Inside Lincoln, building permits come from the City’s Building Division in the Community Development Department, whose counter is on the second floor of City Hall, 600 Sixth Street (916-434-2470), open weekdays from 9:00 a.m. to 3:00 p.m. Re-roofs, water heaters, HVAC units and electrical jobs are usually issued over the counter or by email, while larger projects go through plan check that can take two to six weeks. Fees follow the Master Fee Schedule the City Council approved on May 26, 2026, effective August 1, 2026.
What requires a building permit in Lincoln?
The Building Division applies the code rule that no building or structure may be built, enlarged, altered, repaired, moved, removed, converted or demolished without a permit, and it publishes its own lists of what needs one and what does not.
Permit needed
- New homes, room additions, alterations and remodels
- All electrical and all plumbing work, including sewer lines
- Air conditioners, furnaces and water heaters
- Re-roofs, siding and termite or dry-rot repair
- Covered patios and decks more than 30 inches high
- Detached structures over 120 square feet
- Fences over 6 feet and retaining walls over 4 feet
- Pools, spas, solar units, signs and demolition
No permit
- Sheds and playhouses up to 120 square feet that meet zoning setbacks and height (patio covers are not exempt)
- Concrete walkways and patios not on an accessible route
- Retaining walls up to 4 feet with no surcharge
- Cabinet replacement, floor and window coverings
- Interior painting and wallpaper
- Shallow above-ground pools of up to 5,000 gallons (the City’s list prints the depth limit as both 18 and 24 inches)
Exempt work still has to meet homeowners association rules and City zoning and grading requirements, and exterior painting may need planning approval. The City’s page states that converting a garage into living space is strictly prohibited. Starting work without a required permit brings an immediate stop-work order, a permit application and an investigation fee of twice the permit fee.
What Lincoln decides and what the state holds
The City sets its fees, zoning and design criteria and requires a City business license for contractors. Its published design criteria are seismic design category D, exposure B, a soil capacity of 1,500 psf, no frost line or snow load, an 85 mph wind speed, a roof live load of 20 psf and energy Climate Zone 11. Local ADU rules are in Municipal Code Chapter 18.37, and contractor licensing stays with the state.
Lincoln building department: who handles permitting
The Building Division enforces the codes and ordinances the City has adopted and issues commercial, industrial and residential permits for property inside Lincoln city limits. Encroachment permits for work in streets come from the City’s Engineering staff.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Building Division counter | City Hall, 600 Sixth Street (2nd floor), Lincoln, CA 95648; 916-434-2470 |
| Counter hours | Monday to Friday, 9:00 a.m. to 3:00 p.m. (City Hall 8:00 a.m. to 5:00 p.m.) |
| Minor residential permits | OTCPermits@lincolnca.gov |
| Permit Center | cddpermitcenter@lincolnca.gov |
| Inspections | Citizen Portal, 916-434-2470 or the Permit Center, 8:00 a.m. to 3:00 p.m. |
| Engineering (encroachments) | 916-434-3233; drop box on the 3rd floor of City Hall |
| City Hall main line | 916-434-2400 |
Payments for processed applications can be made in the Accela Citizen Portal, which is also used to schedule inspections.
Permit types in Lincoln
The fee schedule has flat-fee permits for common stand-alone jobs, valuation-based permits for new buildings, additions, tenant improvements and remodels, and separate valuation tables for stand-alone electrical, mechanical and plumbing permits.
Residential permits
For a new home, renovation or added structure, file a Building Permit Application with three plan sets and the fee check at the counter. Minor residential permits can be emailed to OTCPermits@lincolnca.gov: re-roofs and HVAC changes (with energy documents), panel change-outs by licensed electricians, sewer, water or gas line work (with a site plan), window change-outs (with a floor plan and energy forms) and solar, storage and EV chargers. Residential rooftop solar and batteries can also get instant approval through Symbium, open to contractors and homeowners. Fire sprinkler systems need a Fire Systems Permit Application and a fire flow report first. Pre-approved ADU master plans are accepted in person, and a site-specific permit using one is approved or denied within 30 days of a complete submittal.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial permits need three plan sets with a cover page listing the designers and their stamps, a revision block, a vicinity view, occupancy and construction type, an accessibility data section, scope of work and any deferred submittals, on sheets of at least 18 by 24 inches. A letter of authorization from the property owner, not the tenant, is required. Some projects need plans from a California-licensed architect or engineer under the City’s stamp requirement handout.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning. Setbacks vary by zone; the Planning Division confirms them before you build or remodel.
