The City of Mill Creek’s Building Division reviews plans, issues building, mechanical and plumbing permits and inspects the work, and all of those applications are made on the City’s OpenGov portal. Wiring permits are bought from the state Department of Labor and Industries (L&I), whose south Everett office at 729 100th Street SE (425-290-1300) is closed on Wednesdays. Under the 2026 Master Fee Schedule, plan review adds 70% to the valuation-based permit fee, and even a fence, replacement included, needs an $88 permit.
The Permit Counter is at City Hall North, 15720 Main Street, Suite 110A. Walk-in help runs Monday to Thursday from 9 a.m. to noon, and the afternoons from 1 to 5 p.m. are kept for booked appointments, which can be reserved online. The counter’s line is 425-551-7254. Mill Creek’s 2025 Census estimate was 20,902 people.
Mill Creek permits apply inside the city limits. The surrounding unincorporated land, including the Municipal Urban Growth Area the City may annex, is permitted by Snohomish County.
What requires a building permit in Mill Creek?
Mill Creek wrote its own list of house projects that need no building permit: section 15.04.055 of the Mill Creek Municipal Code (MCMC) replaces the residential code’s exemption list, and section 15.04.015 adds temporary job shacks to the commercial list. The City’s homeowner flyer (updated August 2025) puts the general rule plainly: no building, mechanical or plumbing system may be built, altered, replaced, moved or demolished without a permit unless an exemption applies.
Permit required
- New homes, additions, garages, carports, garage conversions and accessory dwelling units
- Interior remodels and new door, window or skylight openings
- Fences, including replacing an existing fence ($88)
- Any deck attached to the house or serving its exit door, and any deck more than 30 inches above grade
- Re-roofing where the sheathing is removed or replaced
- Furnace and water heater replacement, gas piping, zero-clearance fireplaces and irrigation systems
- Retaining walls or rockeries over 4 feet, and tree removal
No permit (MCMC 15.04.055)
- One-story detached accessory buildings of 200 sq ft or less (setbacks still apply)
- Freestanding decks no more than 30 inches above grade that do not serve the required exit door
- Retaining walls up to 4 feet from footing to top that hold no surcharge
- In-kind re-roofing that keeps the existing sheathing, and in-kind window replacement meeting the energy code
- Nonstructural siding, but not veneer, stucco or EIFS
- Painting, flooring, cabinets, counters, playground equipment and prefabricated pools under 24 inches deep
Two points are easy to miss. Fences are not on Mill Creek’s exemption list at all, which is why the flyer lists every new or replacement fence as permitted work. And a deck stays exempt only while it is freestanding: the flyer mentions just the 30-inch height, but the adopted code also excludes decks attached to the house.
Short on time to read all of this?
Get a free quote →What the city decides and what the state holds
Chapter 15.04 MCMC (last updated by Ordinance 2024-914) adopts the 2021 International Building, Residential, Mechanical, Fuel Gas, Fire and Existing Building codes, the Uniform Plumbing Code and the Washington State Energy Code with the state’s amendments; Mill Creek’s design values are a 25 psf ground snow load, seismic category D1, 110 mph wind and a 12-inch frost depth. The City chooses its exemption list, its fees (set by Council resolution under chapter 3.42 MCMC), its tree, grading and critical areas rules, and sends building code appeals to its hearing examiner.
Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington
Mill Creek building department: who handles permitting
The Building Division, within Community Development and Planning, issues building, mechanical and plumbing permits for new and existing construction and does the plan review and field inspections. The Permit Counter staff also help with land disturbing activity, land use, right-of-way and tree removal permits. Fire permits are filed in the same OpenGov portal, with fees set under an interlocal agreement with South County Fire, which provides the city’s fire service.
| Detail | Information |
|---|---|
| Permit Counter | City Hall North, 15720 Main Street, Suite 110A, Mill Creek, WA 98012 |
| Phone and email | 425-551-7254; permitcounter@millcreekwa.gov |
| Counter hours | Walk-in Monday to Thursday, 9 a.m. to noon; appointments Monday to Thursday, 1 to 5 p.m. |
| Inspection line | 425-338-1133, or online in OpenGov |
| Applications | OpenGov (building, mechanical, plumbing, fire, land use, tree, grading, right-of-way) |
| Electrical permits | Washington Department of Labor and Industries |
| City Hall main line | 425-745-1891 |
Permit types
Residential permits
House projects fall into a few OpenGov record types: a building permit for new homes, additions, ADUs, decks and remodels, priced by valuation; flat-fee permits for fences ($88), re-roofs under the residential code ($175) and residential demolitions ($350); and separate mechanical and plumbing permits. A simple job such as a water heater or furnace swap can use the express mechanical or plumbing permit, which costs $175 for up to four fixtures and $18 for each extra one.
