In Belmont, building permits come from the city’s Permit Center in the Community Development Department, One Twin Pines Lane, Suite 110 (650-595-7422, PermitCenter@Belmont.gov). It covers roofs, water heaters, furnaces, remodels, decks, fences, solar, private sewer lines, pools, demolition, new buildings, tenant improvements and any other work on private property; work in the public right-of-way, tree removal and planning entitlements go to other departments. Applications and inspections run through eTRAKiT, plan checks currently take 21 to 28 days, and the FY 26-27 Fee Schedule sets flat fees such as $534 for a residential re-roof, with valuation-based fees and plan check at 65% of the building fee for larger projects.
What requires a building permit in Belmont?
The Permit Center lists the work covered by a building permit as roofs, water heaters, furnaces, remodels, decks, fences, solar, sewer lines on the property, pools, demolition, new buildings, tenant improvements “and any other work done on the property”. Work on or under the street is a separate Engineering matter.
Building permit (Permit Center)
- Re-roofs, water heaters, furnaces and HVAC changes
- Kitchen and bathroom remodels, windows, siding and stucco
- Decks, pergolas, fences, retaining walls and drainage systems on the property
- Pools, spas and saunas
- Solar, battery storage and EV chargers
- Voluntary foundation and seismic upgrades
- Demolition, new buildings and tenant improvements
Other departments
- Engineering and right-of-way permits: driveway approaches, sewer laterals, parking pads, curb drains, street trenching, sidewalks, and retaining walls, stairways or fences in the public right-of-way
- Grading, oversize loads, utility work and block or street closures
- Tree removal: Parks and Recreation for dangerous trees or removals with no planning entitlement; Community Development when a development project includes tree removal
- Planning entitlements such as design review and use permits
A stop work order for work done without permits is charged at twice the applicable permit fee.
What Belmont decides and what the state holds
Belmont sets its own fee schedule, single-family design review tiers, construction hours and construction time limits, noise rules, grading and tree rules, and impact fees. Fire review uses the SMC Fire department application. The building code and contractor licensing are state matters.
Belmont building department: who handles permitting
The City of Belmont issues its own building permits through the Permit Center and Building Division of the Community Development Department. Staff for permitting, building, planning and engineering are all at the walk-in counter during its hours, so one visit can cover questions for each. Outside counter hours, the Permit Center takes appointments by phone or email.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Permit Center / Building Division | One Twin Pines Lane, Suite 110, Belmont, CA 94002; 650-595-7422; PermitCenter@Belmont.gov |
| Walk-in counter | Monday, Wednesday and Thursday, 8:30 to 11:30 a.m. |
| Appointments outside counter hours | 650-595-7422 or permitcenter@belmont.gov |
| Daily inspection windows | Call 650-595-7422 from 8:30 a.m. |
| Online permits and inspections | eTRAKiT (registration required) |
| Fee schedule | Finance Department fees page |
Belmont permit types
The Permit Center uses a general Building Permit Application, a separate Re-Roofing Application and an MEP Application for mechanical, electrical and plumbing work. Several permits can be issued automatically through Symbium, and over-the-counter applications currently take 1 to 18 days with a complete package.
Residential permits
- Flat-fee jobs: the FY 26-27 schedule prices common residential work as a single permit fee, such as a bathroom or kitchen remodel at $946, a deck at $1,355 and a re-roof at $534.
- Additions and new homes: additions are sorted into design review tiers by size. Tier 1 (ground-floor additions of 399 sq ft or less) needs only a building permit; Tier 2 (ground-floor additions up to 899 sq ft, upper-floor additions up to 399 sq ft, or a combination up to 899 sq ft) goes to the Zoning Administrator; Tier 3 (larger additions) and all new homes go to the Planning Commission.
- ADUs: Belmont has separate applications for an ADU built from a pre-approved plan and a site-specific ADU.
- Solar: the city offers solar streamlined permitting; residential solar is $450 plus $15 per kW above 15 kW, and battery storage $450.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Tenant improvements and new commercial buildings use the valuation-based building permit fee, commercial trade rates ($0.30 per sq ft for new work, additions and alterations in each trade) and commercial solar ($1,000 base). New commercial buildings and commercial additions go through Planning design review ($13,251 and $10,998), and Engineering reviews building permit plans on a sliding scale by project cost. Larger projects can owe transportation impact fees, commercial housing mitigation fees and a 1% public art requirement.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Design review: Tier 2 review by the Zoning Administrator is $4,783 plus $1,651 in Engineering support; Tier 3 Planning Commission review of an addition is $10,166 plus $4,039; a new home takes a $13,000 Planning deposit plus a $5,500 Engineering deposit. Administrative design review for exterior changes is $3,926.
