Stone County, Missouri Building Permit Guide

To get a building permit in Stone County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Stone County, Missouri issues a zoning building permit for unincorporated land through its Planning & Zoning office in Galena, charged at 20 cents per square foot of footprint, after an inspector checks the staked site.

Authority: Stone County Planning & ZoningFee: $0.20 per sq ft of footprintPhone: 417-357-8402
Where to apply
112 E. 5th St., Galena
Site inspection
Up to 5 working days; stake the site
Septic first
Health Dept. permit, any lot size
Moratorium
Data centers, solar, wind, batteries to June 4, 2027

On unincorporated land in Stone County, the county’s Planning & Zoning Department, 112 E. 5th St., Galena (417-357-8402), issues the building permit. It is a zoning permit: staff check the use, setbacks and site, and the fee is 20 cents per square foot of footprint with no maximum. Voters chose to keep county planning and zoning on April 7, 2026, and a 12-month moratorium on data centers and large energy projects was enacted on June 4, 2026. Kimberling City, Reeds Spring, Branson West and the other towns run their own permits.

What needs a county permit?

Under the county zoning regulations (effective August 5, 2009), a building permit from the Planning and Zoning Director is needed before any structure is built, moved or rebuilt and before land is improved for a new use. Repair or maintenance needs no permit unless it changes the structure’s height or the ground area it covers. The Director must issue or refuse a permit within ten days of receiving the application, and the permit lapses after six months if work has not started. The regulations and the permit packet adopt no building code, and the only inspection the packet describes is a site visit before construction starts.

Before the building permit, a lot that is not on sewer needs a Stone County Health Department septic permit; a new access from a county road needs a driveway inspection number from the county road foreman, and an access from a state road needs MoDOT. The application asks whether the building will be used as a short-term rental, and tells applicants to contact the Stone County Fire Marshal before building.

Stone County building department: who handles permitting

Planning & Zoning is open 8:00 a.m. to 4:00 p.m. weekdays (mailing address P.O. Box 301, Galena); the County Commission is at P.O. Box 19, Galena (417-357-8141). Each town permits work inside its own limits:

Short on time to read all of this?

Get a free quote →
Who permits building work in Stone County’s towns (2025 Census estimates)
PlaceWho permits building work
Kimberling City (2,345)City Hall, 34 Kimberling Blvd. (417-739-4903); permits for any building, accessory structure or work that needs inspection; 2021 International Codes and 2020 National Electrical Code; contractors need a city licence
Reeds Spring (1,223)City Building Inspector, City Hall, 21016 Main St., Suite B, 417-272-3309; 2009 International Building and Residential Codes, 2018 plumbing and existing building codes, 2017 National Electrical Code
Indian Point (580)Zoning Administrator issues a zoning compliance permit before any structure is built or altered
Branson West (485)Building Department, City Hall, 110 Silver Lady Lane, 417-272-3313; 2012 International Codes and 2011 National Electrical Code
Galena (474)City Hall, 113 E. 4th St., 417-357-6226; its posted ordinances set rules for placing mobile, manufactured and modular homes; ask City Hall about other building permits
Crane (1,509)The state lists a city floodplain contact at 120 N. Commerce (417-723-8305); ask City Hall about building permits
McCord Bend (225), Hurley (178)No town code or permit form is published online; the state lists city floodplain contacts for Hurley (202 S. Walnut, 417-369-3420) and McCord Bend (1901 McCord Bend Rd., 417-357-8500); ask the town about building permits
Blue Eye (310), Coney Island (46)No town code or permit form is published online; ask the town clerk before building
Branson (no residents in this county)Branson Planning & Development, Building Division, 417-337-8549

County permit fees

The building permit costs 20 cents per square foot of the footprint, counting decks, porches and the garage, with no maximum; the fee doubles if concrete is poured or construction starts before approval. For example, a house with a 1,800 sq ft footprint including its porch and garage pays 1,800 × $0.20 = $360.

Not sure this scope needs a permit?

Get a free quote →
Other Stone County Planning & Zoning fees
ApplicationFee
Conceptual permit; lot split$50; $50
Rezoning$200 plus $1 per mailed notice
Conditional use permit$100 plus notices and the county’s cost for third and later engineer reviews
Subdivision or plot assignment district$60 per lot plus third and later engineer reviews
Condominium project$60 per unit plus third and later engineer reviews
Sign permit; variance$100; $100
Administrative appeal; appeal of a board decision$150; $300
Boat dock parking$200 plus $1 per mailed notice

Site inspection and setbacks

An inspector visits the property before construction can start; because of demand this can take up to 5 working days, and an unstaked site may add another week. The setbacks on the application are 25 ft from the front and back property lines (measured from the road easement), 10 ft from each side, 25 ft from any Corps of Engineers property line, and 10 ft between a detached building and the main structure. The county permit expires six months from purchase.

