Inside Lindsay, building permits are issued by the City’s City Services Department, which handles residential, commercial and industrial plan review, permits and inspections from 150 North Mirage Avenue (559-562-7102 ext. 4). Under the City’s fiscal year 2026–2027 fee schedule, a project valued at $100,000 pays a $1,897.35 building permit fee plus a $1,232.49 plan check fee, and many common jobs, from water heaters to reroofs, carry flat fees.
What requires a building permit in Lindsay?
Lindsay’s fee schedule shows the range of work the City permits. New buildings and additions are priced on project valuation, and a long list of everyday jobs has a flat permit fee, so many replacement jobs, such as water heaters, windows and reroofs, need a City permit. Doing work without a permit doubles the permit fees in each category that applies.
Flat-fee permits listed by the City
- HVAC units, wall furnaces, evaporative coolers and water heaters
- Reroofing, window replacement and residential stucco
- Fences: wood, vinyl, wrought iron and chain link, and residential masonry (CMU) fences
- Patios and carports, swimming pools and water softeners
- Tubs and showers, building sewers and septic tank or well abandonment
- Demolition, 400-amp electrical services, temporary power and signs
Valuation-based and other permits
- New buildings, additions and remodels (valuation table)
- Solar photovoltaic systems (per kilowatt)
- Landscape irrigation under the water efficient landscape ordinance
- Fire sprinkler and hood suppression systems
- Grading (per cubic yard) and right-of-way excavation
The application form also reminds owners of two City ordinances: owners of land next to a public sidewalk must keep the sidewalk safe (Ordinance 538, section 12.30), and trees and shrubs along streets must be trimmed to clear 8½ feet above the curb and 7 feet above the sidewalk (section 12.20.010).
What Lindsay decides and what the state holds
The City sets its permit fees, its construction and demolition debris recycling rules (Chapter 8.32, Ordinance 517), zoning and development standards, and the acreage, parkland and general plan fees charged with building permits. City Services works with the Planning and Economic Development department so that projects meet City ordinances and the building codes the City has adopted. Contractor licensing is a state function.
Lindsay building department: who handles permitting
The City Services Department handles building and construction oversight in Lindsay: residential, commercial and industrial plan review, the permit process and inspections, along with streets, engineering, water, wastewater and storm drain utilities. Planning applications are taken at the same office, and the Finance Department collects building permit fees with City Services. Outside the city limits, unincorporated land is permitted by Tulare County.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| City Services Department (building permits, plan check, inspections) | 150 North Mirage Avenue, P.O. Box 369, Lindsay, CA 93247; 559-562-7102 ext. 4; fax 559-562-5748; 8:00 a.m. to 4:30 p.m. |
| Planning (planning applications) | 150 North Mirage Avenue; 559-562-7102 ext. 4 |
| City Hall (Finance, business licenses) | 251 E. Honolulu Street, Lindsay, CA 93247; 559-562-7102 |
Because one department covers building, engineering and the City’s utilities, encroachment, grading, sewer and water acreage fees are assessed by the same office that issues the building permit.
Permit types in Lindsay
The City’s quick forms include the building permit application (an “Application for Permit/Plan Check”), the construction and demolition debris form, the solar plan submittal checklist, the planning project application, sign permits, the home occupation application and the business license application. Signing the building application makes the applicant responsible for all permit and plan check fees.
Residential permits
Home projects are priced either on the valuation table or by flat fee: a residential reroof is $392, a window replacement $329, a water heater or HVAC unit $349, a patio or carport $590 ($43 more with electrical) and a wood, vinyl, wrought iron or chain link fence $175. A residential solar system of up to 15 kilowatts is $450, plus $15 for each added kilowatt. Solar submittals need three plan sets and, when the existing service panel is used, photos of the panel with and without its dead-front cover, the panel door label showing the maximum bus rating, the main breaker and the roof framing; installations on rafters need engineering calculations, while engineered trusses do not. The checklist warns that incomplete solar submittals are rejected. Running a business from home takes a $117 home occupation permit and a City business license.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial work follows the same valuation table, with commercial flat fees such as a $610 commercial reroof, $479 for a commercial fire sprinkler or hood suppression system and $87 per room for commercial electrical. Commercial solar is $1,000 for systems up to 50 kilowatts, $7 per kilowatt from 51 to 250 kilowatts and $5 per kilowatt above that. New development pays storm drain acreage fees by zone, from $950 per acre for industrial land to $1,090 for commercial land, plus water ($400) and sewer ($300) acreage fees per acre; residential storm drain acreage fees are $550 in the R-1-7 zone, $650 in RM-3 and $800 in RM-1.5.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning approvals. The building application asks whether site plan review applies; site plan review is a $2,906 deposit, a conditional use permit or variance a $2,425 deposit and a preliminary plan review a $1,004 deposit. Incomplete planning applications are returned.
