Artesia runs its own building department. Building Inspection, a division of the City’s Planning Department, reviews plans and issues building, electrical, plumbing and mechanical permits for work inside city limits. Applications go in on paper at 15 E Compress Road, the building fee follows project valuation ($400 for a $100,000 job), and the City says plan review takes from 2 days to several weeks.
What needs a permit in Artesia?
The City publishes a “Do I Need a Permit?” chart with one column for the building permit and one for Fire Department review. These are the building-column answers, followed by the exemptions listed in the City’s Residential Building Permit Guide.
Building permit: yes
- New houses, house additions and new commercial buildings
- New garages and garage remodels; attic alterations
- Decks, fences, retaining walls and siding
- Roofs: new, tear-off or shingle replacement
- Doors (new or replacement), fireplaces and furnaces
- Plumbing or mechanical work; sewer taps
- Swimming pools and signs
- Metal shops larger than 120 sq ft
- Mobile home placement and demolition
- Sidewalks, driveway approaches and cuts to a curb, gutter, street or alley
No building permit
- Insulation
- Landscaping
- Spas
- Painting, papering, floor coverings, cabinets and counter tops
- Detached one-story sheds and playhouses up to 120 sq ft (a plan review permit is still required)
- Prefabricated pools less than 24 inches deep
- Swings and playground equipment at a 1- or 2-family home
The chart answers “probably” for a bathroom remodel and “in most cases” for electrical work, so ask the permit technician before starting either. Day care, demolition and new commercial buildings also need Fire Department review, and so do decks, fences, garages and trade work on anything other than a 1- or 2-family home.
Roofing has its own notice: every roofing project over 100 sq ft needs a permit and inspections, including overlays, and a pre-roof inspection is required on all re-roofs. Exempt items can still need a separate electrical, plumbing or mechanical permit.
Who issues permits in Artesia?
Building Inspection sits inside the Community Development Department and issues the building permit and the trade permits for property inside Artesia. The City’s permit page names Don Plotner as Chief Building Official. Permits go only to state-licensed contractors or to the homeowner.
Short on time to read all of this?
Get a free quote →The city code applies its building rules to buildings and structures in the City of Artesia, and the City’s pages do not say whether Building Inspection permits anything beyond the limits. Its own paperwork does reach county-side sites: the standard-plan submittal sheet asks for a Flood Zone and Address verification form from Eddy County “if in County”, and both permit guides say zoning approval may be needed from the City of Artesia or from Eddy County. Eddy County states that it issues no building permits and that the service comes from the City of Artesia, the City of Carlsbad or the state Construction Industries Division (CID), without saying which office covers which area. For a site outside the limits, Eddy County Planning & Development (575-887-9511) supplies the address and floodplain certificate, and the City permit office (575-748-8298) can say whether the building permit is the City’s or the State’s.
| Detail | Information |
|---|---|
| Office | City of Artesia Community Development: Building Inspection, Planning & Zoning |
| Address | 15 E Compress Road, Artesia, NM 88210 |
| Permit technician | 575-748-8298 |
| Chief Building Official | Don Plotner, 575-748-8295 |
| buildingpermits@artesianm.gov | |
| Hours | Monday to Friday, 7:30 a.m. to 4:30 p.m. |
| Fire Marshal | 575-746-5051 |
Artesia permit applications and forms
Artesia uses one universal Application for Permit for building and trade work. The City’s FAQ says an original signature is required, so the form can be downloaded and printed but has to be handed in or mailed with the plans. Electronic submittal is allowed for some projects; the City asks you to call first to find out whether yours qualifies. Issued permits can be looked up in the City’s iWorQ permit search.
Documents the City posts next to the application:
- Residential and Commercial Permit Application Procedures, one page each on what to hand in and how review works.
- Plan requirement sheets for residential additions and new homes, residential remodels, standard-plan homes, and residential and commercial modular buildings.
- Homeowners’ Responsibilities form, which an owner-applicant signs before a notary and submits with the application.
- Manufactured Units Placement Procedure and the Manufactured Home Placement Permit.
- Residential Foundation Policy, a masonry fence foundation detail and two window flashing details.
- Roofs/Re-roof Information for contractors and homeowners.
A homeowner’s permit cannot be used on a job where a licensed contractor is acting as general contractor, and an owner may not do the electrical, plumbing or mechanical work without passing the state CID exam for that trade.
Building permit fees in Artesia
The municipal code (section 8-1-6) leaves permit and inspection fees to a schedule set by City Council resolution. The City’s posted Building Permit Fees sheet prices each permit by project valuation, and the fee is the same for a contractor or a homeowner. A signed copy of the owner–contractor contract goes in with the application to support the valuation.
