Outside its towns, Independence County issues no building permit and publishes no building code or inspection program of its own. For a rural build, the county’s offices are the County Judge, who runs the road system (870-793-8800), and the 911 Coordinator (870-805-0340). Inside Batesville, the Code Enforcement department permits building and trade work; Southside issues a Certificate of Zoning Compliance and Permit to Build, and Cave City issues building permits under its zoning code.
Who issues permits in Independence County?
The County Judge runs the county roads and carries out the ordinances the Quorum Court passes; the office is in the County Courthouse at 192 E. Main Street, Batesville. The county’s department list has no planning, zoning or building office. Populations below are Census Bureau Vintage 2025 estimates.
Short on time to read all of this?
Get a free quote →| Place | Who permits building work |
|---|---|
| Batesville (11,860), county seat | City Code Enforcement, Batesville Municipal Building, 500 E. Main Street; 870-698-2456. New houses: $15 plus $0.15 per sq ft under roof |
| Southside (4,274) | City of Southside: Certificate of Zoning Compliance and Permit to Build, signed by the City’s Code Enforcement Official; City Hall, 2181 Batesville Blvd; 870-569-1550 |
| Newark (1,184) | City of Newark: fence permits from the City’s Zoning Department (Ordinance 2025-06); ask City Hall (870-799-2663) about building permits |
| Pleasant Plains (348) | Town of Pleasant Plains: its posted ordinances include the sewer ordinance (Ordinance 2022-02), which requires a $50 building sewer permit from the sewer Superintendent before connecting to the public sewer; ask City Hall (501-345-2262) about building permits |
| Sulphur Rock (655), Cushman (447), Oil Trough (222), Magness (221), Moorefield (129) | The published sources do not say; ask the town |
| Cave City (182 in Independence; most of the city is in Sharp County) | City of Cave City: building permits for new construction or renovation, approved by the Mayor or the Mayor’s designee under the City’s Zoning Code (Ordinance 2025-04, version 2026-01), with a plot plan; City Hall, 201 S. Main Street; 870-283-5455 |
| Unincorporated Independence County | No county building permit; county roads through the County Judge and Road Department |
Not sure this scope needs a permit?
Get a free quote →Roads, addresses and flood maps in Independence County
- County road right-of-way: the right-of-way on county roads runs 25 ft from the centerline, and the Road and Bridge Department asks that no trees, shrubs or other plantings go inside it. The department builds and resurfaces county roads and cleans culverts and ditches; its office is on 870-793-8862.
- Driveways in Southside: Southside sends driveway questions to Independence County, and driveways or culverts on a state highway inside the city to the Arkansas Department of Transportation District 5 office (870-251-2374).
- Addresses: the county’s 911 Coordinator is on 870-805-0340; ask that office about the address for a new building. The Office of Emergency Management is on 870-307-8917.
- Flood maps: FEMA lists Independence County as a National Flood Insurance Program participant, with a current map dated March 15, 2012. The county’s website names no floodplain administrator; the County Judge’s office runs county administration. Batesville, Cave City, Moorefield, Newark, Oil Trough and Sulphur Rock also take part, and Batesville requires a Floodplain Development Permit for development in its flood hazard areas. Cushman, Magness and Pleasant Plains are listed as not participating, and Southside is not listed.
- Septic: where there is no sewer, the onsite wastewater permit comes from the Arkansas Department of Health through its local Environmental Specialist.
Southside’s rules: the City’s Zoning Code, revised May 18, 2026, makes the Mayor or the Mayor’s designee its Code Enforcement Official and records zoning compliance on every permit the City issues. The permit form commits the applicant to the Arkansas Energy Code and the 2021 Arkansas Fire Prevention Code, and a building may not be occupied until it meets City and State codes. Violating the zoning code is a misdemeanor: after the deadline in a notice of violation, a conviction brings a fine of up to $250 plus the costs of the case, and each further day counts as a separate offense.
Rather talk it over?
Call 1-855-478-4290 →Newark fences: under Ordinance 2025-06, anyone erecting, replacing or significantly altering a fence in Newark needs a fence permit from the City’s Zoning Department, with a plan showing height, material and location. Fences are limited to 6 ft unless the zoning commission approves more, and fines run $200, $300 and $500 for first, second and third offences.
Steps for building in Independence County
Check whether the lot is inside Batesville, Southside or another town; a Batesville mailing address does not mean the lot is in the city.
In Batesville, apply to Code Enforcement; in Southside, file the Certificate of Zoning Compliance and Permit to Build with City Hall.
No county building permit is needed; ask the county’s 911 Coordinator about the address before you build.
Keep trees and other plantings out of the 25 ft county right-of-way, and call the Road Department about work at a county road.
Without sewer, apply to the Arkansas Department of Health for the onsite wastewater permit.
Rather not deal with the Independence County building department?
Get a free quote →Arkansas building code
Arkansas’s building code is the 2021 Arkansas Fire Prevention Code, adopted by the State Fire Marshal and in force statewide since 1 January 2023; building permits are issued locally where a city or county runs a permit program, and the plumbing, gas, mechanical, energy and electrical codes are adopted by separate state agencies. The Arkansas codes
Independence County permit FAQs
Does Independence County issue building permits?
No. The county has no building permit or inspection program for land outside its towns. It handles county roads, 911 and emergency management.
Who issues building permits in Batesville?
The City’s Code Enforcement department at the Batesville Municipal Building, 500 E. Main Street (870-698-2456).
Do I need a permit to build in Southside?
Yes. Southside issues a Certificate of Zoning Compliance and Permit to Build for new homes, commercial buildings, additions and new businesses; call City Hall on 870-569-1550.
Who handles addresses for a new house in rural Independence County?
Ask the county’s 911 Coordinator, on 870-805-0340.
How wide is a county road right-of-way?
The county counts 25 ft from the centerline of the road, and it asks that nothing be planted inside that strip.
Who permits septic systems in Independence County?
The Arkansas Department of Health, through its local Environmental Specialist.
Want this handled start to finish?
Get a free quote →Official Independence County permit resources
- Independence County department directory
- Independence County Roads & Bridges
- Independence County Judge
- City of Southside documents: permit form, zoning code and zoning map
- Southside Certificate of Zoning Compliance and Permit to Build
- Southside Zoning Code (May 18, 2026)
- City of Newark Ordinance 2025-06, fences
- Cave City Planning Commission: zoning code and adopted codes
- Town of Pleasant Plains ordinances
- Arkansas Department of Health: Onsite Wastewater
- FEMA Community Status Book: Arkansas
Inspections are where schedules slip.
Get a free quote →Simplify Independence County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Arkansas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Independence County sooner?
Let Alliance prepare, file, and track your Independence County permits while your crew stays on the job.
More Arkansas permitting guides
This guide is provided by Alliance Permitting for general information about Independence County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.