Schuyler County, New York Building Permit Guide

To get a building permit in Schuyler County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Each of Schuyler County’s eight towns and four villages has its own code enforcement officer who issues building permits; the county’s Watershed Protection Agency must clear a new septic system before a town permit can issue.

Authority: Town and village code enforcement officers (12 municipalities)Code: 2025 NYS Uniform Code and Energy Code
Building permits
Local code officers8 towns and 4 villages, part-time hours
Septic and wells
Watershed Protection Agency910 S. Decatur St; 607-535-8140
New-build septic
$950 typicalSite evaluation, permit, well site, engineer review
County roads
Highway DepartmentWork and driveway permits; 607-535-2531

Schuyler County has no county building department. Building permits come from the code enforcement officer of each town (Catharine, Cayuta, Dix, Hector, Montour, Orange, Reading and Tyrone) and each village (Burdett, Montour Falls, Odessa and Watkins Glen). The county’s part is the ground under the house: Public Health’s Watershed Protection Agency evaluates the site, approves the septic design and the well location, and sends its preliminary approval to the town officer so a building permit can issue, while the Highway Department permits driveways and any work in a county road right-of-way.

What requires a building permit in Schuyler County?

Every municipality enforces the state code through its own officer, so the basic list is broad everywhere. The Town of Orange spells it out for residential, farm, commercial and institutional property alike: moving a mobile home onto a lot, new houses, garages, decks and outbuildings, additions and alterations, every extension of electrical or plumbing systems, structural work, and every chimney or solid-fuel appliance. Watkins Glen, the largest village, takes building applications online through Cloudpermit.

Town or village permit

  • New houses, garages, decks and outbuildings
  • Additions, alterations and structural repairs
  • Extensions of wiring and plumbing
  • Chimneys, wood stoves and other solid-fuel appliances
  • Placing a mobile home on a lot
  • New or altered driveways in Odessa, on the village’s approval sheet

County approvals

  • Site evaluation, septic design and construction permit: Watershed Protection Agency
  • New well location: Watershed Protection Agency
  • Septic inspection when a property is sold or refinanced, where required
  • Work in a county road right-of-way and new driveways: Highway Department

What the towns and villages decide and what the state holds

The construction rules are the state’s 2025 Uniform Code and Energy Code everywhere. Land use is where Schuyler’s municipalities differ most. According to the county Planning Department’s town pages, Cayuta, Hector, Orange, Reading and Tyrone and the Village of Burdett have no zoning ordinance; Reading regulates through a 2023 Land Use Law instead, Tyrone has site plan and subdivision laws, and Hector has a 2021 solar law. Dix, Catharine, Montour, Montour Falls, Odessa and Watkins Glen are zoned. Schuyler County is not among the twelve counties the Department of State lists as having opted out of the enforcement of the Uniform and Energy codes; today each of its twelve towns and villages has its own officer.

Schuyler County building department: who handles permitting

All twelve municipalities appear below with the officer’s office number and hours from the county’s Town & Village Planning directory. Three villages straddle town lines: Watkins Glen lies in Dix and Reading, Montour Falls in Montour and Dix, and Odessa in Catharine and Montour. In each case the village officer, not either town, permits the land inside the village.

Short on time to read all of this?

Get a free quote →
Building permit offices in Schuyler County (12 municipalities)
PlaceWho issues building permitsOfficial page
Catharine (town, outside its part of Odessa)Town code enforcement officer, 607-594-2273, Thursdays 9 a.m. to 2 p.m.Town of Catharine planning page
Cayuta (town)Town code enforcement officer, shared with Tyrone; 607-594-2507, hours varyTown of Cayuta planning page
Dix (town, outside Watkins Glen and Montour Falls)Town code enforcement officer, 607-535-7973 ext. 205, Wednesdays 6 to 8 p.m.Town of Dix planning page
Hector (town, outside Burdett)Town code enforcement officer, 607-546-5286 ext. 227, weekdays 8 a.m. to 4 p.m.Town of Hector planning page
Montour (town, outside Montour Falls and Odessa)Town building inspector, 607-535-9476, Wednesdays 3 to 6 p.m.Town of Montour planning page
Orange (town)Town code enforcement officer, 607-542-6537; Town Hall, 899 Hornby Road, Beaver DamsTown of Orange Code Enforcement
Reading (town, outside its part of Watkins Glen)Town code enforcement officer, 607-535-7459 ext. 102Town of Reading planning page
Tyrone (town)Town code enforcement officer, 607-292-3168, Mondays and Thursdays 9 a.m. to 1 p.m.Town of Tyrone planning page
Burdett (village, in Hector)Village code enforcement officer, 607-546-2266, 5 to 7 p.m.Village of Burdett planning page
Montour Falls (village, in Montour and Dix)Village code enforcement officer (part time), 607-738-4323Village of Montour Falls planning page
Odessa (village, in Catharine and Montour)Village code enforcement officer, 607-481-8663, Tuesday morningsVillage of Odessa Code Enforcement
Watkins Glen (village, in Dix and Reading)Village code enforcement, 303 N. Franklin Street, 607-535-2736 (option 7); online filing through CloudpermitVillage building permit page

