To get a building permit in Grant County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Grant County Development Services in Ephrata permits building outside city limits, and applications go in as PDFs through its SmartGov portal.

Authority: Grant County Development Services, Building DivisionCode: 2021 Washington codesPhone: 509-754-2011 ext. 3001
Authority
Development Services, Building DivisionUnincorporated Grant County
Apply
SmartGov portal10 days to finish a draft
Plan review
50% of the permit feeBuilding and fire
New home review
4 to 6 weeksCounty average

Outside the cities and towns, Grant County building permits are issued by the Building Division of Grant County Development Services, 264 Division Avenue West in Ephrata (509-754-2011 ext. 3001). You build the application in the county’s SmartGov portal, the county routes it to planning, the fire marshal, public works and the health district, and new homes average four to six weeks of review. Fees follow Resolution 23-055-CC: a valuation table tied to the ICC’s annual cost data, with plan review at 50 percent of the permit fee.

What requires a building permit in Grant County?

The Building Division reviews permit applications for structures in unincorporated Grant County and enforces chapter 19.27 RCW. Its handout of the 2021 residential code’s section R105 lists what needs no permit; everything else that builds, enlarges, alters, repairs, moves, demolishes or changes the use of a building, or installs gas, mechanical or plumbing systems, needs one.

Permit needed

  • New houses (the fee includes their plumbing and mechanical work), additions and remodels
  • Garages, shops, pole buildings and agricultural structures
  • Decks over the exempt size, carports, pergolas and gazebos
  • Manufactured and mobile homes, cargo containers used for storage, moved buildings
  • Fences and retaining walls above the exempt heights
  • Pools, spas, towers, signs and demolition
  • Fire Marshal permits for propane tanks, sprinklers, alarms and fuel tanks

Exempt under the county handout

  • One-story detached accessory structures up to 200 sq ft (not storm shelters)
  • Fences up to 7 feet; retaining walls up to 4 feet without surcharge
  • Decks up to 200 sq ft, no more than 30 inches above grade, detached and not serving the required exit door
  • Sidewalks, driveways, finish work, swings and playground equipment
  • Prefabricated pools under 24 inches deep; water tanks on grade up to 5,000 gallons
  • Roof-mounted solar arrays on detached accessory structures (fee schedule)

What the county decides and what the state holds

All submittals since March 15, 2024 are reviewed under the 2021 state codes, and residential energy code reviews have followed the county’s Policy 2024-004 since December 5, 2024. The county’s design criteria for houses are seismic category C, 110 mph ultimate wind speed, a 20 psf roof live load with 30 psf ground snow, an 18-inch frost line, climate zone 5 and an air freezing index of 1,200; ice-shield underlayment is not required, and flood hazards follow the FEMA maps. Electrical work is not part of the county permit at all.

Grant County building department: who handles permitting

Development Services combines the Planning, Building, Fire Marshal and GIS divisions under director Jim Anderson-Cook. The Building Division employs ICC-certified plans examiners and inspectors; complaints about unpermitted building go to the division, while other land use and nuisance complaints go to the Sheriff’s Code Enforcement Unit.

Short on time to read all of this?

Get a free quote →
Grant County permit contacts
OfficeDetails
Building Division264 Division Ave W, Ephrata, WA 98823 (mail PO Box 37); 509-754-2011 ext. 3001 or 509-450-1118; lobby 8 a.m. to 4 p.m., phones to 5 p.m., Monday to Friday
Inspection line509-450-1117
Planning Division509-754-2011 ext. 2501 or 2537
Fire Marshal509-754-2011 ext. 3006
Public Works (road approaches)509-754-6082
Grant County Health District (septic and water)509-766-7960
Electrical permitsWashington L&I, 3001 W Broadway Avenue, Moses Lake; 509-764-6900

Cities and towns in Grant County

The county reviews structures outside city limits, and its permit page asks you to confirm the property is not in a city before you apply. None of the cities is on L&I’s list of cities with their own electrical program.