- Fire. Fire plan review and inspection is charged at 75% of the base building permit fee where it applies, and sprinkler systems need a fire flow report.
- Encroachment. Work in the right-of-way needs an encroachment permit, a certificate of insurance naming the City ($1,000,000 per occurrence, $2,000,000 aggregate), a traffic control plan where streets or sidewalks are blocked, and a current City business license; inspections must be requested at least 72 hours ahead.
- Schools. The Western Placer Unified School District collects its school impact fee before the City issues a building permit.
Lincoln permit fees
The City Council approved the updated Master Fee Schedule on May 26, 2026, and it took effect on August 1, 2026, after a full cost-of-service study. Flat fees for common jobs include permit issuance, inspection and plan review. Valuation-based permits add a $78 issuance fee and plan review at 75% of the permit fee, paid when plans are submitted. For tenant improvements, remodels and additions, valuation is set at 50% of the ICC building valuation table where it applies.
| Item | Fee |
|---|---|
| Residential re-roof up to 2,000 sq ft | $357, plus $93 per added 1,000 sq ft |
| Residential HVAC, water heater, panel or line repair | $194 each |
| Residential solar, up to 15 kW | $450 all inclusive |
| Standard patio up to 200 sq ft | $310 ($403 over 200 sq ft) |
| New swimming pool or spa | $1,209 |
| Demolition | $279 |
| Valuation $10,001 to $50,000 | $465 for the first $10,000 plus $16.28 per added $1,000 |
| Valuation $50,001 to $100,000 | $1,116 for the first $50,000 plus $14.88 per added $1,000 |
| Valuation $100,001 to $500,000 | $1,860 for the first $100,000 plus $6.51 per added $1,000 |
| Electrical, mechanical or plumbing | 12% of the base permit fee each |
| Building plan review | 75% of the permit fee, up to three plan checks |
| Energy review | 5% of the building permit fee |
| Permit issuance | $78 |
| General Plan maintenance | $0.79 per $1,000 of valuation |
| Technology fee | 4% of the permit fee |
| Certificate of occupancy | $186 ($279 per 30 days if temporary) |
| Re-inspection after the second, or missed inspection | $93 each |
Rather talk it over?
Call 1-855-478-4290 →Expedited plan check is 1.5 times the standard fee, extra plan review after the third check is $186 per hour, after-hours inspections are $223 per hour with a four-hour minimum, and card payments carry a 3% pass-through charge.
Worked example. An addition valued at $100,000 sits at the top of the $50,001 to $100,000 band: $1,116 plus 50 × $14.88 = $1,860. Plan review at 75% adds $1,395 and issuance $78, for $3,333. With electrical, mechanical and plumbing work, each adds 12% of $1,860 ($223.20), for $4,002.60, before energy review, General Plan, technology, fire and state fees.
New homes. The residential fee sheet effective August 1, 2026 adds the impact and connection fees charged per dwelling unit, which differ by area: in Area 1, sewer connection is $12,258.75, water connection $3,086.56, traffic mitigation $6,666.10 and community services $10,029.53, plus a $261 park tax for a single-family home, a $2,872 Placer County capital facilities fee and a regional traffic fee of $3,376 to $4,638 by home size. Public Facilities Element fees follow Resolution 2026-077, effective August 1, 2026. ADUs over 750 square feet pay impact fees in proportion to the main home.
Trade permits and who may pull them
The Building Division issues electrical, mechanical and plumbing permits. Stand-alone trade permits have their own valuation tables, starting at $93 for work up to $2,000 and reaching $372 for the first $10,000 plus $12.40 per added $1,000; in a larger project each trade adds 12% of the base permit fee. Simple jobs such as water heaters, HVAC units and line repairs are $194 flat.
Permits are issued to the property owner, a licensed contractor or a certified agent of the owner. Property owners may do work on their own homes, with few exceptions, and the City publishes an owner-builder handout explaining the owner-as-worker, owner-as-contractor and owner-as-employer roles. Contractors must hold a current City of Lincoln business license, carry workers’ compensation and be bonded, and every subcontractor also needs a City business license and bond.
Rather not deal with the building department?
Get a free quote →How to apply for a building permit in Lincoln
Check setbacks and any planning, HOA, fire or encroachment needs before drawing plans.
Fill in the City’s application; for commercial work add the property owner’s authorization letter.
