Every building permit in Beverly Hills comes from the City’s Building & Safety Division in the Community Development Department, 455 North Rexford Drive (310-285-1000, cdpermits@beverlyhills.org). Simple jobs are reviewed at the walk-in counter Monday to Thursday from 8 to 10 a.m.; larger projects go through electronic plan review, which the City budgets at 3, 5 or 7 weeks depending on size. Under the FY 2026-27 fee schedule a $50,000 job carries a building permit fee of $2,114.50 before plan check and other charges.
What requires a building permit in Beverly Hills?
The City’s post-entitlement guidance states that a building permit is required for any project that alters a structure in whole or in part, including architectural, landscape, demolition and temporary facility work. The Permit Center guide sorts common permits by how they are reviewed.
Walk-in plan review
- Kitchen and bathroom remodels, and minor interior remodels of single-family homes with no structural work
- Electrical panel upgrades under 400 amps and electrical repair
- HVAC change-outs, plumbing repair, water heaters and earthquake shut-off valves
- Re-roofing, window change-outs (same size, non-structural) and chimney repair
- Foundation bolting and smoke detectors
- Solar PV under 10 kW and EV chargers (more than one charger goes to electronic review)
- New pools or spas on a level pad, and pool re-plastering or re-tiling
- Site work such as fences, walls, fire pits, barbecue areas and water features
Electronic plan review
- New single-family homes, additions and major remodels
- New commercial, multi-family and mixed-use buildings
- Commercial tenant improvements and medical office build-outs
- Residential accessory structures
- Pools and spas on structural piles
- Mandatory soft-story retrofits of multi-family buildings
- Plumbing, mechanical and electrical work that needs plan check
- Water-efficient landscaping
Asbestos abatement, sandblasting, after-hours work and temporary event generators also need City approval; generators with internal combustion engines over 50 bhp need South Coast Air Quality Management District approval first. Every change to a roof needs a roofing permit, one per structure.
What Beverly Hills decides and what the state holds
The City’s own amendments to the state codes are in Beverly Hills Municipal Code Title 9, Chapters 1 and 2, and took effect with the state codes on January 1, 2026; the City also enforces the International Property Maintenance Code. Local rules include a citywide requirement for Class A fire-rated, non-wood roofs, site-specific seismic fault investigations before permits where the City’s fault guidelines apply (BHMC 10-3-1833), heavy-truck rules in Trousdale Estates and construction hours of 8 a.m. to 6 p.m. on weekdays only. Romex cable, banned in the city for work before January 2008, is now allowed in single-family and multi-family homes when installed to the California Electrical Code. Contractor licenses remain a state matter.
Short on time to read all of this?
Get a free quote →Beverly Hills building department: who handles permitting
The Building & Safety Division is the enforcing agency for all residential and commercial construction in the city. Its staff of plan review engineers, architects, permit technicians and building inspectors check plans, issue permits, inspect work and sign off certificates of occupancy, which go through the inspector, the Building Inspection Manager and the Building Official. Before permits are issued on larger projects, plans are also reviewed by Planning, Public Works and the Beverly Hills Fire Department.
| Detail | Information |
|---|---|
| Office | Permit Center, Community Development Department, 455 North Rexford Drive, Beverly Hills, CA 90210 |
| Phone | 310-285-1000 |
| cdpermits@beverlyhills.org | |
| Walk-in plan review | Monday to Thursday, 8 a.m. to 10 a.m. |
| Appointments | Monday to Thursday afternoons and all day Friday |
| Public Works counter | Tuesday and Thursday, 8 a.m. to 10 a.m. (transportation review 9 to 10 a.m.) |
| Fire plan check questions | Monday and Wednesday, 9 a.m. to 11 a.m. |
| Inspection line | 310-285-2534 (automated) |
City Hall itself is open Monday to Thursday from 7:30 a.m. to 5:30 p.m. and Friday from 8 a.m. to 5 p.m. The City notes that it is required by law to check the licenses of all contractors working in Beverly Hills.
Beverly Hills permit types and what comes first
Permits are split between walk-in plan review, permitting appointments and electronic plan review. All electronic projects start with the Online Plan Review and Permit Application (OPA); staff process the application, add the fees and send a link for uploading the plan files.
Residential permits
Over-the-counter home work includes remodels without structural changes, re-roofs, window change-outs, panel upgrades, solar under 10 kW and pools on level pads. New homes, additions and remodels on hillside lots, accessory structures and pools on piles go to electronic review. A re-roof needs a completed application, photos of the existing roof and building, a roofing product with an ICC-ES report and a Cool Roof Rating Label, and the material must be a Class A fire-rated, non-wood roof.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial storefront alterations and minor tenant improvements are small projects; offices, restaurants, medical and surgery centers are intermediate; hotels, theaters and new commercial, multi-family and mixed-use buildings are complex. Fire sprinkler, fire alarm, hazardous materials and medical gas permits are applied for through the Fire Department’s own online permit application. Tenant-occupied multi-family work lasting more than a day needs a construction means-and-methods plan for the Rent Stabilization Division.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning review. Projects subject to Architectural and Design Review must clear it first, with an owner authorization letter; the fee schedule also offers a concept review (one multi-agency review) for $1,586. Roofing visible from the street in the Central Area may need design review, and historic properties can need extra Planning review.
