Jasper County issues no building permits outside its cities; it regulates floodplain work, while septic permits come from TCEQ or ANRA.

Authority: Jasper County Emergency Management (floodplain)Code: No county building codePhone: 409-994-2543 (floodplain)
County permit
Floodplain Permit onlyEmergency Management
Cities
Jasper permits its ownKirbyville, Browndell: not published
Septic
TCEQ or ANRAANRA near Sam Rayburn Reservoir
2025 population
33,075

Jasper County issues no building permit, makes no building inspections and requires no certificate of occupancy outside its cities. What the county does regulate is the floodplain: any work or fill in a FEMA flood zone needs a Floodplain Permit from Emergency Management (409-994-2543), and new homes there must sit at least 2 feet above base flood elevation. Septic systems go to TCEQ, or to the Angelina & Neches River Authority near Sam Rayburn Reservoir.

What needs a permit in unincorporated Jasper County?

The County Judge’s office states that the Commissioners Court has passed no zoning rules except for the airport and floodplain areas, and that the county neither permits nor inspects buildings in unincorporated areas. That leaves a short list of approvals for rural land:

Approvals that apply

  • Floodplain Permit for any work in a FEMA flood hazard area, including fill
  • Septic (OSSF) permit: TCEQ, or ANRA inside the Sam Rayburn control zone
  • Subdivision plat when land is split into two or more parts and any part is 10 acres or less
  • A 911 address from the South East Texas Regional Planning Commission

Not required by the county

  • Building permits and building inspections
  • Certificate of occupancy
  • Countywide zoning approval outside the airport and floodplain areas

Who issues permits in each Jasper County town?

Three cities lie in the county, and about 23,400 of its 33,075 residents live outside them.

Short on time to read all of this?

Get a free quote →
Building permits by area
AreaWho issues permits
Jasper (pop. 7,511)City of Jasper Code Enforcement and Inspections Department, City Hall, 465 S. Main St.; Chief Building Official Jeremy Chesnutt (409-383-6144). Applications through the City’s iWorQ portal.
Kirbyville (pop. 2,031)The City’s website publishes no building permit procedure; City Hall, 107 S. Elizabeth, 409-423-6191.
Browndell (pop. 154)The published sources do not say; the City’s number is 409-698-2044.
Unincorporated countyNo building permit. Floodplain Permits from county Emergency Management; septic permits from TCEQ or ANRA.
Jasper County offices
OfficeContact
County JudgeCourthouse, 121 N. Austin, Room 106, Jasper, TX 75951; 409-384-2612
Emergency Management (Floodplain Administrator)Buna office, P.O. Box 2030, Buna, TX 77612, 409-994-2543; Jasper office 409-383-9067
Public works engineering (LJA)409-833-3363
911 rural addressing (SETRPC)409-347-1911, ext. 6102

Septic systems in Jasper County

The county’s own letter on permit requirements sends septic permitting to TCEQ (409-898-3838); TCEQ lists no local authorized agent for the rest of Jasper County, so its Region 10 office in Beaumont issues those permits. The exception is the shoreline of Sam Rayburn Reservoir. There the Angelina & Neches River Authority (ANRA) is TCEQ’s authorized agent for a control zone that starts at the Corps of Engineers 179-foot elevation line and runs 2,000 feet inland, and a subdivision with any part inside the zone falls entirely under ANRA. TCEQ’s 2025 report shows ANRA issued 14 septic authorizations in Jasper County that year.

Not sure this scope needs a permit?

Get a free quote →
ANRA septic permit fees (effective May 1, 2025, including the $10 TCEQ fee)
ItemFee
Single-family home or single-structure duplex$485
Other system, light (3 or fewer connected buildings, no food preparation)$610
Other system, heavy$1,510
Permit transfer$35
Re-inspection$250
Re-design$175

For an ANRA permit, a licensed site evaluator checks the soil, a registered sanitarian or professional engineer designs the system, and the packet goes to ANRA’s OSSF Department in Lufkin (936-632-7795). The permit to construct is good for one year, and the installer must book the final inspection at least 5 working days ahead. The county issues no electrical, plumbing or mechanical permits; inside Jasper, the City takes separate electrical, HVAC, plumbing and gas, generator and fire protection applications.