Email qualifying minor residential permits to OTCPermits@lincolnca.gov. For other work, bring three plan sets, documents and a check to the second-floor counter.
Building and planning plan check fees are collected when plans are submitted.
Resubmit corrected plans until they are approved; the City publishes a Revision or Resubmittal Application for this.
Pay Western Placer Unified School District fees, then the permit fees, which can be paid in the Citizen Portal once processed.
Review, corrections and what causes delay
The Building Division gives two to six weeks for plan check depending on size and complexity; some projects finish within two weeks. Plan review covers up to three checks, after which review is billed at $186 per hour, and expedited review costs 1.5 times the standard fee. Delays come from missing energy documents on minor permits, a missing owner letter on commercial work, a sprinkler application filed without a fire flow report, and an expired or missing City business license. Permits expire after one year without a final; a 180-day extension can be requested before the year ends.
Inspections in Lincoln
Schedule inspections in the Citizen Portal, by phone at 916-434-2470 or by email to the Permit Center, Monday through Friday from 8:00 a.m. to 3:00 p.m., at least one business day ahead. Every permitted job needs at least one inspection and most need at least seven: foundation, pre-slab or underfloor, shear and roof nailing, rough framing and trades, insulation, drywall and final. Water, gas and waste lines must be on test at the rough inspection.
Contractors must have a 1A-rated, OSHA-approved ladder (300-pound capacity) set up before HVAC and re-roof inspections. For any inspection where the owner is not represented, the homeowner must sign a Permission to Enter Property form; the City will not accept one signed by a contractor. The homeowner must be present for the final smoke and carbon monoxide alarm check, or sign the City’s alarm affidavit when no interior access is needed. A third or later re-inspection, or a missed inspection, costs $93, and the certificate of occupancy is $186.
Building code in Lincoln
Lincoln enforces the codes and ordinances adopted by the City, with its design criteria for seismic category D and Climate Zone 11 and its ADU rules in Municipal Code Chapter 18.37. Flood insurance: FEMA lists Lincoln as a participating community in the National Flood Insurance Program, with a current flood map dated November 2, 2018.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →Frequently asked questions
Does Lincoln issue its own building permits?
Yes. The City’s Building Division issues residential, commercial and industrial building permits for property inside Lincoln and inspects the work.
Can I get a permit over the counter?
Usually, for re-roofs, new HVAC units, water and gas line replacements, water heaters and electrical work. Many of these minor residential permits can also be emailed to OTCPermits@lincolnca.gov.
How much is a re-roof permit in Lincoln?
From August 1, 2026, a residential re-roof up to 2,000 square feet is $357, plus $93 for each additional 1,000 square feet, with issuance, plan review and inspection included.
Do I need a permit for a shed or fence?
A shed of 120 square feet or less that meets zoning setbacks and height needs no permit. The City’s list requires permits for detached structures over 120 square feet and fences over 6 feet.
Do contractors need a Lincoln business license?
Yes. Contractors and all subcontractors need a current City of Lincoln business license and must be bonded, and contractors must carry workers’ compensation.
How long does plan check take?
Two to six weeks, depending on the size and complexity of the project. Small jobs such as water heaters and re-roofs can sometimes be issued over the counter.
How long is a permit valid?
One year. Before it expires you can apply for a 180-day extension; an expired permit without a final inspection brings added fees to restore it.
Lincoln permit search and official resources
Permit status, payments and inspection scheduling are in the Accela Citizen Portal. Copies of building or engineering plans are requested with the City’s Affidavit for Permission to Copy Plans, emailed to the Permit Center.
Inspections are where schedules slip.
Get a free quote →- Lincoln Building Division: building and renovating
- Building permits: what needs one
- Residential permits
- Commercial and industrial permits
- Building inspections
- Accela Citizen Portal
- Master Fee Schedule
- Building fees, effective August 1, 2026 (PDF)
- Residential permit and impact fees, effective August 1, 2026 (PDF)
- Building permit fees and Public Facilities Element resolutions
- Owner-builder handout (PDF)
- Solar, energy storage and EV charger permits
- Pre-approved ADU plans
- Encroachment permits
- California Building Standards Code (Title 24)
Simplify Lincoln permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Lincoln sooner?
Let Alliance prepare, file, and track your Lincoln permits while your crew stays on the job.
More California permitting guides
Placer County
Read guide →Rocklin
Read guide →Roseville
Read guide →Lindsay Building Permit Guide
Read guide →Livermore Building Permit Guide
Read guide →Livingston Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Lincoln permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.