Outside its cities and villages, Iowa County requires a county permit from the Office of Planning and Development, 222 North Iowa Street, Suite 1223, Dodgeville (608-935-0333), for almost any construction or structural alteration; Scott Godfrey is the Planning and Development Director. County zoning is in force in all 14 towns. The county does not hold state dwelling code delegation: every town, village and city is delegated itself, so the building permit and inspections for a new house come from the local inspector, after the county permits.
What requires a county permit in Iowa County?
The county’s permit packet puts it plainly: a permit is required for almost any construction of or alteration to a structure outside a village or city, and a county permit is required even where the town has its own building permit. Under Section 2.3 of the zoning ordinance, no building, sign or other structure may be built, placed or enlarged, and no building’s use changed, without a county zoning permit.
County permit needed
- New houses and other new buildings, priced by footprint
- Additions, and structural alterations or repairs
- Pools, grain bins, tanks and open decks
- Changes of use, signs and towers
- Septic systems and privies (sanitary permit)
- Work within 300 feet of a navigable stream or 1,000 feet of a lake (shoreland), or in or near a mapped 100-year floodplain
- Development within 3 miles of the Iowa County Airport
- Portable livestock shelters up to 300 square feet (permit, no fee)
No county zoning permit
- Minor structures: a non-residential accessory building of 100 square feet or less
- Anything inside a city or village, which zones for itself
What the county decides and what the state holds
The county zones the towns (all 14 adopted county zoning by 1980), regulates shoreland, floodplain and airport areas, permits septic systems and runs land division review, nonmetallic mining, manure storage and wind and tower siting. Cities and villages are outside county zoning. Construction standards for houses and commercial buildings are state codes; DSPS’s UDC delegated-agent list, current as of September 24, 2026, shows no county delegation, so the dwelling code is enforced by each municipality’s inspector. The county packet itself says local permits may be required under the Uniform Dwelling Code and asks owners to check.
Iowa County building department: who handles permitting
The Office of Planning and Development receives applications and issues building and zoning permits under the county ordinance, plus sign, land use and conditional use permits, inspects permitted sites and enforces the ordinances. A sanitarian, who is also the assistant zoning administrator, handles septic permits. Rezonings and conditional uses go through the county’s Planning and Zoning Committee with town input, and variances and appeals through the Board of Adjustment.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Office of Planning and Development, 222 North Iowa Street, Suite 1223, Dodgeville, WI 53533 |
| Phone | 608-935-0333 or 608-553-7575; sanitarian 608-935-0330; fax 608-935-0326 |
| Hours | Monday to Friday, 8 a.m. to 4:30 p.m. |
| Director | Scott Godfrey, Planning and Development Director |
| County highway access | Iowa County Highway Department, 608-935-3381 |
| Municipality | Who issues UDC permits |
|---|---|
| Cities of Dodgeville (5,076) and Mineral Point (2,555) | Each delegated; Mineral Point lists General Engineering |
| Town and Village of Arena | Each delegated; DSPS lists Johnson Inspection, LLC |
| Town of Clyde; Villages of Avoca and Montfort (part) | Delegated; DSPS lists General Engineering |
| Villages of Barneveld, Hollandale and Blanchardville (part) | Delegated; DSPS lists Total Inspection Services |
| Towns of Brigham, Dodgeville, Eden, Highland, Linden, Mifflin, Mineral Point, Moscow, Pulaski, Ridgeway, Waldwick and Wyoming | Each delegated; ask the town clerk for its inspector |
| Villages of Cobb, Highland, Linden, Rewey and Ridgeway; Livingston and Muscoda (small parts) | Each delegated; ask the village for its inspector |
Iowa County permit types
One application packet covers the county zoning permit, the airport-affected permit and the shoreland and floodplain permits. The application asks for the footprint, height and approximate value, distances to lot lines, the road centerline, other buildings and the septic system, a plot plan (an aerial photo works best, and the office can supply one) and a labeled floor plan.
Residential permits
- New houses need, in order, the town’s driveway approval, a county sanitary permit, a town official’s signature confirming the building site, then the county zoning permit and an address number. The town’s own building permit and UDC inspections follow.
- Additions and accessory buildings are priced by footprint; only non-residential buildings of 100 square feet or less are exempt.
- Decks, pools and bins count as structures that are not buildings ($150).