- Debris recycling. The City’s construction and demolition form, which lists construction, demolition, grading, renovation, remodel and addition projects, collects a recycling and reuse pre-plan under Ordinance 517 and requires a permitted hauler; the Building Official may withhold approval of plans until any penalty is paid.
- Street work. Excavation or encroachment in the right-of-way is a $393 permit that includes two inspections, with a $105 encroachment plan check; a portable storage container in the street needs a $333 encroachment permit for up to 30 days.
- Grading and engineering. Grading plan check is a $726 deposit, grading permits $0.20 per cubic yard, and engineering plan check and inspection of public improvements 6% of the engineer’s estimate.
Lindsay permit fees
The City’s Fee Schedule for Fiscal Year 2026–2027 sets building, planning and engineering fees. The building permit fee for valuation-based work comes from the schedule’s table (Attachment A), with a plan check fee equal to 65% of the building permit fee; electrical, plumbing and mechanical permits refer to Attachment A for their base permit fee and add the unit fees below. Refunds are limited to 70% of the fee.
| Project valuation | Building permit fee + plan check fee |
|---|---|
| $99,001 to $100,000 | $1,897.35 + $1,232.49 |
| $100,001 to $101,000 | $1,911.62 + $1,241.76 |
| $124,001 to $125,000 | $2,253.90 + $1,464.06 |
| $149,001 to $150,000 | $2,610.45 + $1,695.64 |
Worked example. A $100,000 project pays $1,897.35 for the building permit and $1,232.49 for plan check, or $3,129.84. The general plan update fee of 8% of the building permit fee adds $151.79, for $3,281.63 before trade unit fees and any acreage or parkland fees.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Re-inspection | $130 |
| Demolition / temporary power / 400-amp electrical service | $305 each |
| Electric meter up to 200 amps | $305 |
| Electrical, per room with receptacles: residential / commercial | $43 / $87 |
| Plumbing: water heater or vent / gas piping, first five outlets | $131 / $131, plus $43 per added outlet |
| Plumbing: water piping / building sewer / room with fixtures / grease trap | $87 / $43 / $43 / $130 |
| Mechanical: wall furnace or HVAC / fan / duct / hood | $130 / $43 / $43 / $43 |
| Swimming pool, above-ground or in-ground | $697 |
| Signs without / with electrical | $460 / $590 |
| Residential fire sprinkler system | $218 |
| Backflow preventer, residential or commercial | $175 |
| Landscape irrigation (water efficient landscape ordinance), under / over 2,500 sq ft | $305 / $392 |
| Parkland fee | $650 per house |
| Home occupation permit / sign review | $117 / $155 |
| Lot line adjustment | $2,835 deposit |
| Application | Fee |
|---|---|
| Preliminary plan review | $1,004 deposit |
| Site plan review | $2,906 deposit |
| Conditional use permit or variance | $2,425 deposit |
| Zone change or general plan amendment | $5,331 deposit |
| Tentative parcel map / tentative subdivision map | $5,239 / $8,148 deposit |
| Categorical exemption (CEQA notice of exemption) | $408 |
| Negative declaration or mitigated negative declaration review | $1,000 deposit |
| Will serve analysis | $5,000 deposit |
| Planning appeal | $769 deposit |
A permit for work done without one costs double in every fee category that applies. The schedule notes that its photovoltaic fees follow a state law limit that was to remain in effect until January 1, 2025, and still lists those amounts.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them
City Services issues electrical, plumbing and mechanical permits as well as building permits. Each has a base permit fee (the schedule points to Attachment A) plus unit fees: $43 per residential room with outlets, $131 for a water heater and vent, $130 for a wall furnace or HVAC unit, and $305 for a new meter of up to 200 amps. Fire sprinkler systems, backflow preventers and landscape irrigation under the water efficient landscape ordinance are permitted on the plumbing side.
