Building permits in the City of El Segundo are issued by the Building and Safety Division of the Community Development Department, City Hall, 350 Main Street (310-524-2380, permits@elsegundo.org). Applications, plans and documents must be filed electronically in the city’s E-Z Permit Hub, which also handles fee payments, reviews, permit issuance and inspection requests. Regular plan check takes one to four weeks from payment of the plan review fees, and an accelerated plan check aims for 7 working days.
What requires a building permit in El Segundo?
El Segundo requires a building permit for any construction, improvement, repair, alteration or demolition project. The city’s own list spells out these items:
Building permit needed
- Solar panels, EV chargers and energy storage systems
- Pools and spas
- Sandblasting and most excavation
- Temporary structures, including temporary power poles
- Re-roofing
- Plumbing, mechanical and electrical improvements
Separate permits that may apply
- Electrical, mechanical and plumbing
- Fences and retaining walls not part of a building
- Grading and demolition
- Pools, spas and other site improvements
- Driveway aprons and street use
- Public Works permit for sidewalk, alley or street work
The division publishes a Building Permit Exemptions handout listing work that needs no permit, an Express Permits handout for simple jobs, and a Home Owners Guide. Signs, fences, retaining walls, shoring and pools or spas are “miscellaneous permits” that need plans approved before the permit is issued.
What El Segundo decides and what the state holds
The city sets its own permit process and submittal rules, allowable construction hours (Monday to Saturday, 7 a.m. to 6 p.m., with no work on Sundays or legal holidays), the business license rule for every contractor and subcontractor, and its own requirements such as the ADU security code instructions and a waste reduction and recycling plan. Plan check here also covers fire safety. The building code and contractor licensing come from the state.
El Segundo building department: who handles permitting
The City of El Segundo Building and Safety Division issues building and trade permits for all property in the city. Its plan check engineers review structural, architectural, grading and fire safety elements of each project, and its inspectors confirm that work matches the permit, local codes and approved plans. Plans are routed at the same time to every other city department that must review them. The division’s Code Enforcement section enforces the Municipal Code, including zoning and land use, property maintenance and building standards.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | City Hall, Development Services, 350 Main Street, El Segundo, CA 90245 |
| Hours | Monday to Thursday 7 a.m. to 5 p.m.; Friday 7 a.m. to 4 p.m. |
| Building questions | 310-524-2380; permits@elsegundo.org |
| Inspection request line | 310-524-2379 |
| Planning Division | 310-524-2344; planning@elsegundo.org |
| Public Works Engineering | 310-524-2360 |
| Fire Marshal | 310-524-2239 |
| Code enforcement (Neighborhood Preservation) | 310-524-2387 |
| Business tax registration | 310-524-2317; taxinquiries@elsegundo.org |
| Portal | El Segundo E-Z Permit Hub |
El Segundo permit types
The E-Z Permit Hub is the single place for building permit applications, plan submittals, payments, reviews, issuance and inspection requests, and it has its own category for EV charger permits. The division’s handouts include packets for a new single-family building, a new commercial building, a change of use and a change of use to a food establishment, plus a smoke alarm self-certification form and a request form to modify or extend a permit.
Residential permits
- New homes, multi-family buildings, additions to multi-family residences and ADUs follow the city’s minimum plan submittal requirements: a fully dimensioned site plan, floor plans for every affected story, elevations and sections, structural plans and calculations where the design departs from conventional construction, an energy certificate of compliance, and a soils report where the plan check engineers ask for one.
- Additions and remodels to single-family and multi-family dwellings have their own submittal sheet and residential addition plan requirements.
- ADUs must also follow the city’s ADU security code requirements, published with instructions and illustrations.
- Block walls follow the city’s block wall requirements handout, and fences and retaining walls need plans before the permit is issued.
- Rooftop solar has an automated residential solar permitting page.
