Lake Stevens, Washington Building Permit Guide

To get a building permit in Lake Stevens, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Lake Stevens issues its own building, mechanical, plumbing, demolition, re-roof and fire system permits through the Citizens Connect portal run by Planning and Community Development at City Hall; electrical permits and inspections come from Labor and Industries.

Authority: Lake Stevens Planning and Community DevelopmentCode: 2021 IBC and IRC (Ordinance 1160)Phone: 425-622-9400
Authority
Planning and Community DevelopmentCity Hall, 1812 Main Street
Counter
Mon–Thu 9–12, 1–4Friday 9 a.m. to noon
Fees
Resolution 2026-06Building table effective July 1, 2026
Electrical
Labor and IndustriesPermits and inspections

The City of Lake Stevens issues building, mechanical, plumbing, demolition, re-roofing and fire alarm and sprinkler permits through its Planning and Community Development department, and all of them are applied for online in Citizens Connect. Electrical work is the exception: those permits and inspections come from the state Department of Labor and Industries (L&I). Under the fee resolution the City Council passed in June 2026, a house’s plan review is 65% of the building permit fee and a 5% technology fee applies to permit payments.

The permit counter is at City Hall, 1812 Main Street (mailing address P.O. Box 257, Lake Stevens, WA 98258). It is open Monday to Thursday from 9 a.m. to noon and 1 p.m. to 4 p.m., and Friday from 9 a.m. to noon; the Permit Desk answers 425-622-9400 and permits@lakestevenswa.gov. The city had 42,091 residents in the Census estimate for 2025.

This page is about permits inside Lake Stevens city limits; land outside them is Snohomish County’s to permit.

What requires a building permit in Lake Stevens?

City code (LSMC 14.80.030) requires a permit to build, enlarge, alter, move or demolish a building or to change its occupancy. For houses, duplexes and townhouses, the exemptions are those of the 2021 International Residential Code, section R105.2, plus two that Lake Stevens added through Ordinance 1160 when the 2021 codes took effect on March 15, 2024.

Permit required

  • New houses, ADUs, additions, remodels and garage conversions
  • Garages, carports, sheds and decks beyond the exempt sizes
  • Re-roofing with a covering of 4 psf or more
  • Retaining walls over 4 feet from the bottom of the footing, or holding a surcharge
  • Demolition, docks, pools and spas, mechanical and plumbing work
  • Fire alarm and sprinkler systems

No permit

  • Re-roofing with a lightweight covering, such as composition or metal roofing under 4 psf (Lake Stevens addition)
  • Replacing exterior windows in the existing openings, with the opening size unchanged and the operable area not reduced (Lake Stevens addition)
  • A one-story detached accessory building of 200 sq ft or less
  • Fences up to 7 feet, sidewalks and driveways
  • A deck of 200 sq ft or less, no more than 30 inches above grade, not attached and not serving the required exit door
  • Finish work, interior door replacement and siding repair, as the City’s interior exemptions sheet lists

What the city decides and what the state holds

The state sets the codes and their base exemptions; Lake Stevens adopts them in chapter 14.80 of its code and adds its own amendments, fee resolution, portal, zoning, shoreline permits and critical areas rules. The City’s own sheet also points out that interior work on a mobile or manufactured home is permitted through L&I, not the City.

Short on time to read all of this?

Get a free quote →

Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington

Lake Stevens building department: who handles permitting

Planning and Community Development runs the permit counter, takes building and land use applications and has the Building Official review plans and inspect. Public Works issues right-of-way permits and schedules its own inspections through a separate Citizens Connect page. Fire plan review follows the 2026 fee tables of Snohomish Regional Fire & Rescue, which the City adopted by reference, and the Lake Stevens Sewer District and the PUD sign off on sewer, water and power availability.

Lake Stevens permitting contacts
DetailInformation
OfficePlanning and Community Development, City Hall, 1812 Main Street, Lake Stevens, WA 98258 (mail: P.O. Box 257)
Phone and email425-622-9400; permits@lakestevenswa.gov
Counter hoursMonday to Thursday, 9 a.m. to noon and 1 p.m. to 4 p.m.; Friday, 9 a.m. to noon
PortalCitizens Connect (applications, payment, inspections)
Who may applyThe property owner, the owner’s agent or a Washington licensed contractor
Electrical permitsWashington Department of Labor and Industries

Permit types

Residential permits

The residential submittal checklist (approved July 2025) covers houses, duplexes and townhouses under the residential code. A new house, addition or alteration needs the application form, a site plan, one combined PDF of foundation, floor, roof, elevation, section and detail plans, an energy code form, and where they apply structural calculations, a geotechnical report for steep slopes, a special inspections agreement, health approval for a well or septic system, a sewer availability letter from the Lake Stevens Sewer District, water or power letters from the PUD, a land use decision and a stormwater pollution prevention plan once 2,000 sq ft of hard surface is added or replaced or 7,000 sq ft of land is disturbed. Garages, carports, decks and sheds need a shorter set. Files must be flattened PDFs under 200 MB, landscape except the site plan, and named as the checklist shows, or staff may reject them at intake.

