Morrow County, Ohio Building Permit Guide

To get a building permit in Morrow County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Morrow County has no state-certified building department: commercial, industrial and multifamily plans go to the State of Ohio, and the county’s own permits are zoning permits in seven townships plus health and road permits.

Authority: State of Ohio (commercial plans)County zoning: 7 of 16 townshipsPhone: 419-946-1911
Building department
None certifiedCommercial plans go to the state
County zoning
7 townships6 zone themselves, 3 unzoned
Zoning permit
Buildings 120 sq ft+Site visit, fee paid on the spot
Septic permit
$399 new systemSite evaluation $400

The county’s own zoning office puts it plainly: Morrow County does not have a state-certified building department, so owners of commercial, industrial and multifamily buildings submit their plans to the State of Ohio, and the residential code is not enforced in the county. What the county does run is zoning: the Morrow County Zoning Office at 80 North Walnut Street, Mount Gilead (419-946-1911), issues zoning permits for new homes, additions and buildings of 120 square feet or more in seven townships. Septic and well permits come from the Morrow County Health District, and county road permits from the County Engineer.

What requires a permit in Morrow County?

Because the county has no certified building department, the permits most owners meet are zoning, health and road permits. Commercial, industrial and multifamily buildings still need Ohio Building Code plan approval, which the state gives directly. The zoning rules differ township by township, so the first question is where the land sits.

County zoning permit (7 townships)

  • A new home
  • An addition to a home or garage
  • Every building with a roof of 120 square feet or more, such as sheds, barns and garages
  • Expanding a building or use, or starting a new use of a building or land
  • A home business (conditional use application)

No county zoning permit

  • Decks, patios and similar uncovered structures, in general
  • Fences, which county zoning does not regulate
  • Land in Franklin, Perry and Peru townships, which have no zoning
  • Properties in the Candlewood Lake development, which follow their own control agreements
  • Land in townships and villages with their own zoning: ask them instead

Health permits apply wherever a home is not on a public sewer or water line: a sewage treatment system permit after a site evaluation, and a private water system permit for a new well. The County Engineer, responsible for 380 miles of county highway and for 348 bridges and about 1,890 culverts on county and township roads, issues driveway culvert, road cut and road bore, right-of-way, utility and special hauling permits, and publishes a road crossing application and design standards for streets in major subdivisions.

What Morrow County decides and what the state holds

Ohio’s building codes apply statewide, but only certified departments may enforce them, and Morrow County has none, so the state handles nonresidential plans and the county states that the residential code is not enforced locally. The county decides its zoning resolution in the seven townships that adopted county-wide zoning, its subdivision regulations through the Regional Planning Commission, its floodplain regulations, and its road permits; the board of health enforces the state’s sewage system law and rules for one-, two- and three-family homes.

Morrow County building department: who handles permitting

Morrow County has 16 townships and seven villages. Zoning, the permit that most often comes first, is split three ways among the townships, and every village zones for itself.

Short on time to read all of this?

Get a free quote →
Who handles zoning in Morrow County
AreaZoning authority
Bennington, Canaan, Congress (except Candlewood Lake), Gilead, Harmony, North Bloomfield and Washington townshipsMorrow County Zoning Office, 419-946-1911
Cardington, Chester, Lincoln, South Bloomfield, Troy and Westfield townshipsThe township’s own zoning inspector (listed on the county’s zoning page)
Franklin, Perry and Peru townshipsNo zoning regulations
Villages of Cardington, Chesterville, Edison, Fulton, Marengo, Mount Gilead and SpartaThe village (Fulton village office 419-864-2574; Marengo 419-253-1392; Sparta 419-768-7682)
Morrow County permit offices
OfficeHandlesContact
Morrow County Zoning OfficeCounty zoning permits, compliance certificates, variances, house numbers80 North Walnut Street, Suite C, Mount Gilead (across the hall from the auto title office); 419-946-1911; Monday to Friday 7:30 a.m. to 4:00 p.m.
Regional Planning CommissionPlats and lot splits in all townships80 North Walnut Street; 419-946-1911
Morrow County Health DistrictSeptic systems and wells; commercial plumbing through Richland Public Health (419-774-4520)419-947-1545
Morrow County EngineerDriveway culverts, road cuts and bores, right-of-way and utility permits150 Home Road, Mount Gilead; permits 419-947-4530; Monday to Friday 7:30 a.m. to 4:00 p.m.
State of Ohio, Division of Industrial ComplianceCommercial, industrial and multifamily plan approval614-644-2223

A sliver of the City of Galion lies in Morrow County, but the Census counts no residents there; Galion is mainly a Crawford County city. The Board of Building Standards’ building-department look-up maps any certified authority for an address.

