In Bexley, the city’s own Building and Zoning Department at City Hall, 2242 East Main Street (614-559-4240), reviews plans, issues building, electrical, mechanical and other permits and inspects the work, for houses and commercial buildings alike. Applications go through the city’s OpenGov online permitting portal, contractors must register with the city ($125), and additions, garages, porches and new homes need Architectural Review Board approval before a permit can be issued. A new house is charged $500 plus $0.10 per square foot, with 1% added for the state.
What requires a building permit in Bexley?
The department’s own list covers air conditioning and heating units, electrical and plumbing work, additions and remodeling, demolition, driveways, fences, yard lights, sidewalks, swimming pools and hot tubs. Its “What Review Does My Project Need?” table goes further and shows, for each common project, whether design review, zoning review and a permit are needed.
Permit needed
- New homes, additions, front and rear porches, and new or replacement garages (after ARB approval)
- Decks and pergolas, and solar panels (after a staff minor architectural review)
- Fences, driveways and patios, and sidewalks, approaches and curbs
- Interior alterations, which need a permit but no design or zoning review
- New window openings in an exterior wall
Design review, no permit (per the table)
- Replacement windows in existing openings
- Siding
- Asphalt and other roofs that are not slate or shake (staff MA-1 review)
- Slate and shake roofs, which go to the Architectural Review Board
The review table and the fee schedule do not quite agree on exterior work: the table marks replacement windows, siding and standard roofs as needing no permit, yet the schedule lists a $90 exterior-improvements charge for roofing, siding and window replacement ($70 each when two or more are done). Ask the department which applies before you book the job. A design review approval is not a permit, and no work may start until the permit itself is issued.
What Bexley decides and what the state holds
The city is certified by the state to approve and inspect all commercial and residential construction, so plan review, permits and inspections all stay at City Hall. Bexley sets its own fee schedule, registers contractors, runs its zoning code and two design boards, enforces its Building Maintenance Code, and purchases water and sewer service from Columbus. The state adopts the building codes the department enforces, collects its Board of Building Standards share on top of the city’s fees, and licenses commercial electrical, HVAC, plumbing, hydronics and refrigeration contractors.
Short on time to read all of this?
Get a free quote →Bexley building department: who handles permitting
All of Bexley lies in Franklin County, and the Building and Zoning Department handles every permit inside the city; the Franklin County Building Department does not issue permits here. Matt Klingler is the director, listed in the city directory as Director of the Building and Planning Department (other city pages call the post Building & Development or Building & Planning Director). The same office runs zoning, community planning with the city planner, and code enforcement, and it staffs both design boards.
| Detail | Information |
|---|---|
| Office | Building and Zoning Department, Bexley City Hall, 2242 E. Main Street, Bexley, OH 43209 |
| Phone | 614-559-4240 (City Hall main line 614-559-4200) |
| Hours | Monday to Friday, 8:00 a.m. to 4:30 p.m. |
| Department head | Matt Klingler, Director |
| Online filing | OpenGov online permitting portal (applications, board reviews, contractor registration) |
| Certification | Certified by the state to approve and inspect all commercial and residential construction |
Bexley permit types
Every application, from a fence to a new house, starts in the OpenGov portal, where each record type matches a line in the review table: Fence, SITE (driveways and patios), ROW (sidewalks, approaches and curbs), MA-1, MA-2 and MA-3 minor architectural reviews, ARB and BZAP board reviews, and RBLD for interior work.
Residential permits
- New houses, additions, porches and garages go to the Architectural Review Board first. The ARB checklist asks for a scaled site plan with setbacks and neighboring structures, elevations of every side, photographs, sectional details from foundation to roof, floor plans and all exterior materials and colors; a new house adds a zoning sheet showing lot coverage, streetscape elevations, a landscape plan and, where the board asks, a tree preservation plan.
- Minor exterior work is reviewed by the Residential Design Consultant or the Zoning Officer without a board hearing: MA-1 covers roofs, windows and siding, MA-2 covers decks and garages, and MA-3 covers solar panels.
- Interior remodeling needs a building permit but skips design and zoning review; a minor interior alteration is $100.
