Inside Campbell city limits, building, electrical, plumbing and mechanical permits come from the Building Inspection Division of the Community Development Department, City Hall upper level, 70 North First Street ((408) 866-2130). Applications are uploaded to the MyGovernmentOnline (MGO) portal in one of nine application groups. Under the Master Fee Schedule effective July 1, 2026, the building permit fee is 2% of valuation on the first $500,000, with a $237 minimum, and a first plan check takes at least 4 to 6 weeks.
What requires a building permit in Campbell?
Campbell’s rule is short: construction needs a building permit. You do not pick an exact permit type; you file a complete submittal in the right one of nine MGO application groups.
Permit needed
- Water heater, furnace and HVAC installs, electrical service upgrades, re-roofs, sewer and water line repairs and whole-house rewiring (trade group)
- Kitchen, bath and whole-house remodels, window replacement, foundation repair, stucco or siding upgrades, porches, patios and sunrooms
- Garage conversions, interior ADUs and junior ADUs
- New houses, additions and detached or attached ADUs
- Fences over 7 feet, walls over 3 feet and every electric gate
- Sheds and other accessory structures of 120 sq ft or more, or any size with electrical, plumbing or mechanical work
- Pools and spas, generators, signs, solar, EV chargers and battery storage
- Demolition, including removal of pools, spas and septic tanks
No building permit
- Accessory structures under 120 sq ft with no electrical, plumbing or mechanical utilities; they must still meet the zoning standards in Municipal Code Section 21.36.020
- Fences up to 7 feet and walls up to 3 feet; a fence, wall or gate over 6 feet, or one that does not meet Section 21.18.060, still needs a Planning fence exception
Plans are not needed for every trade permit. The trade guide asks for plans for commercial HVAC replacement or rooftop equipment, new or relocated residential AC condensers, utility or plumbing trenching, new (not replacement) electric panels, plumbing fixtures and water heaters, and whole-house rewiring.
What Campbell decides and what the state holds
Campbell writes its own zoning (Title 21 of the Municipal Code), fence and accessory-structure standards, fee schedule, construction hours and right-of-way rules. On September 3, 2024 the City Council adopted Air Quality Ordinance No. 2316, which bars NOx-emitting appliances and equipment for space and water heating, cooking and clothes drying in new homes, new commercial buildings and substantial rebuilds, with limited exemptions such as commercial cooking and small propane tanks outdoors. The city’s earlier gas-ban reach code, Ordinance 2290, has been suspended since May 2024.
Campbell building department: who handles permitting
The Building Inspection Division in Community Development issues building and trade permits for property inside Campbell. Plans are checked by city staff together with a third-party plan-check consultant, Planning, Land Development Engineering and the Santa Clara County Fire Department, which reviews fire items such as sprinkler systems. The Community Development Director is Rob Eastwood and the Building Official is Bob Lennen.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Inspection Division, City Hall upper level, 70 North First Street, Campbell, CA 95008 |
| Phone and email | (408) 866-2130, building@campbellca.gov |
| Hours | Monday to Friday, 8 a.m. to 5 p.m. |
| Portal | MyGovernmentOnline (MGO) Connect; MGO support (866) 957-3764 |
| Planning | (408) 866-2140, planning@campbellca.gov |
| Public Works / encroachment | (408) 866-2150 |
| Business licenses | City Hall lower level, (408) 866-2174 |
Campbell permit types
MGO organizes building work into nine groups: general trade (MEP) permits, residential remodels, new residential construction, commercial remodels, new commercial construction, grading and site improvements, simple construction, miscellaneous requests and demolition. Simple construction has three sub-guides: ancillary structures and equipment, renewable energy systems, and wireless telecommunications.
Residential permits
- Remodels cover interior kitchens, baths and whole-house work, interior ADUs, garage conversions and JADUs, porches, patios, sunrooms and window replacement. A garage conversion may need Planning approval first or replacement parking.
- New construction covers new houses, additions and detached or attached ADUs.
- ADUs and JADUs need no land-use entitlement; the complete application goes straight to the Building Division under the new-residential guide. The city’s ADU bulletin of March 5, 2025 sets local and by-right standards, and units built without permits before January 1, 2020 may be legalized through a building permit. The one-week Express Plan Check for ADUs has been suspended since August 2025; a pre-approved ADU plan gallery remains.
- Owner-builders sign the city’s owner-builder disclosure forms with the application. A limited liability company cannot be an owner-builder.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial remodels cover tenant improvements, “market-ready” interior demolition, changes of occupancy without construction and storefront changes. New commercial construction covers offices, retail, industrial and multifamily buildings, institutional buildings and wireless facilities.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning. Site and architectural review, use permits, variances, fence exceptions and tree removal permits come from the Planning Division; approved projects then pay a post-entitlement plan check fee at the building stage.
