City of Batavia, New York Building Permit Guide

To get a building permit in City of Batavia, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The City of Batavia’s Bureau of Inspection at One Batavia City Centre issues building, plumbing and driveway permits inside the city, and applications go in through the city’s iWorQ citizen portal.

Authority: City of Batavia Bureau of InspectionCode: 2025 New York Uniform & Energy CodesPhone: 585-345-6345
Authority
Bureau of InspectionOne Batavia City Centre
Apply
iWorQ citizen portalBuilding, plumbing and driveway permits
Fee basis
1.2% of project value$35 minimum; schedule effective April 1, 2026
Plumbing
City-licensed plumbersOwner-occupant homeowner permit allowed

Inside the City of Batavia, the Bureau of Inspection handles building permits, zoning and property maintenance from One Batavia City Centre, and you file through the city’s iWorQ portal. Most work not on the flat-rate list costs 1.2% of the project value with a $35 minimum under the schedule effective April 1, 2026, and plumbing permits go only to plumbers licensed by the city or to an owner working on the home they live in.

What requires a building permit in the City of Batavia?

Chapter 51 of the City Code requires a permit for any work that must meet the Uniform Code or the Energy Code: building, enlarging, altering, moving or demolishing a structure, and putting in a wood stove, chimney or flue in a home. The flat-rate list in the city’s fee schedule shows how far that reaches in practice.

Permit needed

  • New buildings, additions, renovations and decks
  • Roofing, siding, replacement windows and exterior doors on a house
  • Fences, sheds and similar storage buildings
  • Pools, except above-ground pools built for water under 24 inches deep
  • Central air, heating-system replacement, generators, fireplaces and stoves
  • Fuel tank installation and removal; driveways and parking spaces
  • Plumbing beyond the minor repairs listed in section 51-28 H
  • Demolition, including a private garage

No building permit

  • Swings and playground equipment at a home
  • Retaining walls that support no surcharge and impound no Class I, II or IIIA liquids
  • Awnings on the wall of a one- or two-family house
  • Painting, wallpaper, tile, carpet and similar finish work
  • Like-for-like equipment replacement and repairs that do not touch structure, exits or building systems
  • Faucet, trap, toilet-tank part, disposal, dishwasher and sink swaps under section 51-28 H

The exemption list is narrower than many homeowners expect: roof, window and door replacements are all on the city’s fee list even though they change nothing structural.

What the city decides and what the state holds

The building standards are the state’s Uniform Code and Energy Code, and Batavia cannot tighten them without Code Council approval. The City Council sets the fees by resolution (section 51-18), adopts the zoning chapter with its fence, pool and historic-district rules, and runs its own plumber licensing through an Examining Board of Plumbers, which is a city rule rather than a state one.

City of Batavia building department: who handles permitting

The Bureau of Inspection is the single office for building permits, construction inspections, zoning administration and property maintenance in the city. Its staff are a planning clerk, a planning coordinator who also enforces ordinances, and code enforcement officers. The surrounding Town of Batavia is a separate municipality with its own office; city parcels never go there, and town parcels never come here. Street openings and curb cuts belong to the city’s Bureau of Maintenance.

Short on time to read all of this?

Get a free quote →
City of Batavia permit contacts
DetailInformation
Bureau of InspectionOne Batavia City Centre, Batavia, NY 14020
Phone585-345-6345; fax 585-345-1385
Portal questions585-345-6344 (number printed on the iWorQ portal)
Online filingCity of Batavia iWorQ citizen portal
Population15,168 (Census estimate, July 1, 2025)

City of Batavia permit types and filing

The iWorQ portal carries three applications: a building permit, a driveway permit (upload a copy of your survey) and a plumbing permit. A contractor needs its access code before starting, and any job using roof or floor trusses must upload the city’s truss notice form, which carries a $50 fee. Section 51-6 asks for a description of the work, the tax map number, the occupancy class and at least two sets of construction documents, sealed by a New York architect or engineer where the Education Law requires it, with a site plan where one applies.

Residential permits

For a house, the fee depends on who does the work. If a contractor is building it, the bureau takes the value from a fully signed contract that names both parties, the address, start and finish dates, the work and materials, and the price. If the owner is doing the work, the city prices it with set figures: $80 per sq ft for a new home, $30 for renovations and $25 for garages, porches and decks. Every applicant files proof of workers’ compensation coverage or, if exempt, a new CE-200 for each permit.

