Port Orchard, Washington Building Permit Guide

To get a building permit in Port Orchard, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Port Orchard Permit Center, part of the Department of Community Development, issues building, fire code, plumbing and mechanical permits for the city and takes every application electronically; electrical permits come from Labor and Industries.

Authority: Port Orchard Permit CenterCode: 2021 IBC and IRC (POMC 20.200)Phone: 360-874-5533
Authority
Permit Center720 Prospect Street
House review
4 to 8 weeksFirst round, City estimate of June 9, 2026
Plan review
65% of permit feeResolution 022-25
Inspections
SmartGov portal onlyRequest by 3:30 p.m.

Inside the city limits, the Port Orchard Permit Center in the Department of Community Development takes in and issues building, fire code, public works and land use permits, and its Building Official also acts as fire code official. Applications are accepted only in electronic form, and inspections are booked only through the SmartGov portal. Fees follow Resolution 022-25, in effect since May 3, 2025, with plan review charged at 65% of the building permit fee; electrical permits are bought from the state Department of Labor and Industries (L&I), which serves Kitsap County from its Silverdale office on Kitsap Mall Boulevard.

The Permit Center works from 720 Prospect Street, with mail going to City Hall at 216 Prospect Street, and answers 360-874-5533; City Hall is open 8 a.m. to 4:30 p.m. on weekdays. Nick Bond is the Director of Community Development. Port Orchard had 19,839 residents in the Census estimate for 2025, and Kitsap County handles permits on unincorporated land around it.

What requires a building permit in Port Orchard?

Construction permits are Type I decisions under the Port Orchard Municipal Code (POMC). Chapter 20.200 adopts the state codes and then rewrites the exempt-work lists of both the building code and the residential code, so the Port Orchard lists below replace the model ones.

Permit required

  • New homes, ADUs, duplexes, townhouses, manufactured homes and additions
  • Remodels, basement finishes and garage conversions
  • Decks over 200 sq ft, higher than 30 inches, attached to the house or serving a required exit door
  • Fences over 6 feet and retaining walls over 4 feet
  • Re-roofs over 2,100 sq ft or with new sheathing or structural work
  • Siding over 1,000 sq ft or with structural work; windows and doors
  • Plumbing, mechanical, roof-mounted solar, signs and demolition

No permit (POMC 20.200.014)

  • One-story detached accessory buildings up to 200 sq ft (storm shelters excluded)
  • Fences up to 6 feet
  • Retaining walls up to 4 feet without a surcharge
  • Detached decks up to 200 sq ft and 30 inches high that do not serve a required exit
  • Re-roofing up to 21 squares over existing sheathing
  • Sidewalks, driveways, playground equipment and finish work

What the city decides and what the state holds

The building codes are the 2021 editions adopted through the State Building Code Council, and POMC 20.200.008 lists them with Port Orchard’s additions: appendix B and E of the building code, appendix M (home day care) of the residential code, the Wildland-Urban Interface Code, the energy codes and the property maintenance code. The local choices are the shorter exempt lists (sheds over 120 sq ft at commercial sites need a permit), 6-foot fences instead of 7, the re-roof and siding allowances, sprinklers in assembly, business, factory, mercantile and storage fire areas over 10,000 sq ft, and the fire access road rules in POMC 20.200.016.

Short on time to read all of this?

Get a free quote →

Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington

Port Orchard building department: who handles permitting

The Permit Center is the intake desk for every city approval: zoning and land use, environmental review, construction, fire code compliance, utility connections, site development and work in the right-of-way. Staff check that a submittal is complete, route it to Planning, Building, Fire, Addressing, Engineering and Public Works, collect fees when the permit is ready and schedule inspections.

Port Orchard permitting contacts
DetailInformation
Permit Center720 Prospect Street, Port Orchard; mail to 216 Prospect Street, Port Orchard, WA 98366
Phone360-874-5533
City Hall hoursMonday to Friday, 8 a.m. to 4:30 p.m.
Online servicesSmartGov public portal for inspection requests and results; Camino application portal until the new portal opens
Electrical permitsWashington Department of Labor and Industries
Septic reviewKitsap Public Health District, 360-728-2235

The City is changing its software. In a message posted on October 5, 2026, Director Nick Bond said a new online portal will open before the end of 2026, replacing the split between SmartGov, used for workflow, and Camino, used for applications. Until it does, the Permit Center asks anyone who cannot find an online link for a permit type to email it for other submission instructions.

Permit types

Residential permits

The building forms page has separate online applications for an ADU, a residential building permit, residential plumbing and mechanical work, siding, windows and doors, solar panels, roofing, retaining walls, demolition and manufactured homes. Builders who repeat a design can register a basic plan: after one full review, each later house, ADU, townhouse or duplex built from it pays a $225 reduced plan review instead of the full one, and pre-approved ADU plans work the same way. Plans cannot be reused after a code update unless they are reviewed again.