Not sure this scope needs a permit?
Get a free quote →Valuation, under MCMC 15.04.030, is the full value of the work, labor and materials, including the contractor’s overhead and profit; the applicant gives an estimate and the Building Official sets the figure, using the current ICC building valuation data for new floor area.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial buildings, tenant improvements and signs are priced on the same valuation table, with 70% plan review, the $25 commercial state fee and separate mechanical and plumbing permits; a commercial re-roof is also priced by valuation and a commercial demolition is $700. Fire alarm and sprinkler permits run $300 for up to 5 devices (plan review included), $500 for 6 to 15 and $1,000 for 16 to 25, plus $10 per added device; fire pumps and standpipes are $600 each. Commercial projects and those with 11 or more homes go before the Design Review Board, a Process II land use review with a $4,375 minimum deposit.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
Removing any tree 6 inches or more in diameter at 4.5 feet above ground, or any tree in a critical area, roadway or property buffer, needs a tree permit (free for a standard tree, $175 for a critical area tree); many subdivisions also carry tree preservation plans. A land disturbing activity permit, the former clearing and grading permit, covers clearing, fill, excavation and retaining walls that a building permit does not, and includes the stormwater site plan under the 2019 Ecology manual; it is priced at 1.5% of the engineer’s estimate for review and 3% for inspection. Work in a street needs a right-of-way permit with a site plan and traffic control plan (Type I $350).
The City has been updating its critical areas rules in chapters 17.32 and 18.06 MCMC (the SEPA determination of non-significance for the update was issued in December 2025), and flood hazard areas are regulated under chapter 15.20. The City runs no water, sewer, gas or electric utility: water and sewer come from the Alderwood Water and Wastewater District or the Silver Lake Water and Sewer District, and any septic system is a Snohomish Health District matter.
Mill Creek permit costs and fees
Fees come from the 2026 Master Fee Schedule, adopted by Resolution No. 2025-810 and in force since January 1, 2026. Mill Creek prices permits as a percentage of value, and the bands join up: each one starts where the one below ends. Plan review fees are paid up front, because an application is not complete until they are.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee or rule |
|---|---|
| Valuation $2,000 or less | $88 |
| $2,001 to $25,000 | $175 plus 2% of the value over $2,000 |
| $25,001 to $50,000 | $635 plus 1.5% of the value over $25,000 |
| $50,001 to $100,000 | $1,010 plus 1.0% of the value over $50,000 |
| $100,001 to $500,000 | $1,510 plus 0.8% of the value over $100,000 |
| $500,001 to $1,000,000 | $4,710 plus 0.7% of the value over $500,000 |
| $1,000,001 to $5,000,000 | $8,210 plus 0.6% of the value over $1,000,000 |
| Over $5,000,000 | $32,210 plus 0.5% of the value over $5,000,000 |
| Plan review | 70% of the permit fee (not refundable); extra review at $175 an hour, 1-hour minimum |
| State Building Code Fee | Residential $6.50 plus $2 per dwelling unit over one; commercial $25 plus $2 per dwelling unit over one |
| Technology fee | 3% of all development fees except telecommunications and state fees |
| Re-inspection | 1.5 times the $175 hourly rate, 1-hour minimum |
| Extension of an application or permit | $350 or 50% of the permit fees, whichever is less |
| Work without a permit | Permit fees may be doubled |
Worked example. Mill Creek works in percentages, so a $60,000 addition costs $1,010 plus 1% of the $10,000 over $50,000: $1,110. Add 70% plan review ($777), the 3% technology fee on both ($56.61) and the $6.50 residential state fee, and the City collects $1,950.11; plumbing, mechanical and L&I electrical permits are extra.
New homes also pay impact fees. Park fees under Resolution 2013-503 are set per unit by park type (up to $3,308.45 for a single-family home for neighborhood park land and development), the City’s transportation fee is $3,900 per PM peak-hour vehicle trip under Ordinance 2018-838, and the Everett School District fee is $9,118 for a single-family house. If no work has been done, up to 80% of permit fees can be refunded, but never plan review.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them
The fee schedule and the codes page both send electrical work to L&I: Mill Creek does not appear on L&I’s list of cities with their own electrical inspection, so service changes, circuits, EV chargers and solar wiring are permitted and inspected by the state. The City issues the mechanical, gas piping and plumbing permits, and South County Fire’s fees apply to fire alarm, sprinkler and solar panel permits ($600 for a solar permit, with plan review and one inspection).
