Skip to main content
Municipal GuideCaliforniaCulver City · Los Angeles County

Culver City, California Building Permit Guide

To get a building permit in Culver City, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Culver City’s Building Safety Division at City Hall, 9770 Culver Boulevard, issues building, electrical, mechanical and plumbing permits through the city’s online permit portal or its second-floor counter.

Authority: Culver City Building Safety DivisionPhone: (310) 253-5800Fees: FY 2026-27 schedule
Authority
City Building Safety9770 Culver Blvd, second floor
Apply
Online permit portalOne application per structure and trade
Plan check
About 20 business daysPer round; 10 for qualified expedited
Inspections
Request by emailIn person or by video call

In Culver City, building permits are issued by the Building Safety Division of the Planning and Development Department at City Hall, 9770 Culver Boulevard ((310) 253-5800), where Tim Koutsouros is the Building Official. Applications go in through the city’s online permit portal, one for each structure and each trade, or at the counter. Fees come from the FY 2026-27 comprehensive fee schedule, in effect since July 1, 2026; on a $200,000 job the building permit fee is $2,669.25 and plan check $2,805.00 before surcharges.

What requires a building permit in Culver City?

The city lists new residential and commercial construction, home additions and remodels, accessory dwelling units, re-roofs, sandblasting, tenant improvements, repairs and mechanical, electrical and plumbing work as jobs that need a Building Safety permit. Demolition, pools and spas and block walls take their own permits, separate from the main building permit.

Culver City also publishes plan check thresholds. A project that crosses one must be submitted with plans for review; a project below all of them can go straight to a permit application without plans, although unusual projects may still need review.

Plans required (building)

  • New construction, tenant improvements, additions and demolition
  • Adding, removing or moving existing walls
  • Window replacement
  • Block walls over 3 feet 6 inches, fences over 7 feet, and any retaining wall
  • New or altered pools and spas, earthquake retrofits and parking lot restriping
  • Anchorage for equipment over 400 pounds

Plans required (trades)

  • Mechanical: commercial kitchen hoods, work areas of 10,000 sq ft or more, A/C systems over 9 tons, new buildings of 3 or more units
  • Electrical: work areas of 5,000 sq ft or more, replacing half or more of the fixtures, services of 400 amps or more, new buildings of more than 4 units
  • Plumbing: commercial kitchens, grease or sand interceptors, 16 or more fixtures, sump pumps, gas systems over 2 inches
  • Any cannabis-related project, in every trade

What Culver City decides and what the state holds

The city enforces the 2025 California Building Standards Code with its own amendments in Municipal Code Chapter 15.02, plus the 2024 International Property Maintenance Code. Local rules include the mandatory soft-story retrofit program for older wood-frame apartment buildings, a September 29, 2025 urgency ordinance that allows a single exit stairway in residential buildings up to six stories, gender-neutral restrooms in new ground-up buildings applied for after June 27, 2024, and the Section 3307 rule that protects neighboring property during construction.

Culver City building department: who handles permitting

The Building Safety Division handles permits, plan check and inspections for all property inside Culver City. Its online permit portal and virtual appointments cover Planning and zoning questions, permit issuance, code questions and the soft-story program, and email questions are answered within 24 to 48 hours in the order received.

Short on time to read all of this?

Get a free quote →
Culver City permit contacts
DetailInformation
OfficeBuilding Safety Division, Planning and Development Department, City Hall second floor, 9770 Culver Boulevard, Culver City, CA 90232
Phone / email(310) 253-5800; building.safety@culvercity.org
HoursMonday to Friday, 7:30 a.m. to 5:30 p.m.; City Hall closes on alternating Fridays
Building OfficialTim Koutsouros, Division Manager
Current Planning(310) 253-5710
Public Works Engineering(310) 253-5600 (site re-grading and right-of-way)

Other city divisions sign off on the same building permit and may add their fees: the Fire Department’s Community Risk Reduction Division for construction plan review and inspection, Environmental Programs and Operations ((310) 253-6400) for trash enclosures and waste bins, and Cultural Affairs ((310) 253-6001) for the Art in Public Places requirement.

Culver City permit types

Every structure and every record type (building, mechanical, electrical, plumbing, demolition and solar) needs its own application. Residential rooftop solar and battery systems can get an instant permit through the city’s partnership with Symbium, open to contractors with an A, B, C-10 or C-46 license and to applicants using the state SB 379 path. Electric vehicle chargers have a streamlined no-fee option for qualifying installs; others are filed with an electrical permit application and plans by email.