Morrow County permit types

Residential permits

With no certified residential department and the county stating that the residential code is not enforced, a house in Morrow County needs no local building permit or plan review. Ohio law says that where no department certified for residential buildings has jurisdiction, the owner does not have to submit plans for a house. The county’s zoning office is clear that its own sign-off is not a building approval: after a new home is finished it makes a compliance inspection for use, setbacks and parking and issues a Compliance Certificate, which is not an occupancy permit. A new home in the zoned townships must meet the zoning resolution, and a manufactured home may not be moved in if it is more than ten years old, must be at least 1,100 square feet, and must have septic and water service; only one home is allowed per residential lot.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial, industrial and multifamily owners submit plans to the State of Ohio for approval, and the state reviews and inspects nonresidential work where no certified department has jurisdiction. County zoning still applies to commercial buildings in the seven county-zoned townships, with different setbacks and uses in commercial and industrial districts, so the zoning office asks owners to check with it early.

What comes before the building permit

  • Zoning permit. Call the zoning office, which gathers parcel information from county sources and reviews the rules with you; then mark the project location and lot lines and book a site visit, where the fee is collected and the permit issued if everything matches.
  • Setbacks. In residential and agricultural districts the main building needs a 35-foot front yard measured from the edge of the right-of-way, 15-foot side yards and a 40-foot rear yard; accessory buildings stay 15 feet from side and rear lines.
  • Lot splits. The Regional Planning Commission reviews every plat and lot split, and offers free technical reviews on Tuesdays by appointment with Regional Planning, Zoning, Health, Soil & Water and Engineering at one table.
  • Septic. The health district reviews vacant lots that need a sewage system before anyone builds, once soil evaluation and system design forms are submitted.
  • Floodplain. The county’s floodplain information page posts a floodplain permit application and the Morrow County Flood Damage Reduction Regulations; check them before building in a mapped flood area.
  • Address. A new house number costs $40 through the zoning office.

When a project cannot meet the county zoning resolution, the Board of Zoning Appeals can grant a variance, normally only where the site has an extraordinary feature such as steep slopes, dense woods or an odd lot shape; the application carries its own requirements and fee, and the case goes to a public hearing with legal notice deadlines. A home business in the county-zoned townships needs a conditional use approval. Both forms can be filed in person or by email to the zoning office.

Rather talk it over?

Call 1-855-478-4290 →

Morrow County permit costs and fees

There is no county building permit fee. The zoning office collects its zoning permit fee at the site visit; the amount is not listed on its web pages, so call 419-946-1911 for it. State plan approval fees for commercial work are set by the Division of Industrial Compliance, and the Board of Building Standards assessment of 3% applies to nonresidential fees. The clearest published fees are the health district’s 2026 Environmental Health schedule.

Morrow County Health District fees (2026 schedule)
Permit or serviceFee
Site evaluation (any)$400
New sewage treatment system (or gray water system) installation$399 ($325 local + $74 state)
Replacement of an existing system$399
Alteration of an existing system$235
Tank replacement / one component$225
Abandoning a system$175
New private water system, 1–3 family dwelling$374 ($280 local + $74 state + $20 ODNR)
Well alteration / sealing / test well$145 / $145 / $251
Sewage system installer registration$230

Worked example from the schedule: a new home on a vacant, unsewered lot with a new well pays $400 for the site evaluation, $399 for the septic installation permit and $374 for the well permit, or $1,173 in health district fees. The zoning office charges $40 for a new house number, and variance and conditional use applications carry their own fees and a public hearing.