- Seismic fault investigation. Where the City’s Fault Investigation Guidelines apply, a peer-reviewed site investigation must be approved before building permits, starting with a consultation and consultant deposit.
- Public right-of-way. Work in the street, sidewalk, driveway approaches, curb and gutter or sewer laterals needs a right-of-way permit; no right-of-way construction is allowed from November 16, 2026 through January 4, 2027.
- Trousdale Estates. Construction there needs a registered traffic management plan, certified heavy vehicles and 24-hour hauling notices under Ordinance 15-O-2683.
Beverly Hills permit fees
Fees come from the City’s Schedule of Taxes, Fees, and Charges for Fiscal Year 2026-27. The building permit fee is set by total valuation and covers building, demolition, grading, shoring, asbestos abatement, synthetic turf and sandblasting permits; plan check and a set of percentage surcharges are added.
| Item | Fee |
|---|---|
| Valuation $0 to $500 | $80 |
| $501 to $1,000 | $80 plus $13.50 per $100 over $500 |
| $1,001 to $20,000 | $147.50 plus $53 per $1,000 over $1,000 |
| $20,001 to $50,000 | $1,154.50 plus $32 per $1,000 over $20,000 |
| $50,001 to $100,000 | $2,114.50 plus $23 per $1,000 over $50,000 |
| $100,001 to $500,000 | $3,264.50 plus $22 per $1,000 over $100,000 |
| Over $500,000 | $12,064.50 plus $19 per $1,000 over $500,000 |
| Permit issuance | $95 on all development permits and plan review |
| Plan check | 80% of the total permit fee |
| Energy permit / energy plan review | 20% / 10% of the building permit fee |
| Electrical, mechanical or plumbing | 8.33% of the valuation-based permit fee each |
| Technology fee | 3.7% of permits and plan checks |
| Document maintenance | 10% of the permit fee |
| Training and education | 1.2% of building and trade permits |
| Reinspection for incomplete work | $299 |
| Permit extension | $135 |
| Residential solar up to 15 kW | $450, plus $15 per kW above 15 kW |
Rather talk it over?
Call 1-855-478-4290 →Worked example. A $50,000 kitchen remodel falls at the top of the $20,001 to $50,000 band: $1,154.50 plus 30 × $32 gives a building permit fee of $2,114.50. Plan check at 80% adds $1,691.60 and issuance adds $95, before the energy, trade, technology, document and state fees. Band starting figures in the table are computed from the City’s per-unit rates.
Other charges that often apply: a General Plan maintenance fee of $0.00194 per dollar of valuation on all development, a construction-related parking permit priced by valuation (from $63 up to $10,000 to $4,545 over $500,000), $395 for after-hours construction over 1 to 14 consecutive days and $1,258 for a temporary or final certificate of occupancy.
Trade permits and who may pull them
Electrical, mechanical and plumbing permits are issued by the same division and are priced at 8.33% of the permit fee produced by the overall project valuation, with a trade plan check fee of at least $53 each. Fire sprinkler and fire alarm systems are permitted through the Fire Department’s online application, and the rough fire alarm inspection is booked with the building inspector.
The City requires a licensed contractor for every project valued at $1,000 or more. Someone pulling a permit for a license holder needs an agent-authorization letter on company letterhead. Owner-builder permits are limited to owner-occupied single-family homes and owner-occupied condominiums (interior work only); the City publishes an Owner-Builder Acknowledgement and Information Verification form and an Owner-Builder Consent Letter for these permits. Contractors should ask the City’s finance office (310-285-2419) whether a business license is required.
Rather not deal with the building department?
Get a free quote →How to apply for a building permit in Beverly Hills
Use the Permit Center guide to see whether your job is a walk-in, an appointment or an electronic plan review; book a pre-application consultation for larger projects.
Get any Architectural or Design Review approval, and complete a seismic fault investigation where the City’s guidelines require one.
Bring or upload the plan review and permit application, two sets of plans, structural calculations, Title 24 energy calculations and, as applicable, contractor, HOA and owner authorization letters, an asbestos survey, a roofing ICC report and a sound transmission rating.
Walk-in jobs are handled at the counter from 8 to 10 a.m., Monday to Thursday. Electronic projects start with the OPA; staff apply the fees and send an upload link.
Answer comments from Building, Planning, Public Works and Fire. Resubmittals take 2 or 3 weeks depending on project size.
Pay through the City’s CitySmart portal or at the counter; an account email must be added to the permit of record to pay online.