Starting a project on rural Jasper County land

1. Check the city limits

Inside Jasper, apply to the City’s Code Enforcement and Inspections Department; inside Kirbyville or Browndell, ask the city first.

2. Get a 911 address

Rural addresses come from SETRPC 911 Addressing at 409-347-1911, ext. 6102.

3. Look up the flood zone

Search the FEMA Flood Map Service Center, or ask Emergency Management, which keeps the county’s floodplain files, elevation certificates and map amendments.

4. Apply for a Floodplain Permit if mapped

Expect to supply an elevation certificate and, where the Floodplain Administrator asks, a flood study, before-and-after topographic survey or a FEMA map revision.

5. Permit the septic system

Hire a site evaluator and designer, then apply to TCEQ or, near Sam Rayburn, to ANRA before installation.

6. Plat any new lots

Dividing land so that any new tract is 10 acres or less needs a concept plan, preliminary plat and final plat approved by Commissioners Court.

Rather talk it over?

Call 1-855-478-4290 →

Inspections, plats and penalties

The county makes no building inspections and issues no certificate of occupancy for rural homes. Septic systems are inspected by the permitting authority before they are covered. In a flood zone, the Floodplain Administrator approves a permit only after finding that the work will not harm neighboring property, reduce the watercourse’s flood capacity or create a hazard during floods. Under state law the county can sue in District Court to stop unpermitted floodplain work, and fines can reach $100 a day.

Subdivisions: the county’s rules (amended September 10, 2018) cover land outside the cities divided into two or more parts when any part is 10 acres or less; divisions among family members and by will are exempt. Six copies of the preliminary plat go to the County Engineer at least 30 days before the Commissioners Court meeting, and an approved preliminary plat lasts 18 months. Where lots will use private septic systems, percolation tests by an engineer or registered sanitarian go with the plat. New roads need a 50-foot right-of-way and a 22-foot paved surface, and the county holds a “no negative impact” policy on flood levels and downstream flows. Plats inside a city’s extraterritorial jurisdiction are approved by the city or the county as set by interlocal agreement.

Rather not deal with the Jasper County building department?

Get a free quote →
County Clerk plat recording fees
ItemFee
Plat recording (recording, records management, archive and courthouse security fees)$56
Each extra page$5

The Clerk needs one original plat on an 18 x 24 inch sheet and one signed original no larger than 8.5 x 14 inches.

Texas building code

Texas has no single statewide building code: state law makes the International Residential Code the base code for homes in cities and the International Building Code the base for commercial buildings, with each city choosing the edition and its own amendments, while the National Electrical Code and the energy code apply statewide. Outside city limits most counties issue no building permits for homes. Texas building code rules

Want this handled start to finish?

Get a free quote →

Jasper County official resources

Jasper County permit FAQ

Do I need a building permit to build a house in rural Jasper County?

No. The county requires no building permit, inspection or certificate of occupancy outside the cities, though a Floodplain Permit and a septic permit may still apply.

When do I need a Floodplain Permit?

Before any work in a FEMA-mapped flood hazard area, including placing fill. New homes in the floodplain must have their finished floor at least 2 feet above base flood elevation.

Who issues septic permits in Jasper County?

TCEQ’s Region 10 office in Beaumont for most of the county; the county’s letter gives 409-898-3838. Within 2,000 feet of Sam Rayburn Reservoir’s 179-foot line, ANRA issues them, at $485 for a single-family system.

Inspections are where schedules slip.

Get a free quote →

Who issues building permits in the City of Jasper?

The City’s Code Enforcement and Inspections Department at City Hall, 465 S. Main St., through its iWorQ portal. Residential plans are drawn to the 2018 International Building Code and 2023 National Electrical Code.

Does Jasper County have zoning?

Only for the airport and floodplain areas.

How do I get an address for a new rural home?

From the South East Texas Regional Planning Commission’s 911 addressing office, 409-347-1911, ext. 6102.

Simplify Jasper County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Texas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Jasper County sooner?

Let Alliance prepare, file, and track your Jasper County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Jasper County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.