In Centerton, the City’s Department of Building Safety reviews plans and issues building, electrical, plumbing, mechanical, pool, solar and demolition permits for property inside city limits (479-795-2750). A house valued at $200,000 pays a $760 building permit under Title 11, plus a trade fee set by square footage and a $4,023 impact fee that must be paid before the permit is released.
What needs a permit in Centerton?
Title 11 of the Centerton Municipal Code requires a City permit before anyone builds, places, remodels or repairs a house and its outbuildings, a multifamily building or any business, commercial, manufacturing or storage building inside the city, and for any other work the adopted codes put under permit.
Permits the department issues
- New homes, additions, remodels and repairs
- Garages, storage and shop buildings, pool houses and ADUs
- Covered patios, pavilions and outdoor kitchens
- Electrical, plumbing and mechanical (HVAC) work
- Solar installations and swimming pools
- Storm shelters (no fee, but a site plan and permit are required)
- Demolition and house moving
- Commercial buildings, tents and fireworks stands
Separate City approvals
- Grading and erosion control permits, filed in the iWorQ portal and paid at City Hall
- Floodplain development permits from the Floodplain Administrator
- Planning review for garages with living quarters, ADUs and pool houses with living space
- Fire inspections by the Fire Marshal or Fire Chief
- Backflow (RPZ) devices and yard hydrants under Centerton Utilities rules
No building permit issues for a lot until the City has approved a final plat, it is recorded with Benton County and the Fire Chief has assigned a 911 address.
Who issues building permits in Centerton?
The Department of Building Safety handles permitting, plan review and inspections for construction inside the corporate limits and issues certificates of occupancy. Robert Coffelt is the Building Official. Fire inspections are separate: the Fire Marshal, Fire Chief or a designee carries them out.
| Detail | Information |
|---|---|
| Phone | 479-795-2750: permit clerk ext. 203, deputy building official ext. 202, Building Official ext. 201 |
| buildingsafety@centertonar.gov | |
| City of Centerton, Department of Building Safety, P.O. Box 208, Centerton, AR 72719 | |
| Inspections | BSA Online web portal (access details come with the permit) |
| Grading permits | iWorQ portal; payment at the City Hall Finance Department |
Short on time to read all of this?
Get a free quote →According to the Mayor’s State of the City report to the council in March 2026, the City issued 2,970 permits and completed 11,822 inspections in 2025.
Centerton permit applications
Title 11 requires applications in digital form, emailed or delivered on a USB thumb drive (discs are not accepted), with building plans and a site plan. The department posts separate 2026 forms for each permit type:
- Residential Building Permit packet (revised January 6, 2026), with the builder checklist and the electrical, mechanical and plumbing contractor page.
- Commercial Building Permit application, plus commercial electrical, mechanical-HVAC and plumbing permits.
- Residential electrical, mechanical, plumbing and solar permit applications.
- Swimming pool, storm shelter and demolition permits.
The residential packet asks for the builder’s licence number, general liability and workers’ compensation, and the master licensee for each trade. It also states the department’s own rules: OSB is the only sheathing allowed without engineered plans, and retaining walls and crawl spaces need an engineer’s design.
Centerton permit fees
Section 11.20.03 of the Municipal Code sets the fees. Building Safety values a structure with the ICC Building Valuation Data table, which is updated every six months, and applies the “Building Permit Fee Schedule 2019” restated by Ordinance 2023-47:
| Valuation | Fee |
|---|---|
| $1,000 or less | No fee unless an inspection is needed; then the $50 single-phase fee applies |
| $1,000.01–$50,000 | $50 for the first $1,000 plus $5 per additional $1,000 |
| $50,000.01–$100,000 | $260 for the first $50,000 plus $4 per additional $1,000 |
| $100,000.01–$500,000 | $460 for the first $100,000 plus $3 per additional $1,000 |
| Over $500,000 | $1,660 for the first $500,000 plus $2 per additional $1,000 |
The bands do not join up at $50,000 (the first band would reach $295 there, the second starts at $260), so work out a fee inside one band. A house valued at $200,000, for example, pays $460 plus 100 × $3, or $760.
New homes also pay electrical, mechanical and plumbing fees with the building permit, collected from the general contractor before the permit is released:
Not sure this scope needs a permit?