Review, corrections and what causes delay
The City budgets 3 weeks for small projects such as storefront alterations, solar and new pools on piles, 5 weeks for intermediate work such as new homes on level pads and commercial tenant improvements, and 7 weeks for complex jobs such as hillside homes, hotels and new commercial buildings. Expedited plan check shortens intermediate reviews to 3 weeks and complex ones to 4 weeks. Projects are held up by missing items on the City’s document list, a fault investigation or construction management plan that is not yet approved, or right-of-way work scheduled during the year-end moratorium.
Inspections in Beverly Hills
Book building inspections through the CitySmart portal up to 10 days ahead, or by the automated phone system at 310-285-2534. A limited number of next-day slots open at 9 a.m. each weekday on a first-come, first-served basis. Fire sprinkler, fire alarm and fire life-safety inspections other than the rough fire alarm are booked with the Fire Department Prevention Division at 310-281-2703. Right-of-way permits starting with “BS” follow the building inspection process; “PW” permits need a Public Works pre-construction meeting at least five business days before work starts.
Work may only run Monday to Friday from 8 a.m. to 6 p.m., and not on City-listed holidays, which include Yom Kippur and the day after Thanksgiving. After-hours special inspections need the assigned inspector’s approval, a Special Inspection and Supplemental Plan Review form filed at least 72 hours ahead, and a fee paid in advance.
Before the final building inspection, the professional of record must give the City digital as-built plans. A certificate of occupancy or completion (BHMC 9-1-112) is applied for once all permits are finaled; the inspector checks fees, documents and other department approvals, then the certificate is reviewed by the Building Inspection Manager and the Building Official, and any bond deposits are released. Sellers complete a Sale of Property Affidavit and email it to the Permits Division when a property transfers.
Want this handled start to finish?
Get a free quote →Building code in Beverly Hills
The City adopted the current state codes with its own amendments in BHMC Title 9, Chapters 1 and 2, effective January 1, 2026. Flood insurance: FEMA lists Beverly Hills as a participating community in the National Flood Insurance Program, with no special flood hazard area mapped in the city.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Frequently asked questions
Who issues building permits in Beverly Hills?
The City’s Building & Safety Division in the Community Development Department issues and inspects every building, electrical, mechanical and plumbing permit in the city.
How much is a building permit in Beverly Hills?
Under the FY 2026-27 schedule the permit fee is $80 for the first $500 of valuation and rises by band; a $50,000 job is $2,114.50. Plan check adds 80%, issuance $95, and energy, trade, technology and other percentage fees follow.
Can a homeowner pull a permit in Beverly Hills?
Only for an owner-occupied single-family home, or interior work in an owner-occupied condo. Every other project valued at $1,000 or more needs a licensed contractor.
How long does plan review take?
The City budgets 3 weeks for small projects, 5 for intermediate and 7 for complex ones, with expedited plan check of 3 or 4 weeks for the larger categories.
Do I need a permit to replace my roof?
Yes. Any roof change needs a roofing permit, each structure needs its own, and the City requires a Class A fire-rated, non-wood roof with an ICC-ES report and a Cool Roof Rating Label.
What are construction hours in Beverly Hills?
Monday to Friday, 8 a.m. to 6 p.m., with no work on City-listed holidays. After-hours work needs a separate permit, and right-of-way construction is paused from November 16, 2026 to January 4, 2027.
How do I book an inspection?
Online through CitySmart up to 10 days ahead, or at 310-285-2534. Next-day slots open at 9 a.m. each weekday.
How do I find old building permits for a Beverly Hills property?
Search the CitySmart Property Information Page. If a record is not online, file a public records request through the City Clerk; copies of plans need the owner’s and the design professional’s permission.
Inspections are where schedules slip.
Get a free quote →Beverly Hills permit search and official resources
Building permit records are on the City’s CitySmart Property Information Page. Community Development keeps building permits from 1918, electrical, mechanical and plumbing permits from 1987, certificates of occupancy from the late 1950s and geological and soils reports from the 1950s. Copies of plans are released only with written permission from the property owner and the professional who signed them (Health and Safety Code 19851): email the Plan Research Request Form to the Permit Center, view the plans by appointment, then file a notarized Plan Duplication Affidavit in person. The process can take up to 45 days, and if the professional does not answer a certified letter within 30 days the City may allow duplication.
- Beverly Hills Building & Safety
- Plan Review & Permitting guide (PDF)
- Inspections, certificates of occupancy and construction hours
- Permit records and plan duplication
- FY 2026-27 Schedule of Taxes, Fees, and Charges (PDF)
- Roofing permits
- Seismic fault investigation requirements
- Trousdale Estates construction rules
- Post-entitlement permit submittal requirements
Simplify Beverly Hills permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Beverly Hills sooner?
Let Alliance prepare, file, and track your Beverly Hills permits while your crew stays on the job.
More California permitting guides
Los Angeles County
Read guide →Cerritos
Read guide →Claremont
Read guide →Blythe Building Permit Guide
Read guide →Brawley Building Permit Guide
Read guide →Brea Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Beverly Hills permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.