Delano, California Building Permit Guide

To get a building permit in Delano, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Delano’s Building Division, part of the Community Development Department at City Hall, 1015 11th Avenue, issues building permits inside city limits from a complete application package that can be emailed to BuildingPermits@CityofDelano.org.

Authority: Delano Community Development, Building DivisionImpact fees: Resolution 2013-59Phone: (661) 721-3340
Authority
City Building Division1015 11th Avenue, Delano
Impact fees
$26,003.65Single-family home, 2026 schedule
Engineering permits
SmartGov portalEncroachment and grading
Hours
Mon–Fri 8–5(661) 721-3340

Inside the City of Delano, building permits are issued by the Building Division of the Community Development Department, 1015 11th Avenue (661-721-3340, weekdays 8 a.m. to 5 p.m.), led by Interim Community Development Director Roman Dowling. Applications must arrive complete, with plans in PDF form, or they will not be accepted. Engineering permits such as encroachments and grading go through the city’s SmartGov portal. A new single-family home pays $26,003.65 in city impact fees under the 2026 impact fee schedule. Unincorporated land around Delano is permitted by Kern County.

What requires a building permit in Delano?

Delano’s Building Division regulates the design, construction, materials, use, occupancy and location of structures in the city. Its permit submittal checklist shows what a typical job involves, and its separate forms cover smoke and carbon monoxide alarms, water-conserving fixtures and EV chargers.

Common building permits

  • New homes, commercial buildings and multifamily projects
  • Additions and alterations, which add the smoke and CO alarm self-verification and the SB 407 water-conserving fixture retrofit form
  • Accessory dwelling units, including Kern County’s pre-approved plans
  • Electric vehicle chargers, residential and non-residential, with the city’s EVSE checklist

Trade work

  • Electrical, with load calculations showing the panel can carry new loads on additions
  • Plumbing: gas line sizing for houses; a full plumbing plan once a project has four or more water closets
  • Mechanical: register locations and energy compliance for houses
  • Underground feeders for every new project or addition valued over $14,000

What Delano decides and what the state holds

The city adds its own requirements to the state code: by city ordinance, all new projects and additions valued over $14,000 must be served by underground electrical feeders, and commercial and multifamily alterations must include the city’s “Summary of Accessible Upgrades.” Delano sets its own impact fees (Resolution 2013-59), planning fees and business license rules, runs its own zoning ordinance and general plan, and requires a city waste management plan with building applications. The Building Division works with the Kern County Fire Department and county Environmental Health, and the submittal checklist says every applicable city and Kern County department requirement must be met.

Short on time to read all of this?

Get a free quote →

Delano building department: who handles permitting

The city issues its own building permits. Community Development has two divisions, Planning and Building, and works with the Engineering Department on right-of-way and land division matters. Engineering handles encroachment and grading permits through SmartGov. Parcels outside the city limits are permitted by Kern County. The application’s office-use section records a CSLB verification of the contractor’s license and the contractor’s city business license number.

Delano permit contacts
OfficeDetails
Community Development (Building and Planning)1015 11th Avenue, Delano; (661) 721-3340 (the 2021 application lists 721-3360); fax (661) 721-2135; BuildingPermits@CityofDelano.org
Department headRoman Dowling, Interim Community Development Director
HoursMonday to Friday, 8 a.m. to 5 p.m.
Engineering1015 11th Avenue, 2nd floor; (661) 721-3380; City Engineer Brandon Rodriguez, PE
Business licensesFinance, (661) 721-3310

Delano permit types

One Building Permit Application (revised June 2021) is used for most work. It requires the valuation, square footage, construction type and occupancy, the owner’s details, the contractor’s license number, type and expiration, the workers’ compensation carrier and policy, and the architect or engineer’s license. The two-page “Required Documents for Permit Applications” checklist must be signed by the applicant and the property owner.

Residential permits

  • New homes and additions: site plan with property lines, structures and distances, dimensioned floor plan, sections in each direction, all elevations, foundation, shear-wall bracing, roof and floor framing, structural details, and two sets of structural, truss and Title 24 energy calculations (performance calculations need registration information and a watermark).
  • Additions and alterations: also attach the smoke and carbon monoxide alarm self-verification and the SB 407 water-conserving fixture retrofit verification.
  • ADUs: Delano accepts the ADU plans pre-approved by Kern County Public Works; you still submit a building permit application and site plan, so permits are not issued the same day. Designers can submit their own plan for pre-approval with a Master Plan application to BuildingPermits@CityofDelano.org.
  • EV chargers: submit the city’s EVSE permitting checklist with the building permit application.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial, apartment and other multifamily plans must show compliance with access regulations, and alterations and additions must include the city’s Summary of Accessible Upgrades. Plans must be stamped by a California-licensed architect or engineer where the building code or state law requires it, and a geotechnical report is added when required. The checklist adds that Kern County Fire and Environmental Health requirements must be met where they apply.

What comes before the building permit

  • Planning. The city asks applicants to contact the Planning Division before filing any planning application. Site plan review, conditional use permits, variances, home occupations, sign permits and temporary land use permits all use the Master Planning Application Form; two or more entitlements are processed together as a Combined Development Project with a $5,000 initial deposit.
  • Engineering. Encroachment and grading permits are applied for and tracked on the SmartGov public portal.
  • Owner authorization. If you are not the owner, a letter of authorization from the owner is required; plans are not accepted without it.

Delano permit costs and fees

Delano does not post its building permit and plan check fee schedule on the Building pages; the charge is based on the valuation and project details entered on the application, so ask Community Development at (661) 721-3340 for the figure. The city’s development impact fees are posted in the 2026 Impact Fee Schedule, which carries the rates set by Resolution 2013-59 (effective December 20, 2013).