Who handles building permits in each city or town
PlaceBuilding permits
Moses LakeCity Permit Services, with its own online permit portal
EphrataCity Community Development, with building, permit and inspection pages
QuincyCity of Quincy Building Department
Warden, Wilson CreekEach contracts with Northwest Code Professionals for permits, review and inspection
Coulee CityThe town contracts out its building permits and inspections
GeorgeCity application form; plan review and inspection by the city’s contracted planner and building official
Royal City, Electric CityCity building permit applications from city hall
Soap LakeCity construction, demolition and fence permit forms
MattawaCity of Mattawa: its building code (MMC ch. 15.12) is run by the city building official, and the mayor may contract the work out; City Hall, 521 Government Road, 509-932-4037
Grand CouleeCity of Grand Coulee building and demolition permit applications (complete site plan required); the form is run with Northwest Code Professionals
Coulee Dam (Grant County part, no residents)Town building official issues permits under the town code (CDMC 17.125)
Hartline, KruppThe published sources do not say; ask the town hall

Grant County permit types and what comes first

Residential permits

There is no paper application any more: the portal asks the application questions, and you upload the site plan, the Agent Authorization Form (or, for a homeowner with no agent, a statement saying so) and complete construction drawings checked against the county’s residential plan checklist. Every file must be a PDF named in the format set out in the county’s standards. Manufactured homes add the FAS moving form, and gas work an LP-gas piping schematic. A manufactured or mobile home is a $500 flat fee with no plan review.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial submittals follow the commercial checklist and average six to eight weeks. Where special inspection is required under IBC chapter 17, the owner, not the contractor, hires the approved agency, a statement of special inspections is a condition of issuance, and the reports are emailed to the division with the permit number.

What comes before the building permit

  • Planning: the division checks zoning and setbacks on submittals; shoreline determinations and permits, floodplain development permits, shrub-steppe review, variances and site addresses also go through Planning.
  • Health District: septic design, site evaluation and permits, and proof of water such as well reports or shared-well agreements; adding bedrooms or restrooms means contacting the district first.
  • City services: a lot that will connect to city water or sewer needs a confirmation letter from the city.
  • Fire Marshal: access and fire flow; homes over 3,600 sq ft or short of the fire protection credits needed for fire flow may need separate Fire Marshal permits, and a fire flow worksheet for a home over 3,600 sq ft is $50.
  • Access: Public Works must approve a road approach from a county road before issuance; a new access onto a state highway needs WSDOT.

Grant County building permit fees

The commissioners adopted the current Building and Fire fee schedule by Resolution No. 23-055-CC after a hearing on June 27, 2023, effective July 1, 2023. Instead of fixing dollar values per square foot, the county adopts the ICC’s February Building Valuation Data every July 1, so valuations move each year while the fee table stays put; the 2026 table is the ICC’s February 2026 data, which prices one- and two-family dwellings at $175.92 to $224.62 per sq ft depending on construction type and unfinished basements at $31.50. Plan review is 50 percent of the permit fee for both residential and commercial work.

Grant County building and fire valuation fee table
ValuationFee
$1 to $1,400$50
$1,401 to $2,000$50 plus $3 per $100 over $1,400
$2,001 to $25,000$68 plus $14 per $1,000 over $2,000
$25,001 to $50,000$390 plus $10 per $1,000 over $25,000
$50,001 to $100,000$640 plus $7 per $1,000 over $50,000
$100,001 to $500,000$990 plus $6 per $1,000 over $100,000
$500,001 to $1,000,000$3,390 plus $5 per $1,000 over $500,000
$1,000,001 and up$5,890 plus $36 per $10,000 over $1,000,000

Rather talk it over?

Call 1-855-478-4290 →
Other Grant County fees
ItemFee
Plan review (building and fire)50% of the permit fee
State building code fee (RCW 19.27.085, as the schedule quotes it)$6.50 per residential permit, $25 per commercial permit, plus $2 per residential unit after the first
Manufactured or mobile home$500 flat, no plan review
Decks, carports, pergolas, gazebosValued at 50% of the utility (U) rate
Fences and retaining wallsValued at length × height × $10
Agricultural structures50% of the valuation
Residential pool / spa$150 / $75
Demolition: residential / commercial$100 / $300
Residential plumbing or mechanical (not with a new house)$50 base plus item fees (e.g. water heater $20, furnace $20)
Special inspection or reinspection$100
Work without a permit after a stop work order (not permitted within 72 hours)Double the permit fee
Extension: 30 days near final / one yearNo charge / 50% of the permit fee

The bands join up exactly, so the table can be used across them. Card payments in the portal carry a 2.7 percent bank fee; checks and cash are taken at the counter from 8 a.m. to 4 p.m. For a new house or a new commercial building the 50 percent plan review fee is due when you submit; other projects may be asked for a deposit after intake.

Worked example: a house valued at $300,000 lands in the $100,001 to $500,000 band: $990 plus 200 × $6 is $2,190, which already includes the house’s plumbing and mechanical work. Plan review at 50 percent adds $1,095 and the state fee $6.50, for $3,291.50.