Residential permits

A house, addition or ADU submittal includes architectural drawings with Title 24 energy and mandatory CALGreen forms, structural drawings and calculations, and, where they apply, a geotechnical report, construction management plan, sound attenuation report and a Southern California Edison clearance. Drawings are at least 24 by 36 inches; they can be filed electronically but must be printed full size for inspection. Applications also need HOA approval or a statement that the HOA was notified, a grant deed after a recent sale, an asbestos declaration, an agent authorization where used, and the owner certification form.

Commercial permits

Tenant improvements and new commercial buildings use the commercial submittal list. Food facilities need Los Angeles County Public Health approval before issuance, equipment that emits air contaminants needs a South Coast AQMD permit, and Cal/OSHA permits are needed for trenches 5 feet or deeper and buildings over three stories. For permits issued after June 12, 2025, projects of 20 or more new homes or over 20,000 square feet of new commercial or industrial space must file the contractor transparency disclosure during plan check and keep it updated within three business days of a change.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Current Planning. Discretionary projects are reviewed first. Planning’s own plan check for building permits is graded as major, moderate, minor (a new single-family house or duplex) or minimal (single-family additions, ADUs and non-residential tenant improvements), with landscape review for larger sites.
  • Neighbor notice. New construction and major remodels must mail a notice to owners and occupants within 100 feet at least 10 days before work starts and return a signed affidavit. An excavation deeper than a neighbor’s foundation and than its distance from the property line needs a 30-day notice by certified mail, and no permit is issued until the return receipt is in the plans.
  • Engineering. Site re-grading and work in the public right-of-way go through Public Works Engineering.
  • Art in Public Places. New projects of five or more homes or new commercial buildings valued at $500,000 or more, and remodels of either valued at $250,000 or more, owe a 1% allocation.

Culver City permit fees

Fees come from the FY 2026-27 comprehensive fee schedule, in effect since July 1, 2026. The City Council adopted the comprehensive schedule by Resolution No. 2025-R008 on January 13, 2025 and its latest update by Resolution No. 2026-R046 on May 26, 2026. Building permit and plan check fees are set by project value, which the division checks against ICC building valuation data or RS Means; you may submit contracts or a detailed cost estimate instead. Electrical, mechanical and plumbing fees are charged when the application is filed.

Culver City building fees, FY 2026-27
ItemFee
Building permit, value $25,001 to $50,000$562.75 plus $22.50 per $1,000 over $25,000
Building permit, value $50,001 to $100,000$1,125.75 plus $12.75 per $1,000
Building permit, value $100,001 to $500,000$1,769.25 plus $9.00 per $1,000
Building permit, value $500,001 to $1,000,000$5,468.50 plus $12.75 per $1,000
Building plan check, value $100,001 to $500,000$1,930.00 plus $8.75 per $1,000
Technology fee / General Plan maintenance fee5.44% / 4.97% (the General Plan fee applies to projects over $100,000)
Electrical, mechanical or plumbing issuance fee$120.50 each
Revision plan check / re-inspection$160.75 per hour, one-hour minimum
Residential solar up to 15 kW$450, plus $15 per kW above
Demolition, residential partial / full$201.00 / $265.25
Permit extension or renewal$241.25
Investigation fee, work without a permit$291.50
School fees listed in the schedule, new area of 500 sq ft or more$5.17 per sq ft residential; $0.84 commercial
Commercial/industrial tax$26.50 on the first $250,000 plus 1.5% above
Condominium tax$1,000 per unit

Rather talk it over?

Call 1-855-478-4290 →

Worked example: for a $200,000 addition, the building permit is $1,769.25 plus 100 × $9.00, or $2,669.25, and plan check is $1,930.00 plus 100 × $8.75, or $2,805.00. The technology and General Plan fees, state seismic fees and any Planning, fire and school charges are added on top. Under SB 937, certain development impact fees on qualified residential projects are deferred until final inspection.

Trade permits and who may pull them in Culver City

Electrical, mechanical and plumbing work each need their own permit record, with two full-size plan sets when filed at the counter (four for a building application). Trade jobs below the plan check thresholds go straight to a permit without plans.

  • Contractors list their state license number and Culver City business license number on the application, and both must be active when the permit is issued. Contractors sign the issued permit by email.
  • Owner-builders may sign the permit as the owner, and the division posts the state board’s caution notice for owner-builders.
  • Agents for a contractor or owner may sign with a written authorization.
  • Fire alarms and sprinklers are permitted separately by the Fire Department’s Fire Prevention Division, according to the city’s guide for businesses moving into existing buildings.

