Inside the City of Delaware, permits come from the city’s state-certified Building Division, part of Planning & Community Development at the City Hall Annex, 1 South Sandusky Street (740-203-1600, option 3); Jerry Warner is the Chief Building Official. Applications go through the online permit portal, fees under Ordinance 22-107 are invoiced after review, and plumbing permits come from the Delaware County health district, not the city. Since 2026 contractors no longer register with the city.
What requires a building permit in Delaware?
The city states the rule broadly: all new construction, alterations, improvements and replacements need an approved permit before work starts. Its FAQ then narrows it for homeowners.
Permit needed (residential)
- Structural, electrical and mechanical work, including remodels beyond simple fixture swaps
- Fences, decks, sheds, gazebos, pavilions and detached garages
- Home additions and pools (every pool needs a 4-foot fence, even with an automatic cover)
- Re-roofing, HVAC and furnace work, gas lines and solar or electrical work
No permit named by the city
- Patios, which the FAQ says do not require a permit
- Plumbing is still regulated, but by the health district rather than the city
For a commercial property, all structural, electrical and mechanical work needs a permit. Clearing trees on a development site has its own Tree Clearance Permit, and planning cases use the Master Application Form.
What Delaware decides and what the state holds
Ohio adopts the building codes, and the city’s department is certified to enforce them. Delaware itself sets permit fees (Ordinance 22-107), development impact fees, its Planning and Zoning Code (Part 11 of the Codified Ordinances), flood rules in Chapter 1347 as amended by Ordinance 23-89, and historic district review downtown. Contractor registration was dropped in 2026. Plumbing is permitted and inspected by the Delaware General Health District. The Board of Building Standards look-up map confirms which department holds authority for an address.
Delaware building department: who handles permitting
The Building Division of the Planning & Community Development Department reviews plans, issues permits and inspects; the Chief Building Official is also the city’s floodplain administrator. The Planning and Zoning Division in the same department reviews zoning permits and staffs the Board of Zoning Appeals, the Planning Commission and the Historic Preservation Commission. Plumbing applications go to the county health district. Besides the Planning and Community Development Director and the Planning and Zoning Administrator, three development planners review zoning permit applications and coordinate land development projects.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, City Hall Annex, 1 South Sandusky Street, Delaware, OH 43015 |
| Phone | 740-203-1600, option 3 (City Hall 740-203-1000) |
| Chief Building Official | Jerry Warner (also floodplain administrator) |
| Inspection requests | planning@cityofdelawareoh.gov, by noon on the business day before |
| Plumbing permits | Delaware General Health District, 740-368-1720 (plumbing services) |
| Engineering inspections | Sidewalk, approach and grading: 740-203-1810 |
The city’s permits cover land inside city limits only. For addresses outside the city, its planning FAQ points owners to the Delaware County Building Department (740-833-2200) and the township zoning inspector; the Delaware County guide covers that office. Land joins the city only when its owner asks for annexation, often to get city water and sewer; once annexed, it falls under the city’s zoning and permits.
Delaware permit types
Applications are made in the city’s online permit portal; the posted PDF applications show what each one asks for. For new houses, additions and oversized plans the residential application wants one full set of building drawings, a plot plan showing distances to property lines and an electronic set.
Residential permits
- Decks and additions: a site plan with drawings and specifications.
- Fences: a site plan and a description of the design and materials.
- Pools: a site plan and all pool specifications, including the electrical work; a pool also carries electrical and zoning fees.
- Sheds, gazebos, pavilions and garages: a site plan and drawings; for a prefabricated building the maker’s specifications will do.
- Roof, HVAC, furnace and gas line: just the online form.
- Solar and electrical: specifications, with a structural letter when one is required.
- New homes: list the number of fireplaces, the square footage and the number of bedrooms on the application.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
The commercial application asks for the use group, construction type, square footage and occupant load, any change of use, and the electrical, mechanical and fire protection details; an electrical service over 400 amps needs sealed drawings. Plan review is charged by discipline (structural, electrical, HVAC, insulation and energy, fire protection), and a change of use permit is $40.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning: each residential application is checked by planning and zoning staff, with a zoning review fee; variances go to the Board of Zoning Appeals.