Not sure this scope needs a permit?
Get a free quote →| Project valuation | Fee |
|---|---|
| $1,000 | $50 |
| $5,000 | $58 |
| $10,000 | $76 |
| $25,000 | $130 |
| $50,000 | $220 |
| $75,000 | $310 |
| $100,000 | $400 |
| Over $100,000 | $400 plus $1 for each $1,000 above $100,000 |
The sheet lists every $1,000 step between those rows. As an example, a $250,000 house is $400 plus $150, or $550. Trade permits are priced separately (see below).
The department tells you the fee when plan review is finished. It must be paid before the permit is issued, and the permit has to be picked up and posted before work starts. Work must begin within 180 days or the permit expires and a new permit and fee are needed. Under the city code, work started without a valid permit can be charged double the usual permit fee.
Electrical, plumbing and mechanical permits
Artesia issues its own trade permits; they are not filed with the state. Electrical permits are priced by service size, and plumbing, mechanical and gas permits by item on top of a $40 administration fee each for plumbing, mechanical and gas piping.
| Permit | Fee |
|---|---|
| Electrical, residential, 100 A and below | $45 |
| Electrical, residential, 101–200 A | $72 |
| Electrical, residential, 201–320 A | $99 |
| Electrical, residential, 321–400 A | $225 |
| Electrical, commercial, 201–400 A | $225 |
| Electrical, commercial, 401–600 A | $270 |
| Temporary service pole, mobile home service or service change only | $45 |
| Plumbing, mechanical or gas piping administration fee | $40 each |
| Water heater, water service line or waste discharge device | $4 each |
| Building sewer | $10 |
| Building sewer tap | $100 |
| HVAC split or combination unit | $4 |
| Duct work system | $10 |
| Swimming pool (plumbing) | $50 |
| Re-inspection, any trade | $45 |
Rather talk it over?
Call 1-855-478-4290 →Larger services cost more: a residential service over 400 A is $360, and commercial services run from $360 (601–800 A) to $900 (over 2,000 A).
What to submit and how long review takes
Residential
- Completed application, signed by the contractor’s qualifying party or the homeowner
- 2 bound sets of plans at 1/4 inch = 1 foot, on sheets no smaller than 11 x 17 inches, with 2 plot plans
- Site plan with property lines, setbacks, easements, utilities and drainage
- Foundation plan, floor plan with door and window schedules, floor and roof framing plans
- Sealed truss specifications and wall section details
- Square footage for heated area, garage, carport, porch and patio
- Energy code compliance package
- Signed owner–contractor contract
Commercial
- Completed application signed by a GB98 licensed contractor
- 3 sets of plans and 3 plot plans; a single-file digital copy is recommended
- Cover sheet with code analysis: construction type, occupancy, occupant load, exits, fixtures, sprinklers
- Site plan with parking, accessible routes, utilities, grading and drainage
- Foundation plan with a geotechnical report
- Floor, framing and roof plans, elevations and fire assembly details
- An asbestos survey report may be required at submittal for commercial roofing work
Zoning approval comes before the building application. For a remodel or repair with no structural change, the City accepts 2 written lists of the work and materials in place of drawings, and for a demolition, 2 site plans showing the structure to be removed.
The City’s procedure sheets say plan reviews are done on Tuesdays and Thursdays and that a permit takes from 2 days to several weeks depending on the project. Corrections are marked on the returned set; simple ones can be made in red ink on every set with the plans examiner’s agreement, otherwise complete redrawn sets are needed. Of the 3 commercial plan sets, one comes back with the permit and the others stay with the City Fire Marshal and the Planning Department.
Rather not deal with the building department?
Get a free quote →How to get an Artesia building permit
Look the job up on the Do I Need a Permit chart and get any zoning approval from Planning & Zoning first.
Fill in the universal application; owner-applicants add the notarised Homeowners’ Responsibilities form.
Bring or mail 2 plan sets and 2 plot plans for a house, or 3 of each for commercial work, with the signed contract.
Reviews run on Tuesdays and Thursdays. Answer correction requests promptly; review stops until they are resolved.
Staff phone or email the fee. Pay it, collect the permit card and one approved plan set, and post the permit on site.
Licensed electrical, plumbing and mechanical contractors take out their own City permits and arrange their own inspections.
Request each inspection by noon the business day before; the Certificate of Occupancy follows the final.
Inspections in Artesia
Call 575-748-8298 or email buildingpermits@artesianm.gov by 12:00 p.m. one business day before you need the inspector; slots depend on availability. Keep every permit posted in plain view and a copy of the approved plans on site.