- Demolition of a house or garage is a permit with a cash cleanup bond, and demolishing a principal structure is a major exterior change that goes to the ARB.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial buildings are reviewed and inspected by the same department under the state’s commercial code. Exterior changes must meet the city’s commercial Design Guidelines, reviewed by the ARB, and the zoning code, applied by the Board of Zoning and Planning. Commercial work pays an environmental review application fee based on project value in addition to the building permit, and exterior signs are charged the same way.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Design review. The ARB meets at 6:00 p.m. on the second Thursday of each month; applications are due four weeks ahead. Staff handle MA reviews without a meeting.
- Board of Zoning and Planning (BZAP). Variances, special uses and conditional uses go to BZAP, which meets at 6:00 p.m. on the fourth Thursday and also advises City Council on rezoning. When BZAP needs an ARB recommendation, file six weeks before the BZAP meeting. Both boards recess in December, and incomplete applications are taken off the agenda.
- Zoning review. Fences, driveways, patios, decks, solar, garages, porches, additions and new homes all get zoning review; a residential zoning permit is $50 for an addition, $30 per accessory structure and $60 for a new single-family house.
- Sewer and water. Service comes from Columbus, and a new connection pays a sewer capacity fee based on Columbus fees plus a $500 city impact fee.
- Streets and alleys. Work in a street or alley right-of-way needs an opening permit and a cash bond.
Bexley permit costs and fees
The Building Department’s fee schedule, linked from the Building & Zoning page as “Permit Fees”, has a residential page and a commercial page. It does not print an ordinance number or adoption date. For residential permits the schedule says to add 1% for the state Board of Building Standards; state law sets the commercial share at 3% of fees. Plumbing fees match Franklin County Board of Health fees.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| New 1, 2 or 3 family dwelling | $500 + $0.10 per sq ft |
| 1, 2, 3 family additions and alterations | $400 + $0.12 per sq ft |
| Minor interior alteration | $100 |
| Exterior improvements (roofing, siding, window replacement) | $90; $70 each for 2 or more |
| Accessory structure under 200 sq ft / stoop up to 4 ft x 6 ft | $50 / $35 |
| Garage, carport or accessory structure over 200 sq ft | $150 for a single car + $50 each additional space |
| Plan review (residential) | $60 per floor or actual costs incurred |
| Building fee deposit | $50, forfeited if the permit is not issued |
| Electrical | $75 minimum; $7 base + $0.70 per outlet, fixture and receptacle; service $70 + $0.16 per ampere |
| HVAC / ventilation / gas | $85 per unit / $30 per unit / $70 |
| Swimming pool or hot tub | $100; $50 under 36 inches deep |
| Fence / driveway approach | $50 / $75 ($65 each for 2 or more) |
| Demolition | Principal structure $250, accessory $100, each + $500 cash cleanup bond |
| Certificate of occupancy / conditional occupancy | $70 / $180 + escrow ($200–$300 per unfinished item) |
| New commercial building | $800 + $0.15 per sq ft |
| Commercial addition or alteration | Over 2,000 sq ft: $700 + $0.20 per sq ft; under 2,000 sq ft: $400 + $0.20 per sq ft |
| Commercial environmental review application | $100 up to $5,000 of value, rising in steps to $1,000 over $750,001 |
| Contractor registration | $125, all construction trade contractors |
Board fees are separate: a minor architectural application is $50, and an ARB or BZAP board review is $90 for work valued up to $10,000 plus $5 for each further $10,000, capped at $600. A single-family zoning variance is $100. Reading the residential line as written, a 2,400-square-foot new house is $500 plus $240, or $740, before the 1% state fee, plan review, zoning and trade permits.
Trade permits and who may pull them
Bexley regulates contractors through registration and bonding. Any contractor working in the city must be registered with Bexley before taking out permits; registration is done in the OpenGov portal and costs $125, and the city posts a list of currently registered contractors. Commercial electrical, HVAC, plumbing, hydronics and refrigeration contractors also need their Ohio Construction Industry Licensing Board license.
Rather not deal with the building department?
Get a free quote →- Electrical: issued by the city, priced per outlet, fixture and receptacle with a $75 minimum, plus a service charge per ampere; low-voltage work is $90 plus $0.08 per square foot.
- Heating, cooling and gas: HVAC permits are $85 per unit, ventilation $30 per unit and gas lines $70; a generator permit is $65, and the schedule notes it assumes no objections from neighbors within 40 feet.
