Warren County, New York Building Permit Guide

To get a building permit in Warren County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Warren County’s own Fire Prevention and Building Code Enforcement office issues building permits in every town and village except Queensbury and the City of Glens Falls, which run their own code offices; applications are filed in person in Lake George.

Authority: Warren County Fire Prevention & Building Code EnforcementCode: 2025 NYS Uniform Code and Energy CodePhone: (518) 761-6542
County office
Lake George1340 State Route 9, Human Services Building, 3rd floor
New house fee
$0.35 per sq ft$150 minimum; schedule effective January 2026
Plan review
2 weeks minimumIn the order applications arrive
Own code offices
2 placesTown of Queensbury and City of Glens Falls

In Warren County the county government is the building department for most of the map. Its Fire Prevention and Building Code Enforcement office, on the third floor of the Human Services Building at 1340 State Route 9 in Lake George, administers the Uniform Code and Energy Code in ten towns and the Village of Lake George, issuing permits, reviewing plans, inspecting and signing certificates of occupancy. The two exceptions are the Town of Queensbury and the City of Glens Falls, where the county says it has no enforcement role. Zoning stays local everywhere, so each application carries a zoning sign-off from the town or village.

What requires a building permit in Warren County?

The county office lists what it issues: building permits for new homes, additions, alterations and commercial work, permits for manufactured homes, demolition permits, and separate permits for wood stoves, fireplaces and pellet stoves. Its fee schedule shows the rest of the range, from garages, pole barns and storage sheds to swimming pools, solar arrays and septic permits. Commercial additions, alterations, new buildings and any change of occupancy or use start with a call to the office before an application is drawn up.

County permits

  • New one- and two-family homes, townhouses and modular homes
  • Additions and alterations, with amendments when plans change
  • Garages, pole barns and storage sheds
  • Manufactured homes
  • Swimming pools and solar installations
  • Wood stoves, fireplaces and pellet stoves
  • Demolition
  • Commercial construction and changes of use

Handled elsewhere

  • Queensbury and Glens Falls parcels: their own code offices
  • Zoning compliance: the town or village zoning officer
  • Work in a county road right-of-way: county Public Works

What the towns decide and what the state holds

The building standards are the state’s 2025 Uniform Code and Energy Code, and the county applies them the same way in Bolton as in Thurman. What changes from one town to the next is local law: zoning districts, setbacks, shoreline and site plan rules, short-term rental rules and anything else the town or village has adopted. That is why the county wants two sets of plans signed or initialed by the local zoning officer and a signed zoning compliance certificate before it will review a building application. Design loads can also vary within the county: the snow load map adds 2 pounds per square foot for every 100 feet of elevation above 1,000 feet, read from the county GIS contours.

Warren County building department: who handles permitting

The table lists every city, town and village the Census Bureau counts in the county. For the ten towns and one village served by the county, the local zoning officer comes first and the county permit follows.

Short on time to read all of this?

Get a free quote →
Building permit offices in Warren County (13 municipalities)
PlaceWho issues building permitsOfficial page
Glens Falls (city)City Building and Codes Department; see the Glens Falls guideCity pages, linked in that guide
Queensbury (town, no villages)Town Buildings & Codes; see the Queensbury guideTown pages, linked in that guide
Bolton (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Chester (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Hague (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Horicon (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Johnsburg (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Lake George (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Lake George (village, in the town of Lake George)County Fire Prevention & Building Code Enforcement, Lake George; village zoning sign-off firstCounty Building Codes
Lake Luzerne (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Stony Creek (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Thurman (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes
Warrensburg (town)County Fire Prevention & Building Code Enforcement, Lake George; town zoning sign-off firstCounty Building Codes

Not sure this scope needs a permit?

Get a free quote →

The office is open Monday to Friday from 8 a.m. to 4 p.m., and anyone coming in for a permit should arrive by 3:30 p.m. Inspectors are at their desks between 8 and 10 a.m., which is the best window to reach one by phone at (518) 761-6542. The Village of Lake George sits inside the town of the same name; the county permits in both, and the zoning sign-off comes from whichever of the two governs the parcel.