The site plan must show every property line, easement and setback (existing and proposed), architectural projections such as eaves, balconies and bay windows, landscaping, floor area ratio and lot coverage in square feet and as a percentage, a north arrow and adjacent street names, grade elevations at property corners, driveways and the garage floor, utility meters, sewer connections and fire hydrants, and any building on the next lot within 10 feet of the line. The general notes give the applicable codes, occupancy and construction type, building height, fire sprinklers, fire and seismic zones, the assessor’s parcel number and the legal description.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial and industrial projects, including new buildings, food establishments (with their own document submittal list), additions, tenant improvements and changes of use, follow the commercial submittal requirements: a site plan with parking tabulation, disabled access details for parking, paths of travel, entrances and restrooms, an allowable area analysis for new buildings, and building material specifications. Plans must be approved before mechanical permits for smoke control, compressors using Group B refrigerants, commercial cooking hoods, engineered water heater vents or systems of 500,000 BTU per hour and over, and before electrical permits for theaters, assembly rooms for more than 200 people, health care facilities, new buildings or additions over 30,000 square feet, work over 600 volts or 600 amperes, hazardous locations and emergency systems.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning: zoning review uses the Planning Division’s own applications, guides and forms.
- Public Works: work on a sidewalk, alley or street needs a separate Public Works permit.
- Shoring: plans and calculations may be required for excavations deeper than four feet or any that remove support from a building, a neighbor or the public right of way.
- Grading: plans must be approved before permits for slope or landslide repairs, tract or mass grading, site preparation, removal and re-compaction for building pads, hillside basement or pool excavations, and retaining wall cuts and backfill; the division follows a written geotechnical reports policy.
- Utilities: a new, relocated or upgraded electric service needs the utility’s approval of the meter location.
- Stormwater and landscaping: NPDES best management practices go on the construction documents, and new construction may need a licensed landscape and irrigation plan.
El Segundo building permit fees
El Segundo’s Building and Safety pages do not post a building fee schedule. Fees are assessed project by project: once staff receive an application in the E-Z Permit Hub, they create a plan check number and email an invoice for the plan check fees, and the clock for plan review starts only when those fees are paid. Permit fees are paid in the portal before the permit is issued. For a fee estimate, call the division at 310-524-2380 or email permits@elsegundo.org.
One other city requirement carries its own charge: every contractor and subcontractor must hold a current El Segundo business license through the city’s business tax registration (310-524-2317), and the division asks to see it before issuing a permit to a contractor.
Rather talk it over?
Call 1-855-478-4290 →Trade permits and who may pull them in El Segundo
Electrical, mechanical and plumbing permits are separate permits. Plumbing plans must be approved before a permit for drainage systems, combination waste and vent systems, fuel gas, potable water and reclaimed water piping, larger rainwater systems, subsurface drainage, hillside slope irrigation and pool circulation systems, and the division asks applicants to complete its Plumbing, Mechanical and Electrical Plan Check Questionnaire.
Three kinds of applicant can pull a permit in El Segundo: a residential property owner, a California licensed contractor, or an agent for either with proper authorization. A residential tenant cannot pull a permit unless authorized as the owner’s or contractor’s agent.
- Owners bring photo identification and, after a recent transfer, proof of ownership such as a grant deed or escrow closing statement; trusts, corporations, LLCs and partnerships add the papers naming the authorized signer, and condominium common-area work needs a letter from the HOA president with proof of the position.
- Owners’ agents complete the authorization at the bottom of the Notice to Property Owner form with the owner’s notarized signature, and show identification matching the form.
- Contractors show photo identification, a current City of El Segundo business license, the state contractor’s license pocket card and proof of workers’ compensation insurance.
- Contractors’ agents bring a letter on the contractor’s letterhead authorizing a named person, not a business, plus matching identification.
How to apply for an El Segundo building permit
Property owners and contractors create an account in the city’s online portal.
Follow the minimum plan check submittal checklist and the questionnaire; partially completed plans are not accepted.
Submit the application, plans and documents as PDF or JPG files only.
Staff assign a plan check number and email an invoice; review begins once it is paid.
Plans are routed at the same time to every department involved; contact each reviewer through its step in the record.