Get a free quote →| House size | Fee |
|---|---|
| Up to 1,500 sq ft | $100 per trade, $300 for all three |
| 1,501–2,000 sq ft | $115 per trade, $345 for all three |
| 2,001–3,000 sq ft | $130 per trade, $390 for all three |
| Over 3,000 sq ft | $155 per trade, $465 for all three |
| Project | Fee |
|---|---|
| Demolition | $100 plus a $500 cleanup deposit (20-yard dumpster required) |
| House moving or manufactured home | $100 plus a $500 cleanup deposit and proof of the ARDOT permit |
| Swimming pool | $200 |
| Backflow prevention / RPZ | $50 |
| Single-phase or miscellaneous permit | $50 |
| Tent, fireworks stand or haunted house | $50 |
| Permit renewal or extension; reinspection | $50 each |
| Change of trade contractor | New permit plus $50 |
| Certificate of occupancy deposit (when required) | 50% of the building permit fee, refunded at the CO |
| Work started without a permit | Fees doubled |
Impact fees. Title 16, Chapter 16.16 charges impact fees for police, fire, parks and roads. They are worked out at application and paid before the building permit is issued: $4,023 per single-family home ($232 police, $751 fire, $2,110 parks, $930 roads) and $2,135 per multifamily unit. Per 1,000 sq ft, retail pays $4,881, institutional $4,072, office $1,954 and industrial $865.
So a 2,000 sq ft house valued at $200,000 would owe $760 for the building permit, $345 in trade fees and $4,023 in impact fees, or $5,128, before grading and utility charges. Permit fees are not refunded once collected.
Electrical, plumbing and HVAC permits in Centerton
Building Safety issues the trade permits too. On a new house the general contractor pays all three trade fees with the building permit, but each trade must name its master licensee and licence number on the application. A backflow preventer or RPZ needs its own plumbing permit, pulled by a licensed plumber, and replacing a trade contractor means a new permit for the new firm and a $50 fee.
Rather talk it over?
Call 1-855-478-4290 →| Permit | Fee |
|---|---|
| Commercial electrical | $50 base plus bid or valuation × 0.01 for jobs up to $10,000, × 0.005 for $10,000.01–$20,000, or × 0.0025 above $20,000; education fee valuation × 0.0005 |
| Commercial mechanical | $50 base plus valuation × 0.005; education fee valuation × 0.0005 |
| Commercial plumbing | $50 base, $3 per fixture, $7 per yard line and $7 per in-house water or drainage piping item |
Title 11 adds local rules for the trades. Electrical work follows the National Electrical Code; the City’s code book now names the 2026 edition (Ordinance 2026-36, on the October 13, 2026 council agenda), while the Building Safety web page and the January 2026 packet still list the 2020 NEC. Centerton bans 10-ampere branch circuits in all homes and requires at least 14 AWG copper (12 AWG aluminum) for fixed branch-circuit wiring. Potable water piping, PEX included, may not run in attics or other spaces exposed to freezing unless it is part of an approved sprinkler system. Dryer vents must exit above the slab, never through PVC or under the slab. Carbon monoxide detectors must be hard-wired on every floor.
What to submit
New house
- All pages of the permit application
- Full-size building plans as a PDF; no mirrored or handwritten plans
- Engineer-designed crawl space plans where a crawl space is built
- Site plan showing setbacks, easements, utilities, drainage arrows, septic, inlets, storm drains, light poles and hydrants
- HVAC load and duct calculations (Manual J and Manual D)
- Septic approval form with the signed application and site plan, where septic is used
- Contractor licence, general liability and workers’ compensation
Commercial
- Commercial building permit application
- Full plan set stamped by an architect or engineer
- Signed Arkansas Department of Health approval letter
- Arkansas contractor’s licence
- General liability and workers’ compensation, if applicable
- COMcheck energy compliance
Rather not deal with the building department?
Get a free quote →The application asks for heated, unheated and basement square footage, the subdivision minimum, setbacks and the minimum finished floor elevation from the plat. If the lot is in a floodplain, the Flood Manager must approve it before the permit is reviewed. Footings may not reach into the setbacks.
How to get a Centerton building permit: 6 steps
The lot must be inside city limits on a recorded final plat with a 911 address.
If the lot is in a floodplain, get the Flood Manager’s approval and a floodplain development permit; file any grading permit in iWorQ.
Complete every page of the 2026 application, with PDF plans, the site plan, Manual J and D, septic approval and insurance.