What Warren County itself does beyond building permits

  • Fire safety: the same office carries out fire safety inspections, inspects buildings after a fire or explosion, answers fire and life safety complaints and issues operating permits.
  • Public Works: a right-of-way permit is among the permits issued by the Department of Public Works at 4028 Main Street, Warrensburg, (518) 761-6556, open 7 a.m. to 4 p.m. on weekdays; it also issues special hauling permits and permits for hauling on posted roads.
  • Planning and Community Development: supports the Warren County Planning Board at its monthly review meetings and gives technical help to town and village planning and zoning boards, from the Lake George office at (518) 761-6410.
  • Septic replacement grants: in qualifying lake watersheds the county can pay up to half of eligible costs, to a maximum of $10,000; any replacement under the program needs Planning Department approval, an engineer’s design and all local permits.

Warren County permit types and applications

Residential permits

The county walks applicants through three paths online: a homeowner doing all the building personally, a homeowner hiring a contractor, and a contractor applying. Every path ends at the same paper application, which asks for the owner, the site and tax map number, the occupancy class, the estimated cost and the architect, engineer and contractor. Plans are drawn in some detail: elevations with grade heights, floor plans that label each room and every smoke and carbon monoxide alarm, a window and door schedule showing egress openings, header spans, insulation values, stair and guard dimensions, and cross sections from the footings to the roof. Truss specifications are due before the framing inspection, and the forms page carries a separate certificate for unstamped lumber.

Commercial permits

The online walk-through is written for houses. For a commercial addition, alteration, new building or change of occupancy, the county asks applicants to call (518) 761-6542 first, since those plans need the seal of a New York architect or engineer and often a town site plan approval before the county can review them.

Rather talk it over?

Call 1-855-478-4290 →

What comes before the building permit

  • Town or village zoning: the zoning compliance certificate and the zoning officer’s signature on both plan sets; variances and site plans go to the local zoning and planning boards.
  • Stamped plans: required unless the house is 1,500 square feet or less in gross floor area, or the alteration costs $20,000 or less and does not affect structural stability or public safety; the county may still ask for a stamp.
  • Site plan sheets: two plot plans showing distances to lot lines and other buildings, the well and septic system, and the driveway’s length and width.
  • County road access: a right-of-way permit from Public Works for work on a county road.
  • Insurance: workers’ compensation and disability coverage, or the state exemption form, before the permit issues.

Building permit fees in Warren County

The county charges by floor area under a fee schedule effective January 2026. These rates apply wherever the county is the permitting office; Queensbury and Glens Falls set their own fees, explained in their guides.

Warren County Building Codes fee schedule, effective January 2026
ItemCounty fee (effective January 2026)
New one- or two-family home, townhouse or modular home$0.35 per sq ft, minimum $150
Residential addition or alteration$0.35 per sq ft, minimum $75
Certificate of occupancy, one- or two-family$25 per unit
Residential garage, pole barn or storage shed$0.35 per sq ft, minimum $100
Manufactured home$100
Residential amendment to a permit$0.35 per sq ft, minimum $50
Commercial new construction$0.45 per sq ft, minimum $300; certificate of occupancy $50
Commercial alteration or addition$0.45 per sq ft, minimum $150
Commercial amendment to a permit$0.45 per sq ft, minimum $100
Demolition$100 residential, $200 commercial
Swimming pool$100
Solar$100 residential, $200 commercial
Wood stove, fireplace or pellet stove$50 per device, inspection included
Septic permit$75
Fire safety inspection$75 per tenant and/or classification (use); one $75 fee for several food services in one building with one owner or tenant
Temporary certificate of occupancy$25 each time
Renewal for another yearHalf the original fee
Certificate of occupancy or violation search$25
Work started without a permitThe permit fee or $100, whichever is greater

Rather not deal with the Warren County building department?

Get a free quote →

Worked example: a new 2,000-square-foot house costs 2,000 × $0.35, or $700, which is above the $150 minimum, and the schedule adds the $25 certificate of occupancy for the unit, for $725 in county fees. A 576-square-foot detached garage is $201.60 at the same rate. Fees are figured on area, so an addition’s square footage drives the cost rather than its price tag. Starting without a permit costs at least $100 extra.

