To get a building permit in Auburn, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Auburn’s Building Division at City Hall, 1225 Lincoln Way, handles plan review, permits and inspections inside city limits, and every permit type can be applied for, paid and scheduled in the City’s Civic Access portal.

Authority: City of Auburn Building DivisionFees: Adopted schedule effective July 1, 2026Phone: 530-823-4211 ext. 136
Authority
City Building Division1225 Lincoln Way
Hours
Mon–Thu 8:00–5:00Closed Fridays
Plan review
65% of permit feeUp to three plan checks
Inspections
Ext. 389 by 4:00 p.m.Prior business day

Inside Auburn city limits, building permits come from the City’s Building Division at City Hall, 1225 Lincoln Way (530-823-4211, ext. 136), led by Building Official Michael Pinola. Every permit can be applied for, paid and printed online in Civic Access, and the office is open Monday to Thursday, 8:00 a.m. to 5:00 p.m. Under the fee schedule that took effect on July 1, 2026, a house re-roof is $195, a water heater change-out $129, and larger projects pay a valuation-based permit fee plus plan review at 65% of it.

What requires a building permit in Auburn?

The Building Division’s residential handout states the rule plainly: a building permit is required for all construction not specifically exempted by the California Building Code, and the plans must include the electrical, mechanical and plumbing work in the project. The City also publishes its own conditions for small sheds that can be built without a permit.

Permit needed

  • New homes, additions, remodels and changes of use
  • Re-roofs, siding and window or door replacements
  • Water heater and HVAC change-outs, panel upgrades and generators
  • Solar, battery storage and EV chargers
  • New pools, pool replastering and equipment change-outs
  • Retaining and masonry walls, and fences that need a permit
  • Temporary construction power and demolition

Shed with no permit

  • No power or plumbing
  • 120 square feet or less, single story, no taller than 15 feet
  • At least 10 feet from the house, including decks
  • Setbacks of 20 feet in front, 5 feet on the side and at least 5 feet at the rear
  • Not attached to another structure, not over easements, and not on an undeveloped lot

Even an exempt shed counts toward the City’s zoning limits: all structures together may cover no more than 35% of the lot, and accessory structures may take up no more than 30% of the required rear yard. An older version of the shed handout gives a 3-foot rear setback; the newer flyer says at least 5 feet and refers owners to Planning.

What Auburn decides and what the state holds

The City sets its own fees, zoning, design review and historic district rules, and its Fire Department enforces a local ember-resistant zone. Its design criteria for Auburn list a 20 psf ground snow load, an 85 mph design wind speed, seismic design category D and an elevation of about 2,000 feet. Contractor licensing remains with the state.

Auburn building department: who handles permitting

The Building Division handles plan review, issues building permits, performs inspections and enforces state and local building codes for property inside the City of Auburn. Land outside the city limits in unincorporated Placer County is permitted by the County, not the City.

Short on time to read all of this?

Get a free quote →
Auburn permit contacts
OfficeContact
Building DivisionCity Hall, 1225 Lincoln Way, Auburn, CA 95603; 530-823-4211, ext. 136
Building OfficialMichael Pinola
Office hoursMonday to Thursday, 8:00 a.m. to 5:00 p.m.; closed Fridays; permits issued 9:00 a.m. to 4:00 p.m.
Inspection requests530-823-4211, ext. 389, or Civic Access
PlanningWalk-in help Wednesdays 8:00 a.m. to noon and 1:00 to 5:00 p.m.; submittals by appointment
Public Works (encroachment, grading)530-823-4211, ext. 145
Fire prevention530-823-4211, ext. 182

Civic Access will be offline for maintenance on December 3, 2026.

Permit types in Auburn

The Planning page splits building applications in two. Basic residential and commercial permits that need no plan review, such as water heaters, re-roofs and electrical work, should be filed online and are issued quickly when the paperwork is complete. Projects that need plan review, such as new homes, new structures, additions, remodels and changes of use, can be filed online or in person.

Residential permits

The division’s forms page carries checklists for residential re-roofs, generators and solar, a deck handout, stair and handrail details, a smoke and carbon monoxide alarm sheet and an owner-builder form. Its residential handout notes that new homes must include fire sprinklers and solar, and that owners may draw plans for conventional construction themselves. Residential rooftop solar can be approved instantly through Symbium, which contractors and homeowners can both use, and then permitted in Civic Access. EV charger permits follow the City’s expedited ordinance; a complete application is deemed complete within five business days.