Not sure this scope needs a permit?

Get a free quote →

Several officers serve more than one place. The county directory lists the same officer for Tyrone, Cayuta and the Village of Odessa, another for Catharine and Montour, and another for Orange and Watkins Glen. Cayuta has no website of its own, so its contact runs through the Tyrone code office. Call ahead before driving to a town hall.

What Schuyler County itself does

  • Public Health, Watershed Protection Agency (910 South Decatur Street, Watkins Glen; 607-535-8140; weekdays 8 a.m. to 4 p.m.): site evaluations, septic system construction permits, well site approvals, septic evaluations at property transfer, water testing and the Lamoka-Waneta and Cayuta Lake inspection programs.
  • Highway Department (910 South Decatur Street; 607-535-2531; weekdays 7 a.m. to 3:30 p.m.): permits for any construction or maintenance in a county road right-of-way, a separate driveway installation and replacement permit, and hauling permits for oversize loads.
  • Planning Department and Planning Commission (105 Ninth Street, Unit 39, Watkins Glen; 607-535-8211): the commission receives General Municipal Law 239-m referrals of site plans, zoning changes, special use permits and subdivisions, and meets on the second Thursday of the month in Montour Falls when referrals have arrived.
  • Emergency Management: issues 911 addresses, which Orange requires before a building application.

Schuyler County permit types and applications

Residential permits

Most towns take paper applications through their code officer during set hours; Watkins Glen asks applicants to register on Cloudpermit and file online. Odessa posts a building permit cover letter with its fee schedule, a driveway approval sheet and a solid-fuel appliance permit. In Orange the first step is a 911 address from county Emergency Management, and the landowner buys the driveway sluice pipe.

Commercial permits

Commercial projects add a design professional’s plans and, in zoned places, site plan review. A building that will use more than 1,000 gallons of water a day, or a restaurant or other facility regulated by the state Health Department, falls outside the county’s standard septic routine: the owner’s own design professional submits plans to the Watershed Protection Agency and, as the project requires, to the state Departments of Environmental Conservation and Health.

Rather talk it over?

Call 1-855-478-4290 →

What comes before the building permit

  • Septic preliminary approval: the Watershed Protection Agency’s site evaluation (backhoe on site, perc test if needed) leads to a preliminary approval sent to the town officer, which is what lets the building permit issue.
  • Tear-downs and conversions: replacing a house with one of the same or fewer bedrooms, or converting a building to another use, needs a Watershed Protection Agency review of the existing septic system first, with a site visit and an inspection during a mandatory tank pumping; the agency then issues a Compliance Certificate to the town before the building permit. Adding bedrooms means the system must meet the full state design standards.
  • Zoning boards: in zoned places, the planning board and ZBA (Dix’s planning board meets on the fourth Tuesday; Hector is still forming one).
  • County referral: site plans, special permits and subdivisions near county interests go to the county Planning Commission first; referrals are due around the first of the month.
  • Road access: the county Highway Department inspects the site before a new driveway goes in.
  • Flood zones: every Schuyler municipality participates in the National Flood Insurance Program, so local flood rules apply on mapped flood land.

Building permit and septic fees in Schuyler County

Each town and village sets its own building fee. Few post the figures online, so ask the code officer; the published amounts are below, with the county’s septic fees for a new house on a private system.

Published permit fees in Schuyler County
ItemFeeSource
Village of Odessa building permit$20 minimum for a project under $2,000; $20 plus $3 per $1,000 for a project over $2,000Village rule effective June 1, 2018
Town of Orange, work started before a permitAn extra $50 on top of the permit feeTown Code Enforcement notice
County site evaluation, new construction$300Watershed Protection Agency fee schedule
County septic system permit, new construction$350Watershed Protection Agency fee schedule
County well site approval, new construction$100Watershed Protection Agency fee schedule
County engineer review and approval$200Watershed Protection Agency fee schedule
Septic evaluation for a property sale or refinancing$250Watershed Protection Agency fee schedule

Rather not deal with the Schuyler County building department?