- Pre-application review: $2,373 for a small project and $5,908 for a large one.
- Other entitlements: variances ($11,499), conditional use permits, floor area exceptions, lot line adjustments and historic building alterations ($3,345 at Director level).
- Trees and grading: a protected tree removal permit with development is $985; grading of up to 500 cubic yards is $1,755 (a refundable grading deposit is also listed), and a grading moratorium exception request is $818.
- Fire: the Permit Center posts the SMC Fire department application for projects that need fire review.
Not sure this scope needs a permit?
Get a free quote →Belmont building permit fees
Belmont’s fees are in the FY 26-27 Fee Schedule linked from the Finance Department page, which the Permit Center names as the place for the latest schedule. Projects without a flat fee pay a building permit fee by valuation; the Building Official may set an alternative valuation when the reported one does not reflect the work.
| Total valuation | Fee |
|---|---|
| $1 to $2,000 | $424.35 base + $3.80 per additional $100 |
| $2,001 to $25,000 | $500.25 for the first $2,000 + $19.80 per additional $1,000 |
| $25,001 to $50,000 | $955.65 for the first $25,000 + $46.44 per additional $1,000 |
| $50,001 to $100,000 | $2,116.58 for the first $50,000 + $93.05 per additional $1,000 |
| $100,001 to $500,000 | $6,768.92 for the first $100,000 + $11.12 per additional $1,000 |
| $500,001 to $1,000,000 | $11,215.98 for the first $500,000 + $16.05 per additional $1,000 |
| $1,000,001 to $10,000,000 | $19,239.79 for the first $1,000,000 + $3.66 per additional $1,000 |
On top of the building fee, building plan check is 65% of the building fee, a “Plan Check – Planning Review” line is 35% of the permit fee, and a general plan maintenance fee is 0.77% of the building valuation (the schedule prints it as a percentage of valuation, not of the fee). The schedule does not say which projects the Planning review line applies to, so ask the Permit Center.
Worked example: a remodel valued at $150,000. The building permit fee is $6,768.92 plus 50 × $11.12 ($556), or $7,324.92. Building plan check at 65% adds $4,761.20, Planning review at 35% adds $2,563.72 and the general plan maintenance fee at 0.77% of $150,000 adds $1,155, for $15,804.84 before trade permits, Engineering plan check ($1,729 initial for a $100,001 to $250,000 project) and any impact fees.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Residential re-roof | $534 |
| Bathroom remodel / kitchen remodel | $946 / $946 |
| Deck / pergola | $1,355 / $1,160 |
| Windows, up to 5 / more than 5 | $600 / $1,055 |
| Siding or stucco | $849 |
| Retaining wall up to 50 linear feet (plus per 10 lf) | $1,550 (+$318) |
| New swimming pool / pool or spa alteration | $1,378 / $989 |
| Voluntary seismic upgrade / foundation upgrade | $1,008 / $1,160 |
| Temporary certificate of occupancy | $1,336 |
| Reinspection / inspection outside normal hours | $303 / $336 per hour |
| Additional plan review | $389 per hour |
| Permit re-activation not under construction time limits | $595 |
Impact fees for FY 2026-27 include a transportation impact fee of $8,400.90 per new single-family unit and $6,520.33 per multifamily unit (ADUs of 750 sq ft or more pay in proportion to the size of the main house), a residential development housing mitigation fee of $25.43 per sq ft, and, for subdivisions, Quimby park in-lieu fees of $41,043 per single-family unit and $27,362 per multifamily unit.
Engineering’s review of building permit plans starts at $247 for a project under $4,000 and rises to $494 ($4,001 to $10,000), $864 ($10,001 to $50,000), $1,235 ($50,001 to $100,000) and $1,729 ($100,001 to $250,000), with a $6,500 deposit above $250,000 and $247 an hour after the initial fee. Right-of-way items in the schedule include a debris bin in the street ($338 per 14 days), a driveway approach or small concrete frontage ($926), a sewer lateral video review inspection with report and certificate ($370) and a $500 deposit for NPDES construction stormwater inspections (six inspections for one rainy season).
Trade permits and who may pull them in Belmont
Mechanical, electrical and plumbing permits are filed on the MEP Application. For homes, each trade on new work, additions and alterations is $0.40 per sq ft; stand-alone items include an electrical permit at $382, a service panel, subpanel, temporary power or EV charger at $303, a rewire at $400, a water heater (gas, tankless or heat pump) at $329, a water repipe or private sewer lateral at $362, fixtures at $230, and a furnace, HVAC system or heat pump HVAC at $329. Commercial trade items start at $401.
The Building Department page links the Contractors State License Board, and applicants list their subcontractors on its Subcontractor List form. A property owner doing the work themselves files the city’s Owner-Builder Form with the application. Contractors’ eTRAKiT accounts link their permits automatically; owners with public accounts link the permit to their dashboard themselves.