Commercial permits

The City requires plans by a California-licensed architect or engineer for most building projects. Its examples include new commercial buildings and additions, structural alterations, changes of occupancy, any accessibility work beyond signage, storage racks over 8 feet and alterations to exits or fire-rated construction. The division also publishes an accessibility cost worksheet, a deferred submittal application and a special inspection agreement.

What comes before the building permit

  • Planning approvals. Design review, use permits, administrative permits, variances and tree permits are handled by Planning; the Planning Commission hears larger cases.
  • Historic districts. In the Old Town and Downtown historic districts, the Historic Design Review Commission reviews new development, exterior additions and alterations, signs, materials and colors.
  • Fire. New buildings must keep a 5-foot ember-resistant zone clear of vegetation and combustibles under Municipal Code Section 100.87(D), and the Fire Department will not give final approval without it. Its Fire Hazard Severity Zone map is being updated.
  • Public Works. Encroachment, grading and transportation permits are applied for online, and a residential project may need an encroachment permit before issuance.
  • Schools. School fees go to the Auburn Union School District and Placer Union High School before the permit is issued.

Not sure this scope needs a permit?

Get a free quote →

Auburn permit fees

The City’s adopted Planning and Building Fee Schedule took effect on July 1, 2026. Common jobs have flat fees that already include plan review and inspection, with a $72 permit processing fee and state fees on top. New buildings, additions, tenant improvements and remodels use the valuation table, with plan review charged separately at 65% of the permit fee.

Building fees, schedule effective July 1, 2026
ItemFee
Residential re-roof or siding$195
Residential water heater or HVAC change-out$129
Panel upgrade, EV charger, generator or battery (residential)$174 each
Residential solar, 15 kW or less$347
Window or sliding door retrofit, up to 5$261
Fence needing a permit$174
Retaining or masonry wall under 6 feet$347
New swimming pool1.65% of valuation
Valuation $25,001 to $50,000$400 for the first $25,000 plus $14.00 per added $1,000
Valuation $50,001 to $100,000$750 for the first $50,000 plus $10.00 per added $1,000
Valuation $100,001 to $500,000$1,250 for the first $100,000 plus $9.38 per added $1,000
Electrical, mechanical or plumbing inspection10% of the base permit fee each
Plan review65% of the permit fee, up to three plan checks
Permit processing$72
Re-inspection after the first$87 each
After-hours inspection$208 per hour, 4-hour minimum
Temporary certificate of occupancy$254 per 90 days

Rather talk it over?

Call 1-855-478-4290 →

The smallest band ($1 to $2,000, $169) does not join the next one, which starts at $250 for the first $2,000. Revisions and extra plan review are $169 per hour, a permit extension is $174, and work done without a permit carries an investigation fee equal to the permit fee. Up to 80% of plan review or permit fees can be refunded before work starts, but nothing after 180 days.

Worked example. A remodel valued at $50,000 sits at the top of the $25,001 to $50,000 band: $400 plus 25 × $14.00 = $750. Plan review at 65% adds $487.50 and the processing fee $72, for $1,309.50. If electrical, mechanical and plumbing work are all included, each adds 10% of $750 ($75), bringing the total to $1,534.50, plus state fees of $6.50 (strong motion) and $2 (building standards), or $1,543.00.

Planning and other fees. Design review for an addition or alteration that goes to the Planning Commission is $1,327, administrative design approval $265 or $531, historic district review of an addition or alteration $750, and a tree permit for a single home $112 per tree up to $300. For new homes the residential handout, last revised in December 2024, lists a sewer connection fee of typically $8,615, a facilities and equipment fee of $2,750 and a Placer County facilities fee of $3,560.93, with park, traffic and sewer reimbursement fees possible if they were not collected at the final map.

Trade permits and who may pull them

The Building Division issues electrical, plumbing and mechanical permits along with building permits. Simple trade jobs have flat fees: $174 for a residential panel upgrade, EV charger or generator, and $129 for a water heater or HVAC change-out. In a larger project, each trade adds 10% of the base permit fee. Jobs with no valuation can be priced by the number of inspections, from $174 for one inspection plus $87 for each inspection past four.