Trade permits and who may pull them

For a new house the county’s permit fee covers plumbing, mechanical and fuel gas work; for other projects residential plumbing and mechanical permits start at a $50 base, and commercial ones are priced on project valuation with plan review at 25 percent. Fire systems, propane tanks and roof-mounted solar on a house are Fire Marshal permits. Electrical permits come only from L&I, which has an office at 3001 W Broadway Avenue in Moses Lake.

Rather not deal with the Grant County building department?

Get a free quote →
  • Gas piping: a gas line job needs the LP-gas piping schematic in the submittal, and the residential gas fee is $10 per appliance connection.
  • Fire Marshal items on a house: a propane tank under 501 gallons is $50, a larger one $150, and a home fire sprinkler system $150.
  • Special inspection: on commercial work the owner’s agency, not the contractor, files the special inspection reports with the division.
  • Manufactured homes: since January 31, 2022 owners installing their own home must complete L&I training as an “approved homeowner” and buy installer certification tags before work starts.

State law decides who must hold a contractor registration or trade license and how much electrical or plumbing work owners may do themselves; our Washington licensing overview covers those rules.

How to apply for a Grant County building permit

1. Confirm the parcel is county land

A city address goes to the city instead.

2. Talk to the other offices

Health District, Planning, the Fire Marshal and Public Works each have conditions that can stop issuance.

3. Open a SmartGov account

Use your own name and contact details, not a business name.

4. Build the submittal in the staging area

You have 10 days to answer the questions, upload the named PDFs and press Submit Application.

5. Pass intake and pay any deposit

Incomplete packages go back to your staging area; a requested deposit must be paid before review starts.

6. Follow the approval steps

Track each department’s review in the portal, then pay and print the permit packet.

Review, corrections and what causes delay

The county’s averages are four weeks for small projects, four to six weeks for a new home and six to eight weeks for commercial work. A package returned at intake, an unpaid deposit, or a missing Health District, road approach or city utility approval holds the permit back. Revisions after issuance are billed at $50 an hour, and nothing is accepted or issued after 4 p.m.

Inspections in Grant County

Call the inspection line, 509-450-1117, between 8 a.m. and 4 p.m. on a weekday with your name, phone number, permit number, site address and the inspections you need. The county does not do same-day inspections and cannot give times: keep the whole next business day free, as inspectors may arrive from 7 a.m. to 5 p.m. Fire Marshal inspections are booked with the Fire Marshal at ext. 3006, and changes or cancellations go through a permit technician at ext. 3001.

The inspection card lists the required inspections; skipping one can lead to the permit being revoked or the certificate of occupancy being refused. A reinspection costs $100, and a permit about to expire at the final stage can get one free 30-day extension.

Want this handled start to finish?

Get a free quote →

Flood maps and state code

FEMA’s Community Status Book lists Grant County as participating in the National Flood Insurance Program with a current effective map of February 18, 2009, along with Coulee City, Ephrata, Hartline, Moses Lake, Quincy, Warden and Wilson Creek; Ephrata holds a class 8 rating in the Community Rating System. Electric City and Grand Coulee appear in the section for communities not in the program, with a sanction date of February 18, 2010.

Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington

Grant County building permit FAQ

How much is a permit for a $300,000 house in Grant County?

$2,190 plus $1,095 for plan review and the $6.50 state fee; plumbing and mechanical are included for a new house.

How long does plan review take?

On average four weeks for small projects, four to six weeks for a new home and six to eight weeks for commercial work.

Can I build a shed without a permit?

Yes, if it is a one-story detached accessory structure of no more than 200 sq ft; the exemption does not excuse it from zoning or other county rules.

Can I drop off paper plans?

The county takes applications through SmartGov; for a paper review, call ext. 3001 first.

Who issues permits in Moses Lake or Quincy?

The cities themselves; the county handles only land outside city limits. L&I issues electrical permits in both cities.

Do I need a septic permit before the building permit?

Where there is no sewer, yes: the Grant County Health District reviews the septic design and proof of water as part of the county’s routing.

What happens if I build without a permit?

If a stop work order is not followed by a permit within 72 hours, the permit fee doubles.

Permit search and official resources

Applicants follow their own permits in SmartGov. The Building Division posts weekly lists of building and Fire Marshal permits issued; for older files or anything more specific, use the county’s public records request portal.

Inspections are where schedules slip.

Get a free quote →

Simplify Grant County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Grant County sooner?

Let Alliance prepare, file, and track your Grant County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Grant County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.