Trade permits and who may pull them

The county’s pages list no county electrical, HVAC or residential plumbing permit, since there is no certified building department. Commercial and industrial plumbing is under the Morrow County Health District’s authority, and the district contracts with Richland Public Health to run that program: plumbing questions, permits and inspection requests go to Richland Public Health’s environmental health office at 419-774-4520. The district has stopped requiring plumbers to register in Morrow County.

Rather not deal with the Morrow County building department?

Get a free quote →
  • Commercial trades: electrical, HVAC, hydronics, plumbing and refrigeration contractors on commercial work hold OCILB licenses, and their work is reviewed with the state plan approval.
  • Sewage contractors: installers ($230), service providers and septage haulers register with the health district to work in Morrow County.
  • Wells: private water system construction, alteration and sealing are permitted by the health district.
  • Contractor registration: the county’s pages show no county contractor license or registration for builders.

How to apply for permits in Morrow County

1. Find the township or village

Use the county zoning page to see whether the county, the township or the village zones the land, or nobody does.

2. Book a technical review if you are splitting land

Free on Tuesdays through the Regional Planning office.

3. Start the septic and well process

Send soil evaluation and design forms with the site review application and fee to the health district, which also posts a new home construction process form and lists of soil scientists, designers and registered installers.

4. Get the zoning permit

Call the zoning office, stake the building and lot lines, and pay at the site visit.

5. Get road permits and a house number

Driveway culvert and right-of-way permits from the Engineer; a house number from the zoning office.

6. File commercial plans with the state

Commercial, industrial and multifamily projects submit plans to the Division of Industrial Compliance.

Review, corrections and what causes delay

The zoning permit is issued at the site visit only if the staked location matches the plan, so unclear lot lines are the usual delay. Septic site reviews are scheduled once the application, soil evaluation, system design and fee have all arrived. The Engineer’s downloadable permit forms are not valid until they are brought in for the Engineer’s signature and payment.

Inspections and certificates in Morrow County

For houses there are no county building inspections. The zoning office inspects a finished project for zoning compliance and issues a Compliance Certificate, and the health district inspects the installation, operation and maintenance of sewage systems, abates sewage nuisances and collects septage pumping reports from registered haulers. Commercial buildings reviewed by the state are inspected by the state, and no building may be occupied until a certificate of occupancy is issued.

The zoning office says it does not patrol the townships looking for changes, and acts on written reports of possible violations; many older buildings predate zoning and are allowed to remain.

Ohio building code in Morrow County

The Ohio Building Code applies to commercial work through state plan approval; the county says the residential code is not currently enforced within Morrow County. FEMA’s Community Status Book lists unincorporated Morrow County (community 390868) as participating in the National Flood Insurance Program, with flood maps dated January 11, 2024.

Want this handled start to finish?

Get a free quote →

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Morrow County permit search and official resources

There is no online permit search. Ask the zoning office for zoning permits and compliance certificates, the health district for septic and well records, and the Engineer for road permits; commercial plan approvals are state records. The county takes public records requests through the Commissioners’ office.

Inspections are where schedules slip.

Get a free quote →

Morrow County permit FAQs

Does Morrow County have a building department?

No. The county says it has no state-certified building department; commercial, industrial and multifamily plans go to the State of Ohio, and the residential code is not enforced locally.

Do I need a permit to build a house?

No local building permit, but you need zoning approval where the land is zoned, septic and well permits on an unsewered lot, and road permits for a driveway.

Do I need a zoning permit for a shed?

In the seven county-zoned townships, yes for any building with a roof of 120 square feet or more; fences and uncovered decks generally need none.

Which townships have no zoning?

Franklin, Perry and Peru townships.

What are the setbacks in the county-zoned townships?

For houses in residential and agricultural districts: 35 feet front (from the right-of-way), 15 feet side and 40 feet rear.

Who handles commercial plumbing?

Richland Public Health, under contract with the Morrow County Health District; call 419-774-4520.

Will I get an occupancy permit for a new home?

Not from the county. In the county-zoned townships the zoning office inspects the finished home and issues a Compliance Certificate, which covers zoning only.

How much is a septic permit?

$399 for a new system, after a $400 site evaluation, under the health district’s 2026 schedule.

Simplify Morrow County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Morrow County sooner?

Let Alliance prepare, file, and track your Morrow County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Morrow County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.