Send it to buildingsafety@centertonar.gov or deliver it on a USB drive.
Building, trade and impact fees are due before the permit is released; the permit is then valid for 180 days.
Give 24 hours’ notice (48 hours in busy periods) and pass the final inspection before anyone moves in.
Centerton inspections
All inspection requests go through the BSA Online portal, using the access details Building Safety provides; the permit clerk can resend them. Violations found in the field are noted in BSA and emailed to the people listed on the permit. Title 11 asks for 24 hours’ notice, or 48 hours when construction is heavy, and lists these inspections:
- Foundation, once trenches are dug, forms are up and steel is placed. Rebar is required in every foundation, even where an engineer’s design omits it.
- Slab, after under-slab plumbing passes, with wire mesh and vapor barrier in place and lapped at least 6 inches.
- Framing, when framing, electrical rough-in, plumbing top-out and the heating and air system are complete, before insulation.
- Yard lines for water, sewer, gas and electric before trenches are backfilled.
- Final, before occupancy. The building may not be used until the occupancy permit is issued.
A 911 address sign must be posted before permanent electric service is approved. The department warns that its plan review may not catch every code issue, and passing plan review does not excuse work that fails in the field.
Want this handled start to finish?
Get a free quote →Local rules that matter in Centerton
Floodplain: Title 16 names the Mayor or a designee as Floodplain Administrator. A floodplain development permit is needed for any development in a Special Flood Hazard Area, for new development that drains stormwater straight into one, and for new development within 100 feet of one. In AE zones a new home’s lowest floor must be at least 3 feet above the base flood elevation, documented on an elevation certificate. Nonresidential buildings are elevated 3 feet or floodproofed up to 4 feet above it. Centerton takes part in the National Flood Insurance Program and in FEMA’s Community Rating System at class 7.
Accessory structures: the department’s FAQ says permanent accessory buildings may not stand in front of the house or in side yards and must stay at least 7 feet from the rear property line and off easements and Master Street Plan right-of-way.
Where City permits apply: Title 11 building permits cover land inside the Centerton city limits; land outside them is not under City permitting.
Other City rules: outdoor lighting must meet Chapter 15.12, and Centerton Utilities publishes its own backflow, RPZ and yard hydrant installation requirements.
Arkansas building code
Arkansas’s building code is the 2021 Arkansas Fire Prevention Code, adopted by the State Fire Marshal and in force statewide since 1 January 2023; building permits are issued locally where a city or county runs a permit program, and the plumbing, gas, mechanical, energy and electrical codes are adopted by separate state agencies. The Arkansas codes
Centerton permit FAQs
Who issues building permits in Centerton?
The City’s Department of Building Safety, reachable at 479-795-2750 and buildingsafety@centertonar.gov. It issues building and trade permits and certificates of occupancy inside city limits.
How much is a building permit for a new house in Centerton?
The building permit for a house valued at $200,000 is $760. A 2,000 sq ft house adds $345 in trade fees and the $4,023 impact fee, for $5,128 in total.
Do I need a permit for a covered patio or a shed?
Yes. The department’s FAQ lists covered patios, pavilions, garages and storage or shop buildings as projects that need a permit application.
How do I schedule an inspection?
Through the BSA Online portal, at least 24 hours ahead, or 48 hours when construction is heavy.
How long is a Centerton permit good for?
180 days from issue. A renewal or extension costs $50.
Inspections are where schedules slip.
Get a free quote →What if my lot is in a floodplain?
Contact the Flood Manager first; the permit will not be reviewed until the floodplain approval is in place, and in an AE zone a new house’s lowest floor must be at least 3 feet above the base flood elevation.
Official Centerton permit resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Centerton Department of Building Safety
- Centerton residential building permit packet (January 2026)
- Centerton commercial building permit application (2026)
- Building Safety frequently asked questions (2025)
- Centerton Municipal Code Title 11, Buildings and Construction
- Centerton Municipal Code Title 16, Drainage, Flood and Impact Fees
- Centerton flood information and floodplain permit forms
- Centerton Municipal Code Book
Simplify Centerton permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Arkansas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Centerton sooner?
Let Alliance prepare, file, and track your Centerton permits while your crew stays on the job.
More Arkansas permitting guides
This guide is provided by Alliance Permitting for general information about Centerton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.