Get a free quote →

For a new house with septic and a well, the county’s four new-construction charges come to $950 before any building permit fee. All county fees are paid in full before the agency does any work, by check to the Schuyler County Treasurer or in cash.

Trade permits and who may pull them

Schuyler County lists no contractor or trade licensing office among its departments, and none of the town and village pages lists a local electrician or plumber license. In Orange, extending wiring or plumbing needs a building permit like any other covered work. Every officer still needs proof of workers’ compensation and disability insurance, or the state exemption form for an owner doing the work, before a permit issues. Septic installers follow the agency’s Instructions for Contractors while a system is built.

How to get a building permit in Schuyler County

1. Identify the municipality

Check the tax bill: a Watkins Glen, Montour Falls or Odessa address may be in the village or in a surrounding town.

2. Get a 911 address

For a new building, county Emergency Management assigns the address the town will use.

3. Book the septic site evaluation

Call the Watershed Protection Agency, pay its fees, call UDig NY (811) and have a backhoe on site.

4. Arrange road access

Ask the Highway Department for a driveway permit if the lot fronts a county road.

5. File with the code officer

Submit the town or village application, plans and insurance proof during the officer’s hours, or on Cloudpermit in Watkins Glen.

6. Build, inspect, close

Install the septic system under its one-year construction permit and book each building inspection with the officer.

Review, corrections and what causes delay

Part-time offices are the main constraint: Dix’s officer keeps two evening hours a week, Montour’s three on Wednesday afternoons and Odessa’s Tuesday mornings. A building permit for a new house also waits on the septic preliminary approval, and that waits on a site evaluation with an excavator on site. Missing 911 addresses and unpaid county fees hold files up as well.

Want this handled start to finish?

Get a free quote →

Inspections and certificates

Building inspections are booked with the town or village officer who issued the permit. The septic system is inspected by the Watershed Protection Agency under its construction permit, which lasts one year, and a new well follows the agency’s water supply procedure. Septic contractors give the agency at least 24 hours’ notice before starting, and every component is inspected before it is backfilled; afterwards the agency issues a certificate and, for a replacement system, forwards it to the town code officer. Any repair beyond routine pumping or filter cleaning, such as a new tank, distribution box or extra absorption lines, needs its own agency permit, and the agency says it can often issue a replacement design within two to three days. Once the final building inspection passes, the officer issues the certificate of occupancy or compliance. When a property later changes hands, the agency’s transfer inspection, where it applies, is a separate step.

New York building code

New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York

Schuyler County permit FAQ

Does Schuyler County issue building permits?

No. Each of the eight towns and four villages has its own code enforcement officer. The county handles septic systems and wells through its Watershed Protection Agency and permits work on county roads.

Who issues permits in Watkins Glen?

The Village of Watkins Glen, through its code enforcement office at 303 N. Franklin Street and online on Cloudpermit. The towns of Dix and Reading cover only their land outside the village.

How much does septic approval cost for a new house?

The Watershed Protection Agency charges $300 for the site evaluation, $350 for the septic permit, $100 for the well site approval and $200 for engineer review, $950 in all, paid before the work.

Can the town issue my building permit before the septic system is approved?

Only after the Watershed Protection Agency has sent its preliminary approval to the town code officer; the final septic construction permit follows the engineer’s design.

Do I need a permit for a wood stove?

Yes. Orange lists all chimneys and solid-fuel appliances, and Odessa has a separate solid-fuel appliance permit.

Does my town have zoning?

Not all do. The county lists no zoning ordinance for Cayuta, Hector, Orange, Reading, Tyrone or the Village of Burdett, though other local laws (land use, solar, site plan) still apply.

Where are old permit records kept?

With the town or village that issued the permit; ask its clerk under the Freedom of Information Law. Septic records sit with the Watershed Protection Agency, whose policy includes a section on access to records.

Inspections are where schedules slip.

Get a free quote →

Schuyler County permit search and official resources

There is no countywide permit search. Building files stay with each municipality; septic, well and property-transfer records stay with the Watershed Protection Agency.

Simplify Schuyler County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Schuyler County sooner?

Let Alliance prepare, file, and track your Schuyler County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Schuyler County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.