Commercial permits

Owner-performed commercial work is valued at $55 per sq ft for new construction and $30 for renovations; contractor work again uses the signed contract. New nonresidential buildings and expansions that add parking demand or raise lot coverage by more than 3% or 1,300 sq ft, whichever is less, go to the Planning and Development Committee for site plan review ($250) before the permit. Development also posts an engineering cost-recovery deposit: $2,500 per building in commercial, industrial and planned development districts, and $500 per lot or living unit in residential districts. Certificates of occupancy for commercial buildings cost $75 to $175 by floor area.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

Zoning is checked by the same bureau. A variance or appeal goes to the Zoning Board of Appeals ($50 residential, $100 commercial), and special use permits are reviewed by the Planning and Development Committee ($150). Exterior work visible from a public street in the downtown Historic District Overlay, the area around Main, Court, Evans and Jefferson streets down to Tonawanda Creek, goes to the Historic Preservation Commission, including signs, fences, lighting and paint color changes. Building in a mapped flood zone follows the Flood Damage Prevention chapter (ch. 87). A lot that is not on city sewer goes through GO Health, the Genesee and Orleans County Health Department at 15 Main Street, whose Environmental Health staff work on onsite system design and post the Genesee County Residential Septic Construction Permit Application.

City of Batavia building permit fees

The Bureau of Inspections fee schedule took effect on April 1, 2026. Anything not on its flat-rate list costs 1.2% of the project value, with a $35 minimum. Every fee is tripled if work starts before a required permit is issued.

Selected City of Batavia fees (effective April 1, 2026)
ProjectFee
Work not on the flat list (new homes, additions, renovations, commercial)1.2% of project value, $35 minimum
Reroof, one- or two-family house$65 ($35 for a garage, shed or porch)
Siding, fence, shed or pool$65 each
Replacement windows or exterior doors (residential)$45
Driveway or parking space (residential)$55
Central air, generator, heating replacement, fireplace or stove$65 each
Fuel tank installation$100 under 1,000 gal; $150 to 5,000 gal; $200 above
Tank removal; fuel pump nozzle (each); telecommunication tower or antenna (each)$100; $50; $500
Dumpster (with a demolition permit); parking lot permit (R-2 and R-3 districts)$35; $200
Demolition$100 up to $5,000 of contract value, then $10 per $1,000; private garage $35
Truss construction fee$50
Certificate of occupancy, one- or two-family$50; temporary certificate $50
Plumbing filing fee$80 one- or two-family, $100 other buildings, plus $10 per fixture
Water heater$50 up to 50 gal; $75 larger; $100 commercial
Home occupation permit (one-time)$100
Zoning verification letter$50

Rather talk it over?

Call 1-855-478-4290 →

Worked example: an owner who builds a 300 sq ft deck is valued at $25 per sq ft, or $7,500, and 1.2% of that is a $90 permit. A contractor’s $20,000 signed contract for a kitchen renovation works out to $240. Plumbing is added on its own permit, so a homeowner adding a bathroom with three fixtures pays the $80 filing fee plus $30. Third-party electrical inspections are billed separately by the agency. Work in the street is a separate Bureau of Maintenance permit: a street opening starts at $375 for up to 50 sq ft of pavement, and a curb cut is $200.

Trade permits and who may pull them

Plumbing is licensed by the city. Under section 51-28, plumbing and drainage work inside a property line may be done only by plumbers whom the city’s Examining Board of Plumbers has certified and the city licenses, and plumbing permits go only to them. A new installation needs its permit first; for repairs, the plumber has 48 hours from starting work to take one out. The bureau posts its list of licensed plumbers. A license costs $150 for the exam review and $200 for the first year, then $125 a year if renewed before January 1; after December 31 reinstatement is $300, and a lapse of over a year means applying again.

A homeowner permit is the exception: an owner who lives in a one- or two-family house, or is building one on their own land, may get a plumbing permit and do the work personally inside the walls of the house and its accessory buildings. The homeowner may not make the connection to the city water or sewer system.

Batavia does not license electricians. Instead, electrical work is inspected by an authorized third-party agency at the applicant’s cost, and the code bars connecting new wiring to power until the agency issues a temporary certificate or certificate of compliance. The city’s list names Middle Department Inspection Agency, New York–Atlantic Inland, Empire Inspections, NECI and New York Electrical Inspection Agency. Manufacturers that keep journeyman electricians on staff can apply for a one-year exemption permit under section 51-24.