Delano impact fees per single-family home (2026 schedule)
ItemFee
Water$3,301.65
Sewer$7,423.46
Circulation (Resolutions 2013-59 and 2013-60)$6,365.86
Storm drainage$1,583.31
Police facilities$617.38
Fire facilities$979.53
Park development (projects under 80 units)$2,973.55
Park acquisition (projects under 80 units)$1,358.98
Government facilities$1,399.93
Total for one single-family home$26,003.65

Rather talk it over?

Call 1-855-478-4290 →

The total is the sum of the nine single-family rates on the schedule. In projects of 80 or more units, park development drops to $2,004.80 and park acquisition to $543.59 per home. A multifamily unit at under 15 units per acre pays $1,683.84 for water and $4,305.61 for sewer, and commercial uses are charged per 1,000 square feet or per acre; general retail, for example, pays $792.39 for water and $2,746.68 for sewer per 1,000 square feet. The planning fee sheet the city still posts is dated for 2010; it lists a general plan maintenance fee of $103 per new dwelling unit (not charged on remodels or trade permits for existing buildings), so confirm current planning charges with the Planning Division.

Trade permits and who may pull them

Electrical, plumbing and mechanical work is shown on the plans submitted with the building permit application. For a house, the plumbing plan may simply be gas line sizing unless there are four or more water closets, and the plumbing and mechanical plans may be combined with the electrical plan. Additions must show through load calculations that the existing panel can handle the new loads, and new work over $14,000 needs underground feeders.

  • Contractors: the application records the contractor’s state license number, type and expiration, and the office records a CSLB verification. A CSLB license is required for jobs of $1,000 or more in labor and materials, or any smaller job that needs a permit.
  • City business license: required of every business in the city, including contractors whose offices are outside Delano. Licenses run for the calendar year, to December 31, and every license and renewal carries the $4 state SB 1186 fee.
  • Owner-builders and agents: an applicant who is not the property owner must include the owner’s letter of authorization, and the owner signs the submittal checklist.
  • Workers’ compensation: carrier, policy number and expiration are required on the application.

Rather not deal with the building department?

Get a free quote →

How to apply for a Delano building permit

1. Confirm the parcel is in the city

Check the city maps and GIS pages; unincorporated parcels go to Kern County.

2. Talk to Planning first

Call (661) 721-3340 to see whether a site plan review or other entitlement is needed.

3. Complete the checklist

Work through the Required Documents checklist and gather every item that applies, including the waste management plan.

4. Prepare electronic plans

Provide plans in PDF form (the checklist mentions a CD or flash drive) drawn to scale, stamped where required.

5. Submit the package

File the signed application and checklist at 1015 11th Avenue or email it to BuildingPermits@CityofDelano.org.

6. Clear county and engineering items

Meet Kern County Fire and Environmental Health requirements and get any encroachment or grading permit through SmartGov.

Review, corrections and what causes delay

The checklist is strict: if any applicable document is missing, the application is not accepted. Every document must be resubmitted for each re-review, so keep a complete electronic set. Items the checklist singles out include the owner authorization, Title 24 performance calculations with registration information and watermark, load calculations for an addition, and county Fire and Environmental Health requirements. For pre-approved ADU plans, the city says permits are not issued on the same day as submitted, because the application and site plan still have to be reviewed.

Inspections and certificates in Delano

Delano’s Building pages do not set out an inspection booking procedure, so call Community Development at (661) 721-3340 to arrange building inspections. Engineering permits issued through SmartGov can be followed in the portal, where applicants view their applications and inspection results.

For additions and alterations, the owner or contractor signs the city’s smoke and carbon monoxide alarm self-verification form as part of the permit package, and the SB 407 form verifies that non-compliant plumbing fixtures are being replaced with water-conserving ones. The approved electronic plan set, including any structural and truss calculations, is the set the work is built and checked against, and each re-review requires resubmitting all documents.

California building code in Delano

Delano applies the state code to permits in the city, with its own underground feeder ordinance and accessibility summary requirement. FEMA’s Community Status Book lists the City of Delano (community 060078) as participating in the National Flood Insurance Program, with flood maps first issued September 26, 2008 that show no special flood hazard area in the city.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Delano building permit FAQs

Can I email my building permit application in Delano?

Yes. The application lists BuildingPermits@CityofDelano.org, and plans must be provided in electronic format.

What are the impact fees for a new house?

$26,003.65 for one single-family home under the 2026 schedule, covering water, sewer, circulation, storm drainage, police, fire, parks and government facilities.

Does Delano accept pre-approved ADU plans?

Yes. It accepts Kern County Public Works’ pre-approved ADU plans, with a building permit application and site plan.

Do contractors need a Delano business license?

Yes, including contractors whose offices are outside the city; licenses run for the calendar year.

When do I need underground electrical feeders?

For any new project or addition valued over $14,000, under city ordinance.

What happens if my application is missing a document?

It will not be accepted; all applicable documents on the checklist must be included.

Who issues encroachment and grading permits?

The Engineering Department, through the SmartGov public portal.

Is Delano in a mapped flood zone?

FEMA lists Delano as participating in the flood insurance program with no special flood hazard area mapped.

Delano permit search and official resources

For engineering permits, the SmartGov public portal lets applicants view their applications and inspection results and see public notices. For building permit records, contact Community Development at (661) 721-3340 or BuildingPermits@CityofDelano.org with the address or APN.

Inspections are where schedules slip.

Get a free quote →

Simplify Delano permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Delano sooner?

Let Alliance prepare, file, and track your Delano permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Delano permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.