After approval, pay the permit fees and print the approved, stamped plans, the signed permit card and the inspection cards for the job site.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
Accelerated plan check aims to finish within 7 working days of paying the plan review fees; regular plan check takes one to four weeks depending on scope. Partially completed plans are not accepted. Plans must be legible, fully dimensioned and drawn to at least 1/8-inch scale, signed by the person who prepared them, and wet-stamped by a California architect or engineer when required, without general notes that do not apply to the project. The plan check page still lists paper set counts (three complete sets plus an architectural set for the County Assessor), but the apply page now requires every submittal to be uploaded to the E-Z Permit Hub.
El Segundo building inspections
Work must be inspected before it is covered or concealed, and nothing is approved until inspection staff accept it. Inspections run Monday to Friday except holidays, from 8 a.m. to 4 p.m. Monday through Thursday and until 3 p.m. on Friday (the inspections page says field inspections run weekdays until 4 p.m.). To book, cancel or change an inspection, use the project record in the E-Z Permit Hub or call the inspection line at 310-524-2379; requests made by 11:59 p.m. are scheduled for the next business day, and there are no same-day inspections. Weekend calls go on the next business day’s schedule. Inspections can also be booked in person at the counter. Final inspections are requested the same way; say clearly that it is a “Final Inspection”.
Inspectors are available to the public at City Hall from 7 to 7:30 a.m. on weekdays. A permit is valid for 180 days after issuance, and the period restarts after every inspection. If a permit expires, the city may issue a one-time extension: come to City Hall to speak with the inspectors and the Building Official. A certificate of occupancy is needed to occupy a property; a temporary certificate, possible at some stages of construction, carries conditions that must be met before the final one is issued.
California building code in El Segundo
The division’s Codes and Regulations page and its 2025 Code Adoption handout describe the codes the city enforces, and its handout list includes El Segundo’s own CalGreen checklists for new homes and for residential additions and alterations. FEMA’s Community Status Book lists the City of El Segundo (community 060118) as participating in the National Flood Insurance Program, with a current flood map dated April 21, 2021.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →El Segundo permit search and official resources
Applicants follow their own records in the E-Z Permit Hub. The division also links a plan check status lookup, a list of the day’s scheduled inspections, and a public archive of building permit records in the city’s online document library (WebLink); other records go through the city’s Request a Record page.
- El Segundo Building and Safety Division
- Apply for a building permit
- E-Z Permit Hub
- Building inspections
- Building and Safety handouts and forms
- Building permit exemptions
- Who can pull a permit
- Minimum plan check submittal checklist
- Plumbing, mechanical and electrical plan check questionnaire
- 2025 code adoption handout
- Plan check status lookup
- Building permit records archive
- Automated residential solar permitting
- Planning applications, guides and forms
- Business tax registration
- City contact list
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →El Segundo building permit FAQs
How do I apply for a building permit in El Segundo?
Online, through the E-Z Permit Hub; applications, plans and documents must be uploaded as PDF or JPG files.
How long does plan check take?
One to four weeks for regular plan check, or about 7 working days for accelerated plan check, counted from payment of the plan review fees.
Can a tenant pull a permit?
Only as an authorized agent: with the owner’s notarized authorization, or with a letter from the contractor naming the tenant.
Do contractors need an El Segundo business license?
Yes. Contractors and subcontractors must keep a valid city business license while working, and show it to get a permit.
How do I schedule an inspection?
In the E-Z Permit Hub or by calling 310-524-2379 by 11:59 p.m. for the next business day.
How long is a permit valid?
180 days after issuance, restarting with every inspection; one extension may be granted.
When can construction take place?
Monday to Saturday, 7 a.m. to 6 p.m.; no work on Sundays or legal holidays.
Do I need a permit for re-roofing or a pool?
Yes. The city lists re-roofing, pools and spas among the projects that need a building permit.
Simplify El Segundo permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in El Segundo sooner?
Let Alliance prepare, file, and track your El Segundo permits while your crew stays on the job.
More California permitting guides
Los Angeles County
Read guide →Gardena
Read guide →Glendora
Read guide →Elk Grove Building Permit Guide
Read guide →Emeryville Building Permit Guide
Read guide →Encinitas Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about El Segundo permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.