City of Mill Creek
- Building, mechanical and plumbing permits, with plan review and inspections
- Fire system permits, under South County Fire’s fee terms
- Tree, land disturbing activity, stormwater and right-of-way permits
Other agencies
- Electrical permits and inspections: L&I
- Water and sewer connections: Alderwood or Silver Lake district
- Power: Snohomish County PUD; septic: Snohomish Health District
- Contractors’ registration and trade license status: L&I’s online lookup, linked from the City’s codes page; what the state requires is outlined in our Washington licensing notes
How to apply for a Mill Creek building permit
Look at the City’s maps and residential plat maps, since many developments have tree preservation plans and property buffers. Book a counter appointment or a pre-application consultation if the project is not straightforward.
File the tree removal permit, and the land disturbing activity permit with its stormwater site plan, before or alongside the building application.
Use the City’s design values and the 2021 codes, with a site plan showing setbacks; the codes page links a fence site plan example and construction tip sheets.
Create an account on the Mill Creek OpenGov portal, choose the record type, upload the plans and pay the plan review fee, which makes the application complete.
Answer reviewers’ comments in OpenGov; time beyond the standard review is billed at $175 an hour.
Pay the permit, technology, state and impact fees, download the permit, and buy any electrical permit from L&I before wiring starts.
Review, corrections and what causes delay
Appeals of a Building Official’s decision go to the City’s hearing examiner rather than a board of appeals. A tree removal or grading permit lasts six months, with one extension of up to six more, so time the site work to the building schedule. Extending a building application or permit costs $350 or half the permit fees, whichever is less.
Want this handled start to finish?
Get a free quote →Inspections in Mill Creek
Inspections are requested in OpenGov or by calling 425-338-1133. A request made before 3:30 p.m. gets an inspection on the next business day; one made later is scheduled for the business day after that. A re-inspection is billed at one and a half times the hourly rate with a 1-hour minimum, and an evening, weekend, holiday or expired-permit inspection at double the rate with a 2-hour minimum. A certificate of occupancy issued outside a building permit costs $175.
Mill Creek permit search and official resources
The OpenGov portal’s public search shows the status of building permits by address or record number. Older permit files and plans are requested as public records through the City’s GovQA request center. On flood insurance, Mill Creek is a participating community in the National Flood Insurance Program; FEMA’s status book lists June 19, 2020 as its current effective map.
- Mill Creek Permits and Licensing: counter hours and contacts
- Building permits: apply and schedule inspections
- Building codes and design criteria
- Do I Need a Permit? flyer, August 2025 (PDF)
- 2026 Master Fee Schedule, Resolution 2025-810 (PDF)
- Mill Creek Municipal Code (Title 15, buildings)
- Tree removal permits
- Land disturbing activity permits
- OpenGov permit status search
- Public records requests (GovQA)
- October 2026 annexation decision
- L&I list of cities with their own electrical permits
Inspections are where schedules slip.
Get a free quote →Mill Creek building permit FAQ
Who issues building permits in Mill Creek?
The City’s Building Division, through the Permit Counter at City Hall North, 15720 Main Street, Suite 110A (425-551-7254). L&I issues electrical permits.
Do I need a permit to replace my fence in Mill Creek?
Yes. Fences are not exempt in Mill Creek, and the City lists replacement fences as permitted work. The fence permit is $88 in 2026.
How much is a building permit in Mill Creek?
A $60,000 project pays a $1,110 permit fee, $777 plan review, a $56.61 technology fee and the $6.50 state fee: $1,950.11 in 2026.
Do I need a permit for a deck?
Yes if it is attached to the house, serves the exit door or stands more than 30 inches above grade at any point. A low freestanding deck is exempt.
Do I need a permit for a new roof?
Only if the sheathing is removed or replaced; in-kind re-roofing over the existing sheathing is exempt. A residential re-roof permit is $175.
When will my inspection happen?
The next business day if you request it before 3:30 p.m., online or at 425-338-1133.
Can I cut down a tree on my lot?
Not without a permit if it is 6 inches or more in diameter at chest height, or in any buffer. Standard tree permits are free.
Simplify Mill Creek permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Mill Creek sooner?
Let Alliance prepare, file, and track your Mill Creek permits while your crew stays on the job.
More Washington permitting guides
Snohomish County
Read guide →Arlington
Read guide →Edmonds
Read guide →Monroe Building Permit Guide
Read guide →Moses Lake Building Permit Guide
Read guide →Mount Vernon Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Mill Creek permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.