The City also publishes handouts for ADUs, garage conversions, decks, retaining walls, pools and spas, tiny homes, building height limits and model homes. An owner who will act as their own contractor signs the City’s acknowledgment of the state rule (RCW 18.27.090) and its liability warnings.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial buildings and tenant improvements have their own checklists. Commercial and multifamily plan review is 65% of the Table 1A fee, commercial plumbing and mechanical review 40% of those permit fees (minimum $126), and fire plan review is charged on Snohomish Regional Fire & Rescue’s valuation table, which has a separate flat charge for houses. Adult family home reviews, certificates of occupancy without construction and revisions are billed at $253 for a two-hour minimum.

What comes before the building permit

Many projects need a land use decision first. Critical area review is billed at actual cost plus a $53 administrative fee; a shoreline exemption on the lake costs $601 ($727 with a floodplain development permit), a shoreline substantial development permit $1,196 and a standalone floodplain development permit $495. A pre-application conference is $885, credited toward a later application fee over $1,000 if filed within 12 months. On a septic lot, the Snohomish County Health Department (Land Use, 3020 Rucker Avenue, Everett, 425-339-5250) handles the septic side. Applicants can also elect consolidated review, running the building permit alongside land use approvals at their own risk: no building permit is issued until those approvals are final.

Lake Stevens permit costs and fees

Fees are set by City Council resolution. Resolution 2025-09 brought in the 2026 fees on January 1, 2026, raised the technology fee from 3% to 5% and added a 3% service fee; Resolution 2026-06, passed on June 2, 2026, amended the schedule, and the posted building fee table is marked effective July 1, 2026. The resolution adjusts building, land use and impact fees every January 1 by a five-year average of the consumer price index, and valuation follows the ICC building valuation data.

Rather talk it over?

Call 1-855-478-4290 →
Lake Stevens building fees (Resolution 2026-06, Table 1A and related tables)
ItemFee or rule
Valuation $1 to $1,000$66
$2,001 to $25,000$116 for the first $2,001, plus $21 per added $1,000 or fraction
$25,001 to $50,000$606 for the first $25,001, plus $15 per added $1,000 or fraction
$50,001 to $100,000$1,046 for the first $50,001, plus $11 per added $1,000 or fraction
$100,001 to $500,000$1,580 for the first $100,001, plus $8 per added $1,000 or fraction
Plan review (houses, duplexes, townhouses)65% of the Table 1A fee or $126, whichever is greater; two correction cycles included
Mechanical / plumbing, houseNew house: 10% of the building permit fee each; alteration: $211 for up to 4 items, $16 each after
Demolition$126 permit plus plan check at $126 an hour
Re-inspection$126 an hour
Permit or plan review extension$253
Work without a permitInvestigation fee of twice the permit fee
Technology fee5% of development services payments, not charged on deposits, impact fees or State Building Code Council (SBCC) fees
Service fee3% of every payment except cash or check

The bands do not chain into each other, so each value is priced within its own band; decks are valued at $42 per sq ft uncovered and $53 covered, and an unfinished basement at $26 per sq ft. Worked example. A $60,000 remodel: $1,046 plus 10 × $11 ($110) is a $1,156 permit fee; plan review at 65% is $751.40; the 5% technology fee on both is $95.37, for $2,002.77, before the SBCC fee and any trade permits. Paying by card adds the 3% service fee.

New homes also pay mitigation fees: $4,572 for parks per single-family home, a traffic fee of $5,659 in impact zone 1 or $3,725 in zones 2 and 3, and a school fee of $13,730 per detached house in the Lake Stevens School District or $5,361 in the Snohomish School District.

⚠️ Park fee on the Council’s agenda. “Park Mitigation Fees” was listed as a discussion item for the City Council’s October 27, 2026 meeting; the $4,572 figure is the adopted rate until a new resolution passes.