- Historic district: downtown projects can need Historic Preservation Commission review.
- Flood hazard areas: the floodplain administrator decides whether a structure lies in a flood hazard area and checks that construction meets the elevation and floodproofing standards.
- Impact fees: new dwelling units and nonresidential floor area are entered on the city’s Development Impact Fee Calculation Form A with the building permit application, and the Building Official checks it before sending it to planning.
Not sure this scope needs a permit?
Get a free quote →Delaware permit costs and fees
Fees follow the city’s fee schedule in Ordinance 22-107, which the department links from its page; the summaries printed on the residential and commercial applications are below. Payment is not taken when you apply: the city invoices the fees after review. The state Board of Building Standards adds 1% on residential and 3% on commercial permits.
| Permit | Fee |
|---|---|
| New home | $385 + $0.05 per sq ft |
| Garage, addition, alteration or remodel | $82.50 + $0.05 per sq ft |
| Residential plan review | $55 |
| HVAC: new home or addition over 1,000 sq ft / minor work | $165 / $55 |
| Furnace, air conditioner or water heater replacement | $30 |
| Electrical, new work or additions | $110 up to 1,000 sq ft; $110 + $0.02 per sq ft from 1,001 to 2,000; $110 + $0.04 per sq ft from 3,001 |
| Electrical service upgrade or minor work | $55 |
| Insulation / gas line test (new homes and large additions) | $82.50 / $77 |
| Shed up to 200 sq ft / deck or gazebo / fence | $35 / $45 / $35 |
| Pool | $45 + $55 electrical + $125 zoning |
| Re-roof | $55 |
| Certificate of occupancy: final / temporary | $85 / $140 |
| Zoning compliance / zoning review | $70 / $45 |
| Fireplace / demolition / miscellaneous inspection / reissued lost permit | $40 / $110 / $35 / $55 |
| Re-inspection | $90 |
| Commercial new building or addition | $154 + $0.07 per sq ft, plus structural $88 + $0.05, electrical $88 + $0.04 and HVAC $88 + $0.03 per sq ft |
| Commercial alteration or tenant space | $66 + $0.04 per sq ft |
| Commercial re-submitted plan review | $110 per hour |
| Commercial excavation to connect utilities / water or sewer permit / sidewalk or approach | $55 / $30 / $40 |
| Commercial demolition / change of use / miscellaneous | $110 / $40 / $85 |
| Commercial certificate of occupancy: temporary / final; re-inspection from the third visit | $110 / $85; $90 |
Rather talk it over?
Call 1-855-478-4290 →Worked example using the residential sheet: a 2,400-square-foot new house is $385 plus 2,400 × $0.05 ($120), or $505, plus the $55 plan review, $560 before the 1% state fee, electrical, HVAC and other trade items. The electrical rates printed on the form skip houses of 2,001 to 3,000 square feet, so ask the division for that band, and development impact fees are calculated separately on Form A.
Trade permits and who may pull them
Electrical and HVAC permits are issued by the city as part of the building application or through the portal, while plumbing is permitted and inspected by the Delaware General Health District; its plumbing services line is 740-368-1720. Plumbing underground, rough and final inspections are scheduled with the health district, and under the city’s inspection policy the frame and mechanical rough cannot be scheduled until the plumbing rough passes, nor the mechanical and building finals approved until the plumbing final passes.
Since 2026, contractors are no longer required to register with the City of Delaware, so the line on the December 2022 residential form saying all contractors must be registered is out of date. Commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors still need their Ohio licenses from the OCILB, which cover commercial work. The fire suppression permit for commercial work is $110 plus $5 per signaling device or sprinkler head, up to 300.
How to apply for a Delaware building permit
Outside city limits, Delaware County’s building office and the township handle permits.
Find out whether the lot needs zoning approval, historic review or floodplain review.
Site or plot plan with setbacks, drawings and specifications for the work type; the impact fee form for new units.
Create an account in the city’s online permit portal and upload the application and plans.
Any plumbing work needs its own health district permit.
The city bills the fees after review; the permit and approved plans must then be kept on the job site.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The city does not publish review times. Revisions to a paid permit are their own application type, and commercial plans that come back for another review are billed at $110 an hour. A missing plot plan, a missing electronic plan set on a new house or addition, plumbing that has not been permitted through the health district, or a pool without the required 4-foot barrier can each hold up a permit.