For new single-family homes, the City is running a free, optional prescreening pilot for one year from July 9, 2026: a third-party service checks plans against the 2021 residential code before you submit and flags common errors. It does not replace the City’s own plan review.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial work uses the commercial tenant improvement, multifamily, and commercial plumbing and mechanical applications. A new business moving into an existing space needs a certificate of occupancy whenever the tenant changes, with or without construction; exceptions in POMC 20.200.012 include R-3 dwellings, a second business with the same use classification, and a change of owner or name with no change of use or structure, which the Permit Center records on an updated certificate. The tenant certificate costs $75 and a revised one $60. The Permit Center offers a free 30-minute walk-through with the Building Official and other staff before you sign a lease. Fire alarm, sprinkler, hood and standpipe permits are priced on contract cost through the same valuation table and may go to a contract reviewer.

What comes before the building permit

Land use steps sit in Title 20 of the code: a pre-application meeting ($150), SEPA review, the Shoreline Master Program (a shoreline exemption letter is $150, a shoreline substantial development permit $900 plus hearing examiner costs), critical areas review in chapter 20.162 (an exemption request is $135), flood rules in chapter 20.170, and land disturbing activity and stormwater permits in chapters 20.140 and 20.150, which can also set the life of the building permit. New homes need a Capacity Reservation Certificate for water, sewer and transportation ($460 for all three, including the technology fee), or availability letters if West Sound Utility District or Bremerton Utilities serves the lot.

On a septic lot, Kitsap Public Health District reviews the project before the City issues the permit: a Building Site Application when the work adds bedrooms or wastewater, or a Building Clearance Application for most other new structures and additions. The district exempts re-roofs, window, deck or siding replacement and remodels that add no bedrooms.

Port Orchard permit costs and fees

Resolution 022-25, effective May 3, 2025, is the fee schedule for Community Development and Public Works. Valuation comes from the ICC building valuation data (the February 2025 table) or, for alterations, from the contractor’s bid; for work you do yourself, the construction cost is the price of materials, plus the fair market value of donated or found materials, times two.

Rather talk it over?

Call 1-855-478-4290 →
Port Orchard building fees (Resolution 022-25, effective May 3, 2025)
ItemFee or rule
$1 to $500 of value$36
$501 to $2,000$36 for the first $500, plus $4 per added $100 or part
$2,001 to $25,000$96 for the first $2,000, plus $17 per added $1,000 or part
$25,001 to $50,000$487 for the first $25,000, plus $12 per added $1,000 or part
$50,001 to $100,000$787 for the first $50,000, plus $9 per added $1,000 or part
$100,001 to $500,000$1,237 for the first $100,000, plus $7 per added $1,000 or part
$500,001 to $1,000,000$4,037 for the first $500,000, plus $6 per added $1,000 or part
Over $1,000,000$7,037 for the first $1,000,000, plus $5 per added $1,000 or part
Plan review65% of the permit fee, due with the application; third and later submittals at the hourly rate
Technology fee$10 per application
State fee (City’s estimate sheet)“State Surcharge” of $6.50 on a new house
Plumbing or mechanical$23.50 base; $7 per residential plumbing fixture; $14.80 per furnace
Roof-mounted solar$235
Demolition$75
Re-inspection$75 an hour after two failed inspections for the same work
Work without a permitDouble the permit fee, at least $75

Worked example from the City’s own estimate. The Permit Center’s March 31, 2026 estimate prices a two-story, three-bedroom, 2,000 sq ft house with a 400 sq ft attached garage at a valuation of $364,660. That falls in the $100,001 to $500,000 band: $1,237 plus 265 × $7 ($1,855) gives a $3,092 building permit, and plan review at 65% adds $2,009.80. With plumbing ($116.50), mechanical ($153.95), the $10 technology fee and the $6.50 state surcharge, the permit fees come to $5,388.75. Park ($4,966.59), traffic ($7,678.34) and school ($1,120) impact fees and a $3,087 storm drainage capital facility charge bring the total to $22,240.68, before water and sewer connection fees of about $14,810 and $15,812 on City utilities.

The impact fees in force since March 1, 2026 are $1,655.53 per bedroom for parks, $7,678.34 per detached house for transportation ($2,368.85 for an ADU of 450 sq ft or less), and the South Kitsap School District fee of $0.56 per sq ft, at least $546.62 and at most $2,009.27 per home. Park and transportation fees rise with the Seattle-area CPI-U every March 1.

Rather not deal with the building department?