Rather not deal with the building department?
Get a free quote →How to apply for a Belmont building permit
For an addition or new home, find the tier and file the Planning packet first if Tier 2 or 3 applies.
Permitting, building, planning and engineering staff are at the walk-in counter Monday, Wednesday and Thursday mornings.
Follow the Requirements for Digital Plans and Documents and fill in the Building Permit, Re-Roofing or MEP Application.
Register and submit online; allow up to 12 calendar days for initial processing.
Plan check currently takes 21 to 28 days (30 to 45 days for a new building’s first review).
Resubmittals and revisions take 5 to 14 days; use the Revision Statement form for changes.
Pay through eTRAKiT and schedule inspections there once the permit is issued.
Review, corrections and what causes delay
Over-the-counter times assume a complete submittal package, and plan checkers may add up to 7 calendar days to a posted due date. Additional plan review is billed at $389 an hour. The forms page includes a Parallel Plan Check Release and a Request for Alternate Materials and Methods ($1,596 to review), and the Building Department page posts a Construction Time Limits Acknowledgement; re-activating a permit that is not under construction time limits is $595.
Belmont building inspections
Inspections are scheduled in eTRAKiT, which requires registration for first-time users; results are posted there and can be downloaded. The Building Division inspects in person, with morning inspections from 9 a.m. to noon and afternoon inspections from 1 to 4 p.m. Each day’s schedule is available from 8:30 a.m. by calling 650-595-7422 to get the inspection window. Reinspections are $303 an hour.
Construction is limited to Monday to Friday from 8 a.m. to 5 p.m. and Saturdays from 10 a.m. to 5 p.m.; no work is allowed on Sundays or holidays, including setting up or securing the site. The forms page also includes a Noise Ordinance Exception form. Special inspections use the city’s Special Inspection Agreement and its list of pre-qualified inspection and testing agencies, and an In-Progress Roof Final Agreement is posted for re-roofs.
California building code in Belmont
Belmont’s Building Department page links the California Building Codes, the State Architect’s access compliance pages, the Energy Commission and the City of Belmont Municipal Code. FEMA’s Community Status Book lists the City of Belmont (community 065016) as participating in the National Flood Insurance Program, with a current flood map dated April 5, 2019.
Want this handled start to finish?
Get a free quote →California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Belmont permit search and official resources
The Permit Center page has Search Permits and Viewing Property Files links for looking up a project or an address. Copies of plans are requested with the city’s Request and Affidavit form; research services are billed at $131.
- Belmont Permit Center
- Building Department page
- Permitting applications, forms and fees
- Building Permit Application
- Requirements for digital plans and documents
- Re-roofing application
- MEP application
- Owner-Builder Form
- Revision Statement
- Fire department application (SMC Fire)
- Inspections
- Instructions for online inspection scheduling
- Pre-qualified inspection and testing agencies
- Construction Time Limits Acknowledgement
- Noise ordinance notice
- Request and affidavit for copy of plans
- Residential Design Guidelines
- FY 26-27 Fee Schedule
- 2025 California Title 24 codes
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Belmont building permit FAQs
How long does plan check take in Belmont?
The Permit Center currently quotes 21 to 28 days, 5 to 14 days for resubmittals and revisions, and 30 to 45 days for a new building’s first review, plus up to 12 calendar days for initial processing.
How much is a re-roof permit?
$534 for a residential re-roof under the FY 26-27 schedule.
Does my addition need design review?
A ground-floor addition of 399 sq ft or less (Tier 1) needs only a building permit. Larger additions fall in Tier 2 or Tier 3, and every new home is Tier 3.
When is the walk-in counter open?
Monday, Wednesday and Thursday from 8:30 to 11:30 a.m.; appointments are available at other times by phone or email.
Who handles a new driveway apron or sewer lateral in the street?
Engineering, through a right-of-way permit; the Permit Center handles the work on private property.
Can a homeowner pull a permit?
Yes, an owner doing the work files the city’s Owner-Builder Form with the application.
What are the construction hours?
Weekdays 8 a.m. to 5 p.m. and Saturdays 10 a.m. to 5 p.m.; no work on Sundays or holidays.
What if work started without a permit?
The fee schedule charges twice the applicable permit fee when a stop work order is issued for work without permits.
Simplify Belmont permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Belmont sooner?
Let Alliance prepare, file, and track your Belmont permits while your crew stays on the job.
More California permitting guides
San Mateo County
Read guide →Burlingame
Read guide →Daly City
Read guide →Benicia Building Permit Guide
Read guide →Berkeley Building Permit Guide
Read guide →Beverly Hills Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Belmont permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.