The comprehensive schedule sets a $55 processing fee for a Culver City business tax certificate application.

Rather not deal with the Culver City building department?

Get a free quote →

How to apply for a Culver City building permit

1. Check the thresholds

Use the plan check threshold list to see whether plans and review are needed.

2. Gather documents

Plans, HOA approval, grant deed if recently bought, asbestos declaration, owner certification and any agent authorization.

3. Apply in the portal

Create an account, choose the record type, upload plans under the documents tab and note the record number.

4. Pay plan check fees

Staff check completeness within 2 to 3 business days; once you pay, plans are routed to the other divisions.

5. Answer corrections

Comments and responses run through the portal; more than one round is typical.

6. Pay, sign and send notices

Pay permit, impact and sewer fees, sign the permit by email and mail the 10-day neighbor notice where required.

Review, corrections and what causes delay

Each plan check round takes about 20 business days, or 10 for qualified expedited reviews; the division page puts current plan checks at 15 to 20 business days from payment and routing. Paper revisions dropped in the second-floor bin sit 48 to 72 hours before processing, so small revisions are better emailed with the old and new sheets. An application is treated as abandoned 12 months after filing unless extended, in steps of up to 90 days.

Inspections in Culver City

Request inspections by email to building.safety@culvercity.org with the permit number, site address, type of inspection, the date you want and an on-site contact. Dates are not guaranteed; you get a confirmation email once the inspection is booked. Inspectors can visit in person or inspect by FaceTime or Cisco Webex.

Construction is allowed from 8:00 a.m. to 8:00 p.m. on weekdays, 9:00 a.m. to 7:00 p.m. on Saturday and 10:00 a.m. to 7:00 p.m. on Sunday, unless a development agreement says otherwise. Under Section 3307, new construction and major remodels must put up a protective screen or fence at least 6 feet high next to adjoining property unless the Building Official finds a screen unfeasible, and the Building Official can stop work or withhold inspections when neighboring property is damaged.

Work must begin within 12 months of issuance, and a permit lapses if work stops for 180 days; extensions of up to 180 days each may be granted. After the final, email the division to request a certificate of occupancy for new development or a change of occupancy; a temporary certificate costs $643.25.

California building code in Culver City

Culver City’s codes-in-effect sheet lists the 2025 California Building Standards Code with City of Culver City amendments for applications from January 1, 2026; projects submitted by December 31, 2025 stay under the 2022 edition. FEMA’s Community Status Book lists Culver City (community 060114) as participating in the National Flood Insurance Program, with its current flood map dated April 21, 2021.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Culver City building permit FAQ

Can I apply for a Culver City permit online?

Yes. The city’s online permit portal takes applications, plans, fees and corrections; file one application for each structure and each trade. Counter submittals are also accepted on the second floor of City Hall.

Do I need plans for my project?

Only if it crosses a plan check threshold, such as new construction, moving walls, window replacement, block walls over 3 feet 6 inches or fences over 7 feet. Below the thresholds you apply for the permit without plans.

How much is a building permit in Culver City?

It depends on value. On a $200,000 project the FY 2026-27 schedule gives a $2,669.25 permit fee and $2,805.00 for plan check, before the 5.44% technology fee, the 4.97% General Plan fee and other charges.

How long does plan check take?

About 20 business days per round, or 10 for qualified expedited reviews, and most projects need more than one round.

Do contractors need a Culver City business license?

Yes. The application asks for the city business license number, and both it and the state contractor license must be active before the permit is issued.

Do I have to notify my neighbors?

For new construction and major remodels, yes: mail the city’s notice to owners and occupants within 100 feet at least 10 days before work starts and send the signed affidavit to the division.

Is my building subject to the soft-story retrofit program?

The mandatory program covers older wood-frame multi-unit buildings. Owners must complete evaluations and retrofits on the ordinance’s timelines; the screening form fee is $321.50.

Culver City permit search and official resources

Applicants track their own applications, corrections and issued permits under My Records in the online permit portal. Before selling a property, an owner applies for a Report of Building Records, which costs $160.75 for residential and $321.50 for commercial property. The same section of the division page sets out the smoke detector rules for resale and the earthquake gas shutoff valve requirement.

Inspections are where schedules slip.

Get a free quote →

Simplify Culver City permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Culver City sooner?

Let Alliance prepare, file, and track your Culver City permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Culver City permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.