fence permit application and rules (PDF)
- Encroachment permit application (PDF)
- Site plan review application (PDF)
- Exeter Code of Ordinances
Simplify Exeter permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Exeter sooner?
Let Alliance prepare, file, and track your Exeter permits while your crew stays on the job.
More California permitting guides
Tulare County
Read guide →Farmersville
Read guide →Lindsay
Read guide →Fairfield Building Permit Guide
Read guide →Fillmore Building Permit Guide
Read guide →Folsom Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Exeter permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.