Calhoun County, South Carolina Building Permit Guide

Calhoun County’s Building and Planning Office in St. Matthews permits construction across the county, including inside St. Matthews and Cameron once the town signs off, and inspects on Mondays, Wednesdays and Fridays.

Authority: Calhoun County Building and PlanningCode: 2021 South Carolina Building CodesPhone: 803-874-4201
County authority
Calhoun County Building and Planning
Inspections
Mon, Wed and Fri, 24 hours’ notice
Permit contact
803-874-4201
2025 population
14,188

Calhoun County Building and Planning (102 Courthouse Drive, St. Matthews, 803-874-4201) issues building permits for the unincorporated county and, after a town pre-permit authorization, for St. Matthews and Cameron. Applications can be filed and tracked on the county’s CommunityCore portal; permits start at a $100 minimum, and residential plan review adds 10% of the permit fee.

What requires a permit in Calhoun County?

The county’s fee schedule covers building, sign and demolition permits, manufactured homes, electrical reconnects and floodplain development, and its published building guides cover the projects homeowners ask about most:

Building permits

  • New homes and additions
  • Accessory structures and pole barns
  • Swimming pools
  • Uncovered decks and porches
  • Patio covers and carports
  • Basement finishes and remodels (with a Scope of Work form)
  • Re-roofing, with the county’s roofing affidavit
  • Commercial buildings, signs and demolition

Other county approvals

  • Residential or commercial zoning permit
  • Floodplain development permit
  • Manufactured home placement
  • Electrical reconnects
  • Subdivision plats
  • Farm structures, using the agricultural affidavit and guidelines

Who issues building permits in Calhoun County?

The Calhoun County Building and Planning Office handles permitting and development for residential, commercial and industrial projects, and says it serves both the incorporated and unincorporated parts of the county. It also runs zoning, the Planning Commission and Board of Zoning Appeals, and code enforcement.

Short on time to read all of this?

Get a free quote →
Calhoun County Building and Planning
DetailInformation
Office102 Courthouse Drive, St. Matthews, SC 29135
Phone803-874-4201
Emailplanning@calhouncounty.sc.gov
OnlineCommunityCore public portal: apply and check permit status
ScheduleInspections Monday, Wednesday and Friday; plan reviews and meetings Tuesday and Thursday
Who permits each town in Calhoun County
PlaceBuilding permits
Unincorporated Calhoun CountyCalhoun County Building and Planning
Town of St. MatthewsThe county issues the permit after the town reviews the county’s St. Matthews pre-permit application and authorizes it; every contractor needs a Town business license
Town of CameronThe county issues the permit once Cameron signs its pre-permit authorization; for property inside town limits, visit Cameron Town Hall, 204 Boyce Lawton, first

Calhoun County permit fees

The county’s Building and Planning fee schedule dated July 1, 2025 values projects with the latest ICC Building Valuation Data table. Each band picks up where the last one ends.

Calhoun County building, sign and demolition permit fees
Project valueFee
Any permit$100 minimum
Up to $100,000$100 + $5 per $1,000
$100,001 to $500,000$600 + $4 per $1,000 over $100,000
Over $500,000$2,200 + $3 per $1,000 over $500,000
Residential plan review10% of the permit, $100 minimum
Commercial plan review35% of the permit

Not sure this scope needs a permit?

Get a free quote →
Other Calhoun County fees
ItemFee
Residential / commercial zoning permit$50 / $100
Floodplain development permit$200
Manufactured home$300
Electrical reconnect$50
Re-inspection$100 each
Refund of a permit25% of the permit fee is kept
Zoning appeal or map amendment$300

Example: a house valued at $200,000 pays $600 + (100 × $4) = $1,000 for the permit, $100 for residential plan review and $50 for the residential zoning permit. Starting without a permit doubles the permit fee.

Electrical, plumbing and mechanical work

Trade work on a house is shown on the plans and inspected by the county: the plan set must include plumbing and electrical sheets, with receptacle, GFCI, AFCI, smoke detector and panel locations and an exterior disconnect, and the HVAC contractor supplies Manual J and D calculations. Electrical and plumbing under a slab get their own inspection before the slab pour. The application must list every contractor and subcontractor with a copy of their state licence, plus a town business license for work inside St. Matthews or Cameron; the list is updated before the final inspection.