Moratorium, zoning changes, septic and floodplain

Planning and zoning vote: a citizen petition with 1,496 signatures put the question “shall county planning and zoning be continued” on the April 7, 2026 ballot; it passed 4,123 to 4,045. The Commission adopted amendments to the zoning and subdivision regulations on July 21, 2026 and accepted draft accessory dwelling unit amendments on September 8, 2026.

Rather talk it over?

Call 1-855-478-4290 →

Moratorium: on June 4, 2026 the County Commission adopted an order and ordinance placing a moratorium on solar energy, wind energy, battery storage and data-center facilities in unincorporated Stone County while the zoning regulations are amended. No rezoning, conditional use, building permit or variance application for these facilities is accepted or considered. It ends automatically on June 4, 2027 unless the Commission ends it sooner or extends it because the zoning amendments are not finished. Existing facilities and small systems on a property that produce power for the owner’s own use there are not covered.

Septic systems: the Stone County Health Department permits every onsite system, new, repaired or replaced, regardless of lot size (North Office, 109 E. 4th St., Galena, 417-357-6134; South Office, 701 Old Wilderness Rd., Reeds Spring, 417-272-0050). Installers must be registered with the state and the county, a county-registered soil scientist writes the soil report, the installer stakes the system for a pre-site visit, and the permit must be posted and the system left uncovered for the final inspection. Permits are valid for one year. Since July 1, 2009, a property served by a septic system needs a property transfer certificate before it is sold.

Floodplain: the zoning regulations adopt FEMA’s flood regulations by reference, with a copy at the Planning & Zoning office; floodplain questions go to that office, and the Commission appointed an assistant floodplain administrator in August 2026. Stone County’s flood maps are dated August 28, 2024; Crane, Galena, Hurley, Kimberling City, McCord Bend and Reeds Spring take part in the flood insurance program, while FEMA lists Blue Eye, Branson West, Coney Island and Indian Point as not participating.

Town fees: Branson West charges $4 per $1,000 of value; for a one- to four-family home the minimum is $65, plus plan review of 0.125% of value ($40 minimum) and $45 for each inspection visit. Reeds Spring’s Building Inspector collects $35 per inspection and $70 for a sewer connection. Indian Point fines building without a zoning compliance permit $100 a week in residential zones and $250 in commercial zones.

Rather not deal with the Stone County building department?

Get a free quote →

How to get a Stone County permit

1. Confirm the jurisdiction and zoning

Check that the lot is outside town limits and zoned for the use; rezonings and conditional uses go to the Planning Board.

2. Septic or sewer

Get the Health Department septic permit, or the name of the sewer plant, first.

3. Road access

Get a driveway inspection number from the county road foreman, or MoDOT on a state road.

4. Apply

File the residential application with a site plan showing all buildings and setbacks, and pay 20 cents per sq ft of footprint.

5. Stake the site

Mark the corners so the inspector can check setbacks before work begins.

Missouri building code

Missouri has no mandatory statewide building code for private construction: a county, fire protection district or municipality may adopt one (usually by reference under RSMo 67.280), and in parts of the state none has. Building codes in Missouri

Stone County permit FAQs

Do I need a building permit in unincorporated Stone County?

Yes. The Planning & Zoning Director must issue a permit before a structure is built, moved or rebuilt; repairs that do not change its height or footprint are exempt.

How much is a Stone County building permit?

20 cents per square foot of footprint, including decks, porches and garage, with no maximum; the fee doubles if work starts first.

Which building code applies on county land in Stone County?

None is adopted in the county regulations or permit packet; the county permit is a zoning permit with a site and setback inspection before work starts.

Is there a data center or solar moratorium in Stone County?

Yes. On June 4, 2026 the County Commission adopted a moratorium on data centers, solar, wind and battery storage facilities that ends on June 4, 2027 unless ended early or extended.

Want this handled start to finish?

Get a free quote →

Do large lots need a septic permit in Stone County?

Yes. The county ordinance requires a permit for any new, repaired or modified system regardless of lot size.

Who issues permits in Kimberling City?

City Hall at 34 Kimberling Blvd. (417-739-4903), under the 2021 International Codes; contractors need a city licence.

Stone County permit search and official resources

Inspections are where schedules slip.

Get a free quote →

Simplify Stone County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Missouri. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Stone County sooner?

Let Alliance prepare, file, and track your Stone County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Stone County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.