For a new house the City’s guide lists a foundation inspection (footings excavated, steel and the Ufer ground in place), a slab or under-floor inspection, a frame inspection after the rough trade inspections are approved, a weather-resistive barrier inspection and a final. The inspection guideline sheet adds setbacks, sheathing and nailing, insulation, drywall nailing and shower pans to the list. Final electrical, plumbing and mechanical inspections must be passed before the building final, and the inspector then issues the Certificate of Occupancy to the contractor.
The City also requires a leak test of all plumbing piping before the slab is poured and again at the top-out inspection. On re-roofs, book the pre-roof, any sheathing and the final inspection at least 1 business day ahead.
Artesia details worth knowing
Expansive soils: the City’s Residential Foundation Policy says Artesia is known for expansive clay. Unless you submit a geotechnical report and an engineered foundation, the City requires native soil removed to 24 inches and compacted to 95%, a monolithic slab with a rebar mat (#3 at 18 inches or #4 at 24 inches each way) and perimeter footings 18 inches wide and 24 inches deep.
Want this handled start to finish?
Get a free quote →Site drainage: the standard-plan checklist calls for 6 inches of fall in the first 10 feet away from the house and a slab 12 inches above the crown of the street or the top of the gutter, whichever is higher.
Manufactured homes: apply to the City for a Manufactured Home Placement Permit with a site plan and zoning approval, get the installation permit from the state Manufactured Housing Division, then take City electrical and plumbing permits for the service connections. The State, not the City, issues the Certificate of Occupancy.
Flood zones: list the flood zone on the plot plan. A manufactured unit in an AO zone (1 ft or 2 ft depth) also needs a Flood Plain Use permit.
Subdivisions near town: Artesia has a 1-mile extended platting jurisdiction, so a subdivision there needs approval from the City’s Planning and Zoning Commission even though the land is in Eddy County.
Septic systems: a permit to install or modify an individual liquid waste system comes from the New Mexico Environment Department, not the City. Eddy County sends septic applicants to the Department on 575-885-9023, the number of its Carlsbad field office at 406 N Guadalupe, Suite C.
Dig safely: the City’s inspection sheet reminds builders to call 811 two days before digging.
New Mexico building code
New Mexico adopts its building codes statewide; a city or county with its own certified building official issues its own permits, and elsewhere the state Construction Industries Division does. New Mexico rules
Official Artesia permitting resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Artesia Building Inspection
- Artesia building code information, checklists and forms
- Artesia “Do I Need a Permit?” chart
- Artesia permit fee sheets (building, electrical, plumbing and mechanical)
- Artesia Community Development FAQs
- Artesia Planning & Zoning
- Artesia Municipal Code, Title 8 Chapter 1: building codes and fees
- Eddy County Planning & Development (address and floodplain forms outside the city)
- New Mexico Environment Department liquid waste field offices
- New Mexico Construction Industries Division
Inspections are where schedules slip.
Get a free quote →Artesia building permit FAQs
Does Artesia issue its own building permits?
Yes. The City’s Building Inspection division issues building, electrical, plumbing and mechanical permits inside city limits. For a site outside the limits, Eddy County issues none and says the service comes from the City of Artesia, the City of Carlsbad or the state Construction Industries Division; the published pages do not say where the City’s permit area ends.
How much is a building permit in Artesia?
It depends on valuation: $50 at $1,000, $76 at $10,000, $220 at $50,000 and $400 at $100,000, then $1 more for each additional $1,000. A $250,000 project is $550, before trade permits.
Do I need a permit for a roof, fence or shed in Artesia?
Roofs and fences are both “yes” on the City’s chart, and any roofing job over 100 sq ft needs a permit and inspections. A detached shed up to 120 sq ft does not need a building permit but still needs a plan review permit.
Can I apply online?
Not as a rule. The City requires an original signature on the application, and electronic submittal is allowed only for some projects, by arrangement with the office.
Can a homeowner pull a permit in Artesia?
Yes, for work on the owner’s own home, with the notarised Homeowners’ Responsibilities form. The owner cannot do the electrical, plumbing or mechanical work without passing the state exam for that trade.
How long does plan review take?
From 2 days to several weeks, according to the City. Reviews are done on Tuesdays and Thursdays.
How do I book an inspection?
Call 575-748-8298 or email buildingpermits@artesianm.gov by noon one business day ahead.
Simplify Artesia permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in New Mexico. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Artesia sooner?
Let Alliance prepare, file, and track your Artesia permits while your crew stays on the job.
More New Mexico permitting guides
This guide is provided by Alliance Permitting for general information about Artesia permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.