Rather not deal with the City of Batavia building department?

Get a free quote →

How to apply for a City of Batavia building permit

1. Confirm the parcel is in the city

Use the Genesee County GIS map; Town of Batavia addresses go to the town.

2. Check zoning and overlays

Setbacks, fence heights, the Historic District Overlay and flood zones; ask the bureau whether the job needs a board or committee approval.

3. Assemble the file

Signed contract or square footage, two sets of drawings, survey or site plan, truss notice if trusses are used, and workers’ compensation proof or a CE-200.

4. Apply in iWorQ

Open the building, plumbing or driveway application on the citizen portal and upload the documents.

5. Pay and post the permit

Fees are due with the application; keep the permit visible at the site until the work is done.

6. Book inspections and the electrical agency

Call the bureau at each stage and hire one of the listed electrical agencies for wiring.

Review, corrections and what causes delay

Accepted drawings are stamped; one set stays with the bureau and one goes back to be kept on site. Any change during the work must be reported, and a change that needs an amended permit cannot be built until it is approved. Projects that need Planning and Development Committee, Zoning Board or Historic Preservation Commission action wait for those meetings, and the committee will not take a site plan on a parcel with an open zoning violation. A permit is void if work has not started within six months and expires after 12 months; the code officer may grant at most two renewals of up to three months each.

City of Batavia inspections and certificates

Section 51-7 lists the stages the bureau inspects where they apply: the site before the permit issues, footings and foundation, slab preparation, framing, building systems including underground and rough-in work, fire-resistant construction and penetrations, wood stoves, chimneys and vents, Energy Code compliance, and a final. Work must stay exposed until it passes, and work that fails stays open until it is corrected and inspected again. Inspection fees, where charged, are due before or at the inspection.

Every permitted job ends with a certificate of occupancy or certificate of compliance, and the same applies to any change of use. Before issuing it the bureau needs, where they apply, a statement of structural observations or final special-inspection report and flood hazard certifications, and new wiring may not be energized until the electrical agency issues its certificate. A home certificate costs $50, a temporary or conditional one $50, and a commercial tenancy certificate of compliance $50.

Pools need a permanent fence at least 4 feet high with self-latching gates before use, under the zoning chapter; the bureau’s pool requirements guide covers the rest.

Want this handled start to finish?

Get a free quote →

New York building code

New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York

City of Batavia permit FAQ

How much is a building permit in the City of Batavia?

Work on the flat list costs $35 to $65 for most home projects (reroof $65, windows $45, fence $65). Everything else is 1.2% of the project value with a $35 minimum, so a $20,000 contract costs $240.

Do I need a permit for a fence?

Yes, a $65 fence permit. In residential districts a fence may be 3 feet high within 15 feet of a street line and 6 feet elsewhere; corner lots keep a 40-foot sight triangle clear above 3 feet.

Can I do my own plumbing?

Only in a one- or two-family house you own and live in (or are building on your own land), under a homeowner permit, doing the work yourself. The homeowner permit does not allow connections to the city water or sewer system, and small repairs such as faucets and traps need no permit at all.

Who inspects electrical work?

One of the city’s authorized third-party agencies, hired and paid by the applicant. The power cannot be connected until that agency issues its certificate.

Do I need a permit to replace my roof or windows?

Yes. A house reroof is $65 and replacement windows or exterior doors $45 under the April 1, 2026 schedule.

What if I started without a permit?

The fee is tripled, and the bureau can issue a stop-work order until a permit is in place.

Is Batavia in the flood insurance program?

Yes. FEMA lists the City of Batavia as a participating community with a Community Rating System class 7, a 15% premium discount, and a new flood map effective February 19, 2027.

City of Batavia permit search and official resources

The iWorQ portal has a public search: enter a permit number to see its status, or open the map and search by parcel or permit number. For older files and plans, ask the Bureau of Inspection or make a Freedom of Information Law request; copies cost 25 cents a page under the clerk-treasurer’s schedule.

Inspections are where schedules slip.

Get a free quote →

Simplify City of Batavia permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in City of Batavia sooner?

Let Alliance prepare, file, and track your City of Batavia permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about City of Batavia permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.