- Plumbing: the city’s Board of Health contracts with the Franklin County Board of Health, and Bexley charges the county health board’s plumbing fees. Ask the department where to file and who books plumbing inspections.
- Fire protection: sprinkler or hood suppression work is $60, and a kitchen hood permit is $185.
How to apply for a Bexley building permit
Check the department’s review table, or call 614-559-4240, to see whether the job needs staff review, the ARB or BZAP before a permit.
Each contractor registers with the city through OpenGov before work starts.
Submit the MA, ARB or BZAP application in OpenGov and name the meeting date you want; ARB files four weeks ahead, BZAP six weeks when an ARB recommendation is needed.
Once design approval is in hand, file the building or trade permit with plans and pay the $50 building deposit.
Fees follow the department’s schedule, with 1% added for the state on residential permits.
Begin work only when the permit, not just the design approval, has been issued.
Review, corrections and what causes delay
Missing board materials are the usual hold-up: the department removes incomplete applications from the agenda and contacts the applicant directly, so the case waits for a later monthly meeting. The December recess of both boards means late-autumn filings may wait until January. A resubmitted application costs $50, and when Council, BZAP or staff need an outside architect or planner, the applicant pays that cost on top of the filing fees.
Inspections and occupancy in Bexley
Book inspections with the city’s online Inspection Scheduling Form, linked from the Building & Zoning page, or by calling 614-559-4240. Inspections are made only on weekdays, Monday through Friday. A foundation start is $150, a certificate of occupancy $70, and lost permit documents can be reissued for $35.
A home that is ready to live in before the outside work is finished can receive conditional occupancy for $180 plus escrow held against each open item: $200 each for missing grass, landscaping, sidewalk, gutters and downspouts or architectural conditions, and $300 each for an unfinished driveway or final grade. After construction, the department’s code enforcement officers apply the Building Maintenance Code to the exterior, usually with two notices before a citation to Mayor’s Court.
Want this handled start to finish?
Get a free quote →Ohio building code in Bexley
Bexley enforces the state’s commercial and residential codes through its own certified department, while its local rules, design guidelines and fees sit in the codified ordinances published by American Legal Publishing. FEMA’s Community Status Book lists the City of Bexley (community 390168) as participating in the National Flood Insurance Program, with its current flood map dated June 17, 2008.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Bexley permit search and official resources
Permit and code records can be searched by address in the city’s OpenGov records search, which the Code Enforcement page links. Site plans and exhibits for board cases are filed on the city’s Public Documents page under Board of Zoning Appeals and Planning. For anything else, file a public records request through the city’s NextRequest portal, where fulfilled requests are also posted.
- Bexley Building and Zoning Department
- OpenGov online permitting portal
- Building Department fee schedule (residential and commercial)
- List of registered contractors
- Architectural Review Board
- ARB application checklist
- Board of Zoning and Planning
- Code enforcement and records search
- Codified ordinances
- Public records requests
- Franklin County Public Health plumbing
Inspections are where schedules slip.
Get a free quote →Bexley building permit FAQs
Do I need a permit to replace my roof in Bexley?
The review table calls for a staff MA-1 review but no permit for roofs that are not slate or shake; slate and shake roofs go to the ARB. The fee schedule still lists a $90 exterior-improvements charge, so confirm with the department.
How much is a building permit for a new house?
$500 plus $0.10 per square foot, with 1% added for the state, plus plan review, zoning and trade permits.
Does a fence need a permit?
Yes. A fence gets staff design review, zoning review and a $50 permit; one that needs a variance goes to BZAP.
Can I start work once the ARB approves my plans?
No. Design approval is not a permit; you still need the building permit before any work begins.
Do contractors have to register?
Yes. Every contractor working in Bexley registers with the city, at $125.
When does the Architectural Review Board meet?
At 6:00 p.m. on the second Thursday of each month, except December; applications are due four weeks before.
How do I schedule an inspection?
Use the online Inspection Scheduling Form or call 614-559-4240; inspections are made Monday through Friday.
Simplify Bexley permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Bexley sooner?
Let Alliance prepare, file, and track your Bexley permits while your crew stays on the job.
More Ohio permitting guides
Franklin County
Read guide →Columbus
Read guide →Dublin
Read guide →Blue Ash Building Permit Guide
Read guide →Brecksville Building Permit Guide
Read guide →Broadview Heights Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Bexley permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.