- Anything with plumbing or a water connection, even an accessory building, needs a sanitary permit first.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and business buildings in the towns take the same county zoning permit by footprint, and many uses need a rezoning or conditional use permit first. The land use change application ($750) is due by the first Friday of the month and must carry a written recommendation from the affected Town Board, because every town has an adopted comprehensive plan the county must follow. A rezoning is heard by the Planning and Zoning Committee and takes effect only after the County Board acts, usually the following month; no construction permit can issue before then. A conditional use needs only the committee’s action. Wind energy systems, mobile towers, manure storage facilities and nonmetallic mines have their own county permits and ordinances. Building plan review for commercial buildings is a state matter (DSPS or a delegated municipality), not the county’s.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Pre-application talk. The county asks applicants to discuss every project with its staff first to find zoning, subdivision or site issues.
- Driveway. The Town Board approves new driveways, or existing ones newly serving open land, before the county permit; county and state highway accesses may also need Highway Department or WisDOT approval.
- Sanitary permit. No zoning permit is issued for a structure with plumbing until the sanitary permit is issued.
- Shoreland and floodplain. Shoreland and floodplain permits cost $200 each, or $500 with a special exception and public hearing.
- Land division. Creating a lot under 40 acres, whether sold or kept, generally needs a certified survey map reviewed under the county subdivision ordinance.
- Road setbacks. Buildings must sit 110 feet from the centerline of a state or federal highway (50 feet from the right-of-way), 75 feet from a county trunk highway (42 feet) and 63 feet from a town road (30 feet), unless the district’s yard rule is larger.
Iowa County permit costs and fees
Zoning permit fees are printed in the county’s Zoning, Floodplain and Shoreland Permit Application Packet, with checks payable to Iowa County Planning. The fee depends on the footprint of the structure or use, not its value.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| Footprint up to 999 sq ft | $150 (non-residential 100 sq ft or less may need no permit) |
| Footprint 1,000–1,999 sq ft | $250 |
| Footprint 2,000–4,999 sq ft | $350 |
| Footprint 5,000 sq ft or more | $500 |
| Structure that is not a building (pool, bin, tank, open deck) | $150 |
| Structural alteration or repair with no measurable footprint | $75 |
| Use or activity with no new or converted structure | $150 |
| Permit revision or change in use of an existing building | $75 or the difference between categories, whichever is greater |
| Shoreland or floodplain permit | $200 each; $500 with special exception and hearing |
| Address sign | $75 per sign |
| Airport zoning review | $75 inside county general zoning; $150 outside |
| Rezoning or conditional use application / Board of Adjustment variance or appeal | $750 / $750 |
| Permit obtained after the fact | Triple fee first offense; quadruple second; quadruple plus citation third |
Worked example from the packet: a new house with a 1,800-square-foot footprint pays $250 for the zoning permit and $75 for the address sign, or $325, before the sanitary permit and the town’s building permit. After-the-fact penalties follow the property owner, not the parcel, and each offense is cleared after 36 months without another. Owners rebuilding after a natural disaster may ask the Planning and Zoning Committee to reduce or waive the fee. Sanitary permit fees are set by County Board resolution; ask the sanitarian for the current amount.
Trade permits and who may pull them
The county does not issue electrical, plumbing or HVAC permits; inspection of houses and their systems under the dwelling code is done by the municipality’s delegated inspector. The county’s trade role is the septic system:
Rather not deal with the Iowa County building department?
Get a free quote →- Sanitary permit: filed on the state sanitary permit application and signed by the licensed master plumber who takes responsibility for the installation; renewals, revisions, plumber changes and transfers go through the plumber.
- Contractor lists: the county posts a list of certified soil testers, plumbers and pumpers.
- Privies: need their own county sanitary permit and agreement.
- Permit life: under the county sanitary ordinance, a sanitary permit for a system not yet installed and approved expires two years after issue; the plumber can renew it for another two years before it lapses, and an expired permit must be replaced before work starts.
- Maintenance: every septic tank must be visually inspected and pumped within three years of installation or inclusion in the county inventory and at least every three years after that, unless the tank is found less than one-third full of sludge and scum; pumping is done by a certified septage servicing operator. In its 2025 cycle the county sent 1,517 maintenance notices and issued 217 citations, and its annual report counts 7,460 sanitary permits issued since the program began and about 4,890 active private systems.
