Freeborn County runs its own building permit program: Environmental Services at 2020 Pioneer Trail in Albert Lea handles building plan review, permits and construction inspections under the International and State of Minnesota Building Codes, along with land use, septic, feedlot and wetland work. Sheds of 200 square feet or less and qualifying farm buildings take a land use permit instead, a building permit lapses if work does not start within 180 days, and variance, conditional use and rezoning applications cost $400 each. Each of the 14 cities, Albert Lea included, handles its own zoning.
What requires a permit in Freeborn County?
Freeborn County’s Building Inspections unit, within Environmental Services, states its job as building plan review, permit requirements, inspection of construction and application of the International and State of Minnesota Building Codes. Its building permit application covers new buildings and other projects, with the general contractor and subcontractors listed, the new building’s dimensions and setbacks, and the estimated value of the project.
Building permit
- New homes and additions
- Garages and accessory buildings over 200 sq ft
- Other construction covered by the State Building Code
- Energy storage systems, where the state code applies
Land use permit instead
- One-story detached storage or tool sheds and playhouses of 200 sq ft or less
- Agricultural buildings on land classified agricultural, used only for farm implements, livestock and farm products
The small structure permit exists because the State Building Code does not require a building permit for one-story detached accessory storage buildings of 200 square feet or less. The county still wants to know about them: each one counts against the total detached accessory structure area its zoning ordinance allows. A farm building qualifies only if the parcel is classified agricultural on the latest tax valuation notice and the building will not be used for personal storage or public uses such as retail sales, mini-storage, vehicle storage, riding lessons or livestock shows.
What the county decides and what the state holds
The county applies the State Building Code through its building permits and sets its own zoning, septic and feedlot rules for land outside incorporated cities. The technical rules are the state code’s; its agricultural exemption leaves only floodplain, electrical and skylight-load requirements for qualifying farm buildings. Electrical permits are issued by the Department of Labor and Industry, and wells are regulated by the Minnesota Department of Health.
Short on time to read all of this?
Get a free quote →Freeborn County building department: who handles permitting
Environmental Services groups the county’s building inspections, planning and zoning, septic and environmental health, feedlot, watershed and solid waste programs in one office. Building permit questions and inspection requests go to the Building Inspections staff; septic, well testing and wetland questions to the environmental staff; manure and feedlot permits to the feedlot officer; and rural addressing to solid waste management. The feedlot program files a County Feedlot Officer annual report and a feedlot program financial report with the Minnesota Pollution Control Agency each year, the latest for 2025, and the county posts manure application separation distances for Freeborn County.
| Office | Contact |
|---|---|
| Environmental Services (building, zoning, septic, feedlot) | 2020 Pioneer Trail, Albert Lea, MN 56007; 507-377-5186; weekdays from 8 a.m. (the department pages give closing times of 4:30 p.m. and 5 p.m.) |
| Public Works (county roads, ePermitting) | 3300 Bridge Avenue, Albert Lea, MN 56007; 507-377-5188; weekdays 7 a.m. to 3:30 p.m. |
| Wells | Minnesota Department of Health, Well Management Section, 651-201-4600 |
| Electrical | Department of Labor and Industry electrical permits |
Cities in Freeborn County
County zoning applies outside the limits of incorporated cities, so each city below handles its own zoning and building-code decision. The septic ordinance covers all county land except incorporated areas running their own county-approved program. Flood-program status is from FEMA’s Community Status Book.
| City | Flood program status |
|---|---|
| Albert Lea (18,217) | Participating |
| Alden (575), Glenville (560), Geneva (503), Emmons (363), Twin Lakes (132) | Participating |
| Hollandale (306) | Listed as not participating |
| Clarks Grove (682), Hartland (314), Freeborn (259), Hayward (255), Conger (152), Manchester (53), Myrtle (49) | No separate entry |
Freeborn County permit types
The county posts a building permit application, an agricultural and small structure (land use) permit application, a septic permit application, and three hearing applications: the Board of Adjustment variance, the Planning Commission conditional use permit and the petition for a change of zone. Demolition jobs have their own packet with MPCA steps, a pre-renovation checklist, the 2026 list of licensed asbestos contractors, a notification form, a farm disposal affidavit and forms for abandoning a septic system or well.
Residential permits
A new home needs a building permit and, where there is no sewer, an approved septic permit; the septic ordinance says the septic permit must be issued before the building or land use permit unless the county agrees otherwise in writing. The building application lists the owner, each contractor with a license or bond number, the project description, building dimensions, setbacks on all four sides, the estimated value and the lot size, and county staff confirm the zoning district and setbacks before signing. A small shed of 200 square feet or less uses the small structure form with a site plan showing where it sits.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial and other permits
Commercial and other non-farm buildings go through the building permit and plan review. Agricultural buildings use the land use permit with a written description of the intended farm use. The 2026 energy storage ordinance on the county’s ordinance page, drafted at the Planning Commission’s direction from June 2, 2025 and recommended for approval after its June 1, 2026 hearing (the posted text does not show the board’s adoption date), sets rules in the Renewable Energy Systems chapter for systems of 100 kilowatts or more below the state Public Utilities Commission threshold, outside city limits, including a conditional use permit and building permits