When applying in Civic Access, contractors enter their state license number under the certificates section of their profile. Owner-builders complete the City’s Owner Builder Form, and the PEX certification form and gas line schematic on the forms page cover common trade details.

Every business operating in Auburn, contractors included, must hold a City business license and pay the business license tax under Chapter 33 of the Municipal Code; applications go through the City’s online business license portal.

Rather not deal with the building department?

Get a free quote →

How to apply for a building permit in Auburn

1. Check planning, historic and fire rules

Ask Planning whether you need design review, a use permit or Historic Design Review, and check the parcel against the Fire Department’s hazard zone and ember-zone rules.

2. Register in Civic Access

Log in or register, add your contractor license under your profile certificates, and pick the permit type.

3. Upload plans and documents

For plan-review projects, upload plans with site plan, elevations, structural, truss and energy calculations, and any soils or arborist report. Except for conventional construction an owner can draw, most projects need plans by a California-licensed architect or engineer.

4. Pay plan review

The plan check fee, 65% of the building permit fee, is due when plans are submitted.

5. Clear Public Works and school fees

Apply for any encroachment permit with Public Works and pay school district fees before issuance.

6. Pay and print the permit

Once approved, pay the permit, processing and state fees in Civic Access and print the permit for the job site.

Review, corrections and what causes delay

Plan review includes up to three plan checks; after that, extra review is billed at $169 per hour, and revisions to approved plans are filed with the Plan Revision Form and billed the same way. Common holdups are plans prepared by an unlicensed designer for work that needs a licensed professional, missing energy or structural calculations, unpaid school fees and a missing encroachment permit. The residential handout asks that no applications be made or permits issued after 4:00 p.m., and counter issuance runs from 9:00 a.m. to 4:00 p.m., Monday to Thursday.

Inspections in Auburn

Schedule inspections in Civic Access or by calling 530-823-4211, ext. 389, before 4:00 p.m. on the business day before. Inspections run Monday through Thursday only, so a Monday inspection must be booked by 4:00 p.m. Thursday. The daily route is posted after 8:30 a.m., with morning visits from 9:00 a.m. to noon and afternoon visits from 1:00 to 4:00 p.m. An older residential handout says to call before 8:00 a.m. on the day of the inspection; the inspection page is the current rule.

The first re-inspection is free; from the second on, each costs $87. Phased inspections are $87 each, and after-hours inspections cost $208 per hour with a four-hour minimum. Before a new building gets final approval, the Fire Department checks the 5-foot ember-resistant zone, and a temporary certificate of occupancy is available for $254 per 90 days.

Building code in Auburn

Auburn applies the state codes with its own municipal code provisions, including the fuel modification standards in Section 100.87 that create the ember-resistant zone for buildings built after July 10, 2024. Flood insurance: FEMA lists Auburn as a participating community in the National Flood Insurance Program, with a current flood map dated November 2, 2018.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Does Auburn issue its own building permits?

Yes. The City’s Building Division, led by Building Official Michael Pinola, reviews plans, issues permits and inspects work inside city limits. Unincorporated land around Auburn is under Placer County.

How much is a re-roof permit in Auburn?

Under the schedule effective July 1, 2026, a residential re-roof is $195, which includes plan review and inspection, plus the $72 processing fee and state fees.

Do I need a permit for a shed?

Not if it is 120 square feet or less, one story and no taller than 15 feet, has no power or plumbing, stands at least 10 feet from the house and meets the setbacks. It still counts toward the 35% lot coverage limit.

Can I apply online?

Yes. All permit types are available in Civic Access, where you can apply, upload documents, pay, print the permit and schedule inspections.

When are inspections done?

Monday through Thursday only. Book by 4:00 p.m. the business day before at ext. 389 or online; Monday inspections must be booked by Thursday.

Can I draw my own plans?

For conventional residential construction, yes. Most other projects, including new commercial buildings, structural alterations and changes of occupancy, need plans from a California-licensed architect or engineer.

What is the ember-resistant zone?

A 5-foot strip around any new building built after July 10, 2024 that must be kept clear of vegetation and combustibles. The building cannot pass final without it.

Auburn permit search and official resources

Civic Access shows your permit status, documents and inspections, and its daily inspection schedule lists the day’s route.

Inspections are where schedules slip.

Get a free quote →

Simplify Auburn permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Auburn sooner?

Let Alliance prepare, file, and track your Auburn permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Auburn permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.