Businesses in Lindsay need a City business license from the Finance Department: a one-time $73 application fee and a $4 state CASp fee at every renewal, with quarterly license fees by class, for example $1.25 per $1,000 of gross receipts for professional licenses (minimum $10, maximum $30 a quarter) and $1.00 per $1,000 for service licenses (minimum $10, maximum $50). Contractor licensing is handled by the state.
How to apply for a building permit in Lindsay
Ask City Services and Planning, 150 North Mirage Avenue, whether the project needs site plan review or another planning approval.
Fill out the Application for Permit/Plan Check with the project address, parcel number, description and valuation.
Solar projects attach the solar checklist with three plan sets and photos; construction, demolition and remodel projects add the C&D debris recycling pre-plan.
File at the City Services counter (559-562-7102 ext. 4) between 8:00 a.m. and 4:30 p.m.
Respond to plan check comments and pay the permit, plan check and general plan update fees.
City Services inspects the work; contact the office at ext. 4 as each stage is ready.
Review, corrections and what causes delay
The City warns that incomplete plans delay plan check, and its solar checklist states that incomplete solar submittals are rejected. The solar checklist also requires plans signed by the person who prepared them. Projects needing site plan review, a use permit or a variance go through Planning as well, and the Building Official may withhold approval of plans from anyone with an unpaid debris recycling penalty.
Inspections in Lindsay
City Services performs building, electrical, plumbing and mechanical inspections inside the city; its office line is 559-562-7102 ext. 4. Each re-inspection costs $130. Right-of-way excavation and encroachment permits include two inspections in the $393 fee, and grading inspection starts at a $193 minimum for one to four residential units.
Want this handled start to finish?
Get a free quote →For construction and demolition projects, the debris recycling pre-plan names the haulers and the recycling or reuse rate for each material, and the City can place an unpaid debris penalty as a lien on the property. A compliance review costs $117.
Building code in Lindsay
Lindsay’s City Services Department enforces the building codes the City has adopted, together with City ordinances such as the construction and demolition debris rules in Chapter 8.32. Flood insurance: FEMA lists the City of Lindsay as a participating community in the National Flood Insurance Program, with a current flood map dated June 16, 2009.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Frequently asked questions
Who issues building permits in Lindsay?
The City Services Department, 150 North Mirage Avenue (559-562-7102 ext. 4), which handles plan review, permits and inspections inside the city.
How much is a building permit in Lindsay?
For a $100,000 project, the building permit fee is $1,897.35 and plan check $1,232.49 under the FY 2026–2027 schedule, plus an 8% general plan update fee on the permit fee. Many small jobs have flat fees.
Do I need a permit to replace a water heater or roof?
Yes. The City lists a $349 flat permit for a water heater, $392 for a residential reroof and $610 for a commercial reroof.
Do I need a permit for a fence in Lindsay?
The fee schedule lists a $175 permit to install or replace a wood, vinyl, wrought iron or chain link fence and $392 for a residential masonry fence.
What do I need to submit for a solar permit?
The application, three plan sets and, when the existing panel is used, photos of the panel, its bus rating label, the main breaker and the roof framing. Incomplete solar submittals are rejected.
How much does site plan review cost in Lindsay?
Site plan review takes a $2,906 deposit, and a preliminary plan review a $1,004 deposit, under the FY 2026–2027 schedule. Planning applications are filed at 150 North Mirage Avenue.
What happens if I build without a permit?
The permit fees double in each category that applies, and a $130 re-inspection fee is charged whenever work has to be inspected again.
Is there a recycling requirement for construction debris?
Yes. Projects covered by Ordinance 517 (Chapter 8.32) file a debris recycling and reuse pre-plan with City Services on the City’s construction and demolition form and must use a permitted hauler.
Inspections are where schedules slip.
Get a free quote →Lindsay permit search and official resources
For the history of permits on a Lindsay property, contact the City Services Department, which processes the City’s building permits.
- City Services & Planning
- Planning Department
- Quick forms: building, planning and business applications
- Building permit application (PDF)
- Solar plan submittal checklist (PDF)
- Construction and demolition debris form (PDF)
- Planning project application (PDF)
- Fee Schedule Fiscal Year 2026–2027 (PDF)
- Business license application (PDF)
Simplify Lindsay permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Lindsay sooner?
Let Alliance prepare, file, and track your Lindsay permits while your crew stays on the job.
More California permitting guides
Tulare County
Read guide →Porterville
Read guide →Tulare
Read guide →Livermore Building Permit Guide
Read guide →Livingston Building Permit Guide
Read guide →Lodi Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Lindsay permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.