Trade permits and who may pull them

The county’s building pages and application name no county license for electricians, plumbers or home improvement contractors, and the application lets a homeowner apply for work on their own property. Heating appliances have their own path: each wood stove, fireplace or pellet stove needs a solid fuel permit, and the plans must label every heating appliance. The county’s plan list also asks for plumbing fixtures to be labeled on the floor plans and the type of heat to be shown; Queensbury runs its own rules for electrical inspection agencies, set out in its guide. Proof of workers’ compensation and disability coverage, or an exemption, is part of every county file.

How to get a building permit in Warren County

1. Confirm the municipality

Parcels in Queensbury or Glens Falls go to those offices; everywhere else the county is the building department.

2. Get the zoning sign-off

Take both plan sets to the town or village zoning officer for signature and the zoning compliance certificate.

3. Complete the drawings

Follow the county’s plan list, add energy code compliance and, above the limits, a design professional’s seal.

4. Gather forms

Insurance or exemption forms, an agent authorization if someone else applies, and the unstamped lumber form where it applies.

5. File in person

Bring the package to Lake George by 3:30 p.m.; call first with questions.

6. Build and book inspections

Call for each required inspection and obtain the certificate of occupancy or completion before use.

Want this handled start to finish?

Get a free quote →

Review, corrections and what causes delay

Plans are reviewed in the order received, and the county allows at least two weeks before a permit can issue. The application warns that any change before or during construction needs amended plans and a fresh review. Files most often stall on a missing zoning signature, plans without the required detail, a missing seal on a larger house or a missing insurance form.

Inspections and certificates

The applicant signs a promise to call for every required inspection and to allow access to the site, and the office’s inspectors can be reached at their desks from 8 to 10 a.m. Truss specification sheets must be in the file before the framing inspection. The job closes with a certificate of occupancy, completion or compliance, and a building may not be occupied until it is issued; a temporary certificate costs $25 each time it is granted. A permit can be renewed for an additional year at half the original fee.

New York building code

New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York

In Warren County that code is applied by the county office in eleven municipalities and by the Queensbury and Glens Falls code offices in the other two.

Warren County permit FAQ

Does Warren County issue building permits?

Yes, in Bolton, Chester, Hague, Horicon, Johnsburg, Lake George (town and village), Lake Luzerne, Stony Creek, Thurman and Warrensburg. It does not in the Town of Queensbury or the City of Glens Falls.

Where do I apply?

In person at the Fire Prevention and Building Code Enforcement office, Human Services Building, third floor, 1340 State Route 9, Lake George, before 3:30 p.m. on a weekday.

How much is a building permit for a new house?

$0.35 per square foot with a $150 minimum, plus $25 for the certificate of occupancy; a 2,000-square-foot house comes to $725.

Do I need a permit for a shed?

The county fee schedule lists residential garages, pole barns and storage sheds at $0.35 per square foot with a $100 minimum, and the shed must also meet the town’s zoning setbacks.

Why does the county want my town’s signature?

Zoning is local. The county requires a signed town or village zoning compliance certificate and plans initialed by the zoning officer before it reviews the building permit.

How long does review take?

At least two weeks, with plans reviewed in the order received.

Do I need a county permit for a driveway?

Work in a county road right-of-way needs a right-of-way permit from the Department of Public Works in Warrensburg; town and state roads have their own permits.

Inspections are where schedules slip.

Get a free quote →

Is my community in the flood insurance program?

Yes. All thirteen Warren County municipalities are in FEMA’s participating section of the Community Status Book.

Warren County permit search and official resources

The county posts an online permit inquiry, search and export tool for its own building permits, and its fee schedule includes a $25 certificate of occupancy or violation search for a property. Records for Queensbury and Glens Falls are kept by those offices, and the Glens Falls guide explains the city’s request form.

Simplify Warren County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Warren County sooner?

Let Alliance prepare, file, and track your Warren County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Warren County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.