Rather talk it over?

Call 1-855-478-4290 →

How to apply for a Calhoun County building permit

1. Address and zoning

Get the 911 address verification and zoning approval from the county; inside St. Matthews or Cameron, complete that town’s pre-permit application.

2. Water, sewer or septic

Provide proof of water and sewer service, a state septic permit for a new system, or an installer’s approval of an existing one.

3. Plans

One paper and one digital copy, drawn to engineer’s scale: floor plan, wall section, plumbing, electrical and elevations, plus RESCheck, Manual J and D and a scaled site plan with setbacks, driveway and parking. The truss package can follow later.

4. Contractor papers

A copy of the contractor’s licence, a notarized agent letter if someone else collects the permit, a notarized letter from the homeowner authorizing the contractor, and the subcontractor list.

5. Submit

File through the CommunityCore portal or at the office; plan reviews are done on Tuesdays and Thursdays.

6. Inspections

Call at least 24 hours ahead for a Monday, Wednesday or Friday inspection.

Inspections in Calhoun County

Inspections run on Mondays, Wednesdays and Fridays with at least 24 hours’ notice, and the county cannot promise a time. When you call, give the address, permit number, inspection type, contractor name and a phone number. The county’s residential guide sets the order:

Rather not deal with the Calhoun County building department?

Get a free quote →
  • Foundation: permit posted, approved plans on site, rebar in place with a Ufer ground, and termite treatment before the pour.
  • Slab: 10-mil vapor barrier, compaction results for fill, and any under-slab plumbing or electrical inspected first.
  • Piers or CMU walls: crawl-space homes only, before the pour.
  • Wall and roof sheathing: nailing and hold-downs, before wrap or felt.
  • Rough-in: framing, electrical, plumbing, gas and mechanical in one visit, with gas lines pressure-tested (10 psi natural gas, 20 psi LP).
  • Insulation: R-19 floors, R-13 walls, R-30 ceilings.
  • Final (CO): with the duct leakage affidavit, energy certificate, septic permit to operate and termite letter. Paint, carpet and vinyl can wait.

Each re-inspection costs $100.

Calhoun County details to know

Owner-builders: homeowners pulling their own permit file the county’s Owner-Builder Affidavit and may use family members, not friends, to help; anyone hired under contract must be licensed for the full contract amount.

Floodplain: building in a flood zone needs the county’s $200 floodplain development permit under its flood ordinance.

Permit activity: the office posts monthly reports of issued permits on its web page.

South Carolina building code

Every South Carolina county and municipality enforces the 2021 South Carolina Building Codes, in force since 1 January 2023; the 2024 editions take effect statewide on 1 January 2027, and the energy code stays the 2009 International Energy Conservation Code. South Carolina building codes

Want this handled start to finish?

Get a free quote →

Calhoun County official resources

Calhoun County permit FAQ

Who issues building permits in Calhoun County?

Calhoun County Building and Planning at 102 Courthouse Drive, St. Matthews (803-874-4201), for the unincorporated county and, after town authorization, for St. Matthews and Cameron.

Inspections are where schedules slip.

Get a free quote →

How much is a building permit in Calhoun County?

$100 plus $5 per $1,000 of value up to $100,000, then $600 plus $4 per $1,000 above that. Residential plan review adds 10% (at least $100), so a $200,000 house pays $1,000 plus $100.

On what days are inspections held?

Monday, Wednesday and Friday, with at least 24 hours’ notice. Tuesdays and Thursdays are kept for plan reviews and meetings.

Do I need town approval in St. Matthews or Cameron?

Yes. Complete the town’s pre-permit application; the county issues the permit after the town signs it, and contractors in St. Matthews need a Town business license.

Can I apply online?

Yes. The county’s CommunityCore portal takes permit applications and shows their status.

What does a manufactured home permit cost?

$300 under the July 2025 fee schedule.

Simplify Calhoun County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in South Carolina. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Calhoun County sooner?

Let Alliance prepare, file, and track your Calhoun County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Calhoun County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.