Inspections and certificates in Delaware
Inspection requests go by e-mail to planning@cityofdelawareoh.gov by noon on the business day before, with the contact name and phone, the permit number and the date wanted. Under the inspection policy dated May 18, 2026, inspections run Monday to Friday from 9 a.m. to 2 p.m.; only footings, pre-pour walls and occupied homes get a set time (with a two-hour window), inspectors do not call ahead, and commercial and solar inspections need someone on site.
The regular inspection sequence for a new one- to three-family home runs: sewer, footer, foundation, slab where steel is used, gas and electrical rough (electrical must pass before anything else proceeds), health district plumbing rough, frame and mechanical rough together, insulation, then the electrical, plumbing and gas finals, a blower door test uploaded to the portal, and the mechanical and building finals together. Deck post holes and roofs are inspected from photos uploaded to the permit, showing hole depth, width and footer, or roof decking, flashing and ice barrier at rough and the finished roof at final. Sidewalk, approach and grading finals are booked with Engineering. Two inspections depend on the design: a fire-resistance inspection, scheduled before framing or after insulation, and a drywall or brace-wall inspection only when the drywall is part of the wind bracing plan. The gas rough and subsiding inspections can be done any time before insulation. The final certificate of occupancy costs $85, and a temporary one $140.
Ohio building code in Delaware
FEMA’s Community Status Book lists the City of Delaware (community 390148) as participating in the National Flood Insurance Program, with flood maps effective December 21, 2023. The city’s Flood Damage Reduction Ordinance 23-89 amends Chapter 1347, and the Chief Building Official serves as floodplain administrator.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Delaware permit search and official resources
Each permit has its own record in the city’s online permit portal, where applicants upload documents and inspection photos. For older permits, plans or inspection records, use the city’s Public Records Request page.
Want this handled start to finish?
Get a free quote →- Delaware Building Division
- Online permit portal
- Permit applications
- Residential building and zoning application with fee sheet
- Commercial application with fee sheet
- Inspection policy, May 18, 2026
- Development impact fee forms A to E
- Tree clearance permit
- Master application form (planning)
- Floodplain regulations and requirements
- Planning and zoning
- Planning and Community Development FAQ
- Public records request
- Ohio BBS building department look-up
- Ohio Board of Building Standards
- FEMA Community Status Book, Ohio
Inspections are where schedules slip.
Get a free quote →Delaware building permit FAQs
Do contractors have to register with the City of Delaware?
No. Starting in 2026 the city no longer requires contractor registration; commercial trade contractors still need their state licenses.
Who issues plumbing permits in Delaware?
The Delaware General Health District, not the city; its plumbing inspections are also booked with the health district.
Do I need a permit for a patio or a fence?
A patio does not need a permit; a fence does, with a site plan and a description of the fence ($35).
How much is a permit for a new house?
$385 plus $0.05 per square foot, plus $55 plan review and the 1% state fee, with electrical, HVAC, insulation and gas test fees on top; the city invoices the total after review rather than at submission.
How do I book an inspection?
E-mail planning@cityofdelawareoh.gov by noon the business day before, with your name, phone, permit number and requested date.
My neighbor’s new fence may be on my land. Will the city decide?
No. The planning FAQ treats property line disputes as a civil matter between neighbors and suggests checking or commissioning a survey.
Does Delaware charge development impact fees?
Yes. New dwelling units and new nonresidential floor area are listed on the city’s Development Impact Fee Calculation Form A, filed with the building permit application; the Building Official verifies the form and forwards it to the Planning Department, and the city posts its impact fee forms A through E together.
I live outside the city. Who issues my permit?
The Delaware County Building Department (740-833-2200), together with your township zoning inspector.
Simplify Delaware permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Delaware sooner?
Let Alliance prepare, file, and track your Delaware permits while your crew stays on the job.
More Ohio permitting guides
Delaware County
Read guide →Powell
Read guide →Union County
Read guide →Dover Building Permit Guide
Read guide →Dublin Building Permit Guide
Read guide →Eastlake Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Delaware permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.