- Sewer. West Valley Sanitation District collects infrastructure and sewer fees for new construction before issuance, and its permit copy marked for the building department must be given to the city ((408) 378-2407).
- Schools. Residential work adding more than 500 sq ft, including garage conversions and ADUs, pays school developer fees directly to the district before the permit is issued. Districts serving Campbell include Campbell Union, Campbell Union High, Cambrian and Moreland.
- Public right-of-way. Driveway approaches, sidewalks, utility laterals, street trees, cranes and lane closures need a Public Works encroachment permit, with insurance and a cash deposit or bond.
- Fire and water. Fire sprinkler systems need a separate Santa Clara County Fire Department review letter ((408) 378-4010), and San Jose Water may require a larger service ((408) 279-7900).
Campbell permit costs and fees
Campbell’s fees are in the FY 2027 Master Fee Schedule, effective July 1, 2026. Most building fees rise each July 1 with the San Francisco Bay Area consumer price index. The building permit fee is a percentage of valuation applied in tiers, and the base fees cover up to three plan checks, the first inspection and one re-inspection; further reviews and inspections are billed by the hour.
| Item | Fee |
|---|---|
| Building permit, minimum | $237 |
| Valuation up to $500,000 | 2.00% of valuation |
| Valuation $500,001–$1,000,000 | 1.66% on that portion |
| Valuation above $1,000,000 | 1.00% on that portion |
| Fee at plan check | 33% of the building permit fee |
| Third-party plan check | 0.2% of valuation |
| Title 24 energy plan check | $237 each |
| Fire plan check | Greater of $119 or 10% of the building permit fee |
| Electrical, plumbing or mechanical permit, per trade | $237 base fee |
| Trade permit by inspections (alternative) | $119 for one, $237 for two, $356 for three, $474 for four, $119 each after |
| General Plan maintenance / technology / training | 0.16% / 0.04% / 0.02% of valuation |
| Construction License Tax (Municipal Code 3.40) | $0.50 per sq ft |
| Demolition permit | $1,423 |
| Revisions, excess plan review, re-inspection | $237 per hour; re-inspection paid before the visit |
| Work without a permit | 2 times the permit fee |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedule: a $200,000 addition sits entirely in the first tier, so the building permit fee is 2% of $200,000, or $4,000. The fee at plan check is 33% of that ($1,320), the General Plan maintenance fee $320, the technology fee $80 and the training fee $40. Trade, energy, fire, state and construction-tax charges depend on the plans and are added to the invoice.
Impact and planning fees
The park in-lieu fee is $33,025 for a new single-family unit, $23,360 per multi-family unit and up to $9,328 for an ADU of 750 sq ft or more; JADUs pay nothing. A roadway maintenance fee of 0.32% of the building permit valuation applies, and the inclusionary in-lieu fee ($62 per sq ft) and commercial linkage fee ($9 per sq ft) took effect October 3, 2025. Planning fees include administrative site and architectural review at $2,839 for a new house and $2,193 for an addition or remodel, fence exceptions from $671 and a $5,289 variance. A tree removal permit is free for a single-family home and $310 for other properties.
The initial plan-check payment is due at submittal; once the application is accepted the city emails an invoice that must be paid within two business days or the application is rejected. Card payments carry a 3.36% processing fee and eChecks 1% plus $0.30; cash and paper checks paid at the Finance counter carry none.
Trade permits and who may pull them
Electrical, plumbing and mechanical permits are issued by the Building Inspection Division through the trade (MEP) group in MGO, at a $237 base fee per trade or, where that does not fit the work, by the number of inspections needed. The trade guide matches each job to a state license class: C-10 electrical contractors for service upgrades, rewiring and temporary power poles; C-20 for AC, HVAC and furnaces; C-36 plumbing contractors for water heaters and water or sewer lines; and C-39 roofers for re-roofs. An owner-builder may also do the work.
- Business license. Building and Public Works both ask for proof of a City of Campbell business license before they issue permits. Licenses are filed and renewed in the city’s online portal and run for one year; questions go to (408) 866-2174 or businesslicenses@campbellca.gov.
- Fire systems. Sprinkler work and changes to existing fire systems are reviewed with the Santa Clara County Fire Department.
Rather not deal with the building department?
Get a free quote →How to apply for a Campbell building permit
Confirm the parcel is in Campbell on the city GIS viewer, then ask Planning ((408) 866-2140) whether the project needs site and architectural review, a fence exception or other approval first.
Download the Building Application Guide for the right group; each lists the plan sheets and documents that group needs.
Register on MyGovernmentOnline. If you cannot apply online, the public kiosk in Community Development accepts files on a USB drive only.
Upload the plans as PDFs with forms such as the owner-builder declaration, Green Halo waste plan or special inspection form, then pay the initial plan-check invoice within two business days.