Get a free quote →

Trade permits and who may pull them

Plumbing and mechanical permits are City permits, applied for on the residential or commercial plumbing and mechanical forms; on a new house the fixture and equipment fees ride on the building permit. Port Orchard issues no electrical permits at all, and its estimate sheet sends applicants to L&I. Fire code permits, from sprinklers to tents, are City permits too, because the Building Official acts as fire code official. For the state side (contractor registration with L&I and the electrician and plumber certificates), see our Washington licensing summary.

Who issues what

  • Building, plumbing, mechanical and fire code permits: Port Orchard Permit Center
  • Right-of-way, stormwater and land disturbance: Port Orchard Public Works through the Permit Center
  • Electrical permits and inspections: L&I
  • Septic review: Kitsap Public Health District

Who does the work

  • Work you do yourself is valued for fees at twice the cost of materials
  • Plumbing and mechanical work on a new house is priced into the building permit by fixture
  • Electrical work, by an owner or a contractor, goes through L&I’s rules and permits, not a City form

How to apply for a Port Orchard building permit

1. Look up the lot

Use the City’s zoning map or the Camino permit guide, which works as a guest and shows site constraints, zoning setbacks and the submittal list for some permit types.

2. Meet staff if needed

Book a $150 pre-application meeting for a larger project or the free business walk-through for a tenant space.

3. Prepare electronic files

Follow the City’s electronic document requirements and the checklist on the application form for your permit type.

4. Apply online

Submit through the online application link; the Permit Center emails a fee summary, and the plan review and technology fees are due before the application counts as complete.

5. Answer corrections

Plans are reviewed in the order received; a third or later round is billed hourly.

6. Pay and collect the permit

Pay the permit fee, impact fees and the storm drainage charge at issuance, and buy the electrical permit from L&I.

Want this handled start to finish?

Get a free quote →

Review, corrections and what causes delay

Since June 9, 2026, after building department staff left, a first review of a single-family permit has averaged 4 to 8 weeks, and the Permit Center says it cannot give a firm date for issuance. Because building permits are Type I decisions, POMC 20.200.005 exempts them from the permit-issuance time limits that apply to land use permits. A permit becomes invalid if work does not start within 180 days of issue or stops for 180 days; the Building Official may grant written extensions of up to 180 days each for a justified written request, and a permit expired for less than a year can be reactivated for 50% of the original fee if the plans have not changed. Refund requests must be made within one year of payment and before the permit expires, and no refund exceeds 80% of the plan review fee.

Inspections in Port Orchard

Since August 1, 2025, every inspection has to be requested through the SmartGov portal; the City no longer takes requests by phone or email. To link a permit to your portal account, email the Permit Center for an access code, giving the permit number and your role. Requests made by 3:30 p.m. can be inspected as soon as the next day, though the City warns that it may take several days when inspectors are short. Once the same inspection has failed a second time, each further re-inspection is billed at $75 an hour. All fees must be paid before the final inspection, and no temporary or final certificate of occupancy is issued while any fee on the project is unpaid.

Port Orchard permit search and official resources

The SmartGov portal shows inspection results for permits linked to your account (the City says its new portal will add status tracking and a public record search by address), and the City posts a list of permits issued in the last two months in its records library. Older permits are a public records request. Port Orchard, FEMA community 530094, takes part in the National Flood Insurance Program; building in a mapped flood area also has to meet POMC chapter 20.170, and the current FEMA map is dated February 3, 2017.

Inspections are where schedules slip.

Get a free quote →

Port Orchard building permit FAQ

Who issues building permits in Port Orchard?

The Permit Center of the Department of Community Development, 720 Prospect Street (360-874-5533), for land inside the city limits.

Does Port Orchard issue electrical permits?

No. L&I issues and inspects electrical permits in Port Orchard.

How much are the permit fees on a new house?

The City’s March 2026 estimate for a 2,000 sq ft house shows $5,388.75 in permit fees and $22,240.68 once impact fees and the storm drainage charge are added, before utility connections.

How long does plan review take?

Since June 9, 2026 the City has reported 4 to 8 weeks for a first review of a single-family permit.

Do I need a permit for a fence or shed?

Fences over 6 feet need a permit, as do detached accessory buildings over 200 sq ft, under POMC 20.200.014.

Do I need a permit to re-roof?

Not for up to 21 squares (2,100 sq ft) over existing sheathing with no structural work; larger or structural jobs need a roofing permit.

Can I call in an inspection?

No. Since August 1, 2025 all inspections are requested in the SmartGov portal, by 3:30 p.m. for the next day at the earliest.

Simplify Port Orchard permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Port Orchard sooner?

Let Alliance prepare, file, and track your Port Orchard permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Port Orchard permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.