For a new house, the state Dwelling Contractor certification and the state electrician and plumber licenses apply and are checked by the local building inspector, not the county.
How to apply for permits in Iowa County
Confirm the parcel’s zoning and any subdivision or site restrictions before drawing plans.
The Town Board’s driveway approval, and for a new house or first building a town official’s signature on the building site.
Your plumber files it; it must be issued before the zoning permit for anything with plumbing.
Plot plan, floor plan, footprint, setbacks, and the shoreland or floodplain section if water is near.
Keep it on the premises during construction.
Contact the town’s inspector for the UDC permit and inspections.
Review, corrections and what causes delay
Under Section 2.3 the county must grant or deny a complete application in writing within 30 days. The packet says missing information is the most common reason for denial and delay. A permit lasts 24 months with no extension; after that a new permit is needed to continue. Starting before the permit is a citable violation: work must stop, a late permit with penalty fees must be sought, and if it cannot be issued the site must be restored.
Inspections in Iowa County
The county inspects each permitted project for compliance with the application and its approved use, and no new or altered building may be occupied until the county issues a Certificate of Compliance. It is the applicant’s job to notify the office when the project is ready for that inspection. Septic systems are inspected under the sanitary permit: the plumber in charge gives notice for the final inspection and arranges access, the system stays open until the county has inspected and accepted it, and a reinspection fee applies when a recheck is needed.
Want this handled start to finish?
Get a free quote →Footing, framing, electrical, plumbing and final inspections under the dwelling code are done by the town, village or city inspector who issued the building permit.
Wisconsin building code in Iowa County
Iowa County has no UDC delegation; every municipality in the county enforces the dwelling code itself. FEMA’s Community Status Book lists Iowa County (community 550522) as participating in the National Flood Insurance Program, with flood maps effective December 16, 2015, and the county floodplain ordinance (400.03A, 2023) covers mapped Zone A areas in the towns. The county reported no ordinance revisions in 2025.
Wisconsin's Uniform Dwelling Code covers one- and two-family homes. Its Commercial Building Code covers public buildings, workplaces and buildings of three or more units. Local ordinances must conform to both. Wisconsin rules
Iowa County permit search and official resources
The zoning ordinance requires the office to keep a record of all permits for public inspection; ask Planning and Development at 608-935-0333 for a parcel’s permit, sanitary or zoning history.
- Planning and Development applications, forms and documents
- Zoning, floodplain and shoreland permit application packet with fees
- Iowa County Zoning Ordinance
- County land use ordinances
- Sanitation information and septic permits
- Iowa County Sanitary Ordinance
- Planning and Development FAQ: county zoning
- Planning and Development annual report, 2025
- DSPS UDC delegated agents list
- FEMA Community Status Book, Wisconsin
Inspections are where schedules slip.
Get a free quote →Iowa County permit FAQs
Does Iowa County issue building permits?
It issues county zoning permits, which its ordinance also calls building permits, for nearly all construction in the towns. The state dwelling code permit and inspections come from the town, village or city inspector.
Do I need a county permit if my town issues a building permit?
Yes. The county permit is required regardless of any town permit, and it controls whether, where and how a structure may be built and used.
How much is a county permit for a new house?
It depends on the footprint: $150 up to 999 square feet, $250 to 1,999 and $350 to 4,999, plus $75 for an address sign.
Does a small shed need a permit?
Not if it is a non-residential accessory structure of 100 square feet or less; larger ones need a zoning permit.
How long is a county permit valid?
24 months from issue, with no extension; a new permit is needed to finish after that.
What happens if I build first and apply later?
The permit costs three times the normal fee for a first offense, four times for a second, and a third brings a citation as well.
Does county zoning apply in Dodgeville or Mineral Point?
No. Cities and villages have their own zoning, and the county has no zoning jurisdiction there.
Simplify Iowa County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Wisconsin. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Iowa County sooner?
Let Alliance prepare, file, and track your Iowa County permits while your crew stays on the job.
More Wisconsin permitting guides
Grant County
Read guide →Dane County
Read guide →Sauk County
Read guide →Jackson County Building Permit Guide
Read guide →Janesville Building Permit Guide
Read guide →Jefferson County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Iowa County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.