Pay school developer fees and West Valley Sanitation District fees and get fire sprinkler approval where they apply; both must be cleared before issuance.
After final sign-off, pay the remaining fees in MGO and keep approved plans on site.
Review, corrections and what causes delay
Building, the third-party plan-check consultant, Planning, Land Development Engineering and the fire department review at the same time, and their comments are posted to the MGO portal as each finishes. The city asks for at least 4 to 6 weeks for the first plan check and 2 to 4 weeks for each later review. Resubmittals need an itemized response letter organized by reviewer. An application expires without refund if the permit is not obtained within 180 days of submittal; the Building Official may extend it on request before it lapses.
Inspections in Campbell
Inspections are requested in your MGO account or by phone through MGO at (866) 957-3764. Requests made before midnight are guaranteed for the next business day, and you can note an AM or PM preference. The inspections page gives the morning window as 8 a.m. to 12:30 p.m. and the afternoon window as 12:30 to 5 p.m.; the older handout says inspections run 9 a.m. to 4 p.m. One ICC-certified inspector handles all trades on a job, and some inspections may be done over Zoom.
- Sequence. The city’s list runs from footings and foundation through underfloor work, slab, shear and roof nailing, a watertight check of lath or siding before trade inspections, rough trades, framing, insulation, drywall nailing and shower pans, to final trades, final Planning, Public Works and fire sign-offs, and the building final.
- Limits. Inspectors take up to two inspections per visit and two visits per day. A job that is not ready may be charged a re-inspection fee, which must be paid before the next inspection.
- Keeping the permit alive. An issued permit expires without refund if no inspection is passed for 180 days.
- Construction hours. Work is allowed Monday to Friday 8 a.m. to 5 p.m. and Saturday 9 a.m. to 4 p.m., with no work on Sundays or state and federal holidays.
Want this handled start to finish?
Get a free quote →California building code in Campbell
Campbell’s building regulations are in the Municipal Code, with its own Air Quality Ordinance No. 2316 adding the zero-NOx appliance rule for new buildings and substantial rebuilds. FEMA’s Community Status Book lists the City of Campbell (community 060338) as participating in the National Flood Insurance Program, with a current flood map dated February 19, 2014.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Campbell building permit FAQs
Who issues building permits in Campbell?
The city’s Building Inspection Division at City Hall, 70 North First Street, upper level ((408) 866-2130), for all construction inside Campbell.
How much is a building permit in Campbell?
The permit fee is 2% of valuation up to $500,000, 1.66% on the next $500,000 and 1% above $1,000,000, with a $237 minimum. A $200,000 addition has a $4,000 permit fee, a $1,320 fee at plan check and smaller valuation-based surcharges.
Do I need a permit for a shed or a fence?
Not for a shed under 120 sq ft with no utilities, a fence up to 7 feet or a wall up to 3 feet, though zoning rules still apply. Taller fences and walls, all electric gates and larger or wired sheds need a permit; fences over 6 feet also need a Planning fence exception.
How long does plan review take?
Plan for at least 4 to 6 weeks for the first plan check and 2 to 4 weeks for each resubmittal.
Can a homeowner pull a permit?
Yes, as an owner-builder, by signing the city’s owner-builder disclosure forms with the application. A property held by an LLC needs a licensed contractor.
Does an ADU need planning approval?
No. The ADU or JADU application goes straight to the Building Division; larger ADUs pay school and park fees.
How do I book an inspection?
Request it in MGO or by phone at (866) 957-3764 before midnight for a guaranteed next-business-day inspection.
Campbell permit search and official resources
The status of existing permits can be searched in the MGO portal, and the city’s permit map shows recent permit activity by neighborhood. Older permit and address records are searched by Building staff for $237 an hour under the fee schedule, and other city records are requested through the city’s public records page.
Inspections are where schedules slip.
Get a free quote →- Campbell Building Inspection Division
- MyGovernmentOnline permit portal
- Building Application Guides (nine groups)
- General trade permits (MEP) guide
- Single-family residential remodel guide
- Simple construction guide: fences, sheds, pools
- Building handouts and forms
- FY 2027 Master Fee Schedule, effective July 1, 2026
- Building inspections and construction hours
- How to schedule inspections
- Sequence of inspections
- Accessory dwelling unit bulletin
- Public Works encroachment permits
- Business licenses
- 2025 California Title 24 building standards
- FEMA Community Status Book, California
Simplify Campbell permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Campbell sooner?
Let Alliance prepare, file, and track your Campbell permits while your crew stays on the job.
More California permitting guides
Santa Clara County
Read guide →Cupertino
Read guide →Gilroy
Read guide →Canyon Lake Building Permit Guide
Read guide →Carlsbad Building Permit Guide
Read guide →Carpinteria Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Campbell permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.