Trade permits and who may pull them

Mechanical and plumbing permits are City permits, filed in Citizens Connect: for a new house each costs 10% of the building permit fee, and an alteration costs $211 for up to four pieces of equipment or fixtures. Electrical permits are not: the City says plainly that L&I issues them, and the City’s inspection handout requires L&I’s cover approval before the framing inspection and L&I’s electrical final before the City’s final.

Rather not deal with the building department?

Get a free quote →

Who files what

  • Building, mechanical, plumbing, demolition, re-roof: the City, in Citizens Connect
  • Fire alarm and sprinkler: the City’s portal (fire permits option)
  • Electrical: L&I
  • Right-of-way: Public Works

Owners and electrical

  • Owner-builders sign the City’s acting-as-your-own-contractor form, which cites the RCW 18.27.090 exemption and the owner’s liability for unlicensed helpers
  • The City’s inspectors will not pass framing or the final without L&I’s electrical approvals, whoever did the wiring

How to apply for a Lake Stevens building permit

1. Check zoning and the shoreline

Ask the Permit Desk or Planning whether the lot needs a land use decision, critical areas review or a shoreline permit before the building application.

2. Gather the checklist items

Use the residential or commercial submittal checklist and collect availability letters from the Lake Stevens Sewer District and the PUD, plus any health approval for a well or septic system.

3. Create a Citizens Connect account

First-time users register, then log in and choose the permit type; fire alarm and sprinkler permits are under the fire permits option.

4. Upload and wait for intake

Staff check completeness, usually within 3 business days, and email either a request for more information or an invoice.

5. Pay and answer corrections

Pay by MasterCard or Visa (or by check to avoid the service fee); two correction cycles are included, then review is billed hourly.

6. Print the approved packet

Once issued, print the permit packet and stamped plans from the “Attachments” section and keep them on site for inspectors.

Review, corrections and what causes delay

The City may reject files at intake if they are named or formatted wrongly. An application expires if the permit is not obtained within 180 days of applying, and an issued permit expires if work has not begun within 180 days; the Building Official can grant 180-day extensions on a written request showing justifiable cause, for a $253 fee.

Inspections in Lake Stevens

Inspections are scheduled in Citizens Connect under “Inspections,” and the inspection record card and stamped plans must be on site. The residential handout lists footing and setback (with property corner pins visible), foundation wall, dampproofing, groundwork plumbing, slab insulation, storm and footing drains, water line, slab, floor framing, exterior shear nailing, gas piping, rough plumbing and mechanical, weather barrier and window flashing, framing, insulation and interior shear nailing, then plumbing and mechanical finals.

Want this handled start to finish?

Get a free quote →

Before the final for occupancy, the fire district, the Lake Stevens Sewer District, Planning and Public Works must each have signed off, special inspection reports must be in, landscaping must match the approved site plan and the address numbers must be visible from the street. A re-inspection after the second inspection, or after a cancellation given later than 7 a.m., is billed at $126 an hour.

Lake Stevens permit search and official resources

Citizens Connect shows active permits and their status; for older permit files, contact the Permit Desk at 425-622-9400 or permits@lakestevenswa.gov. Lake Stevens participates in the National Flood Insurance Program, with a current FEMA map dated June 19, 2020; work in a mapped floodplain needs a floodplain development permit from the City.

Inspections are where schedules slip.

Get a free quote →

Lake Stevens building permit FAQ

Who issues building permits in Lake Stevens?

The City’s Planning and Community Development department, at City Hall, 1812 Main Street; electrical permits come from L&I.

Do I need a permit to re-roof?

Not for a lightweight covering such as composition or metal roofing under 4 pounds per square foot; heavier roofing needs a re-roof permit.

Do I need a permit to replace windows?

No, if the new windows go into the existing openings, the size of each opening stays the same and the operable area is not reduced.

How much is a building permit in Lake Stevens?

A $60,000 remodel pays a $1,156 permit fee, $751.40 for plan review and a $95.37 technology fee under the 2026 tables, before the state fee and trade permits.

Can a homeowner apply?

Yes. The owner, the owner’s agent or a Washington licensed contractor may apply; an owner acting as contractor signs the City’s owner-builder form.

How fast is intake?

Staff normally check a new application for completeness within 3 business days, then email an invoice or a request for more information.

When is the permit counter open?

Monday to Thursday, 9 a.m. to noon and 1 p.m. to 4 p.m., and Friday, 9 a.m. to noon.

Simplify Lake Stevens permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Lake Stevens sooner?

Let Alliance prepare, file, and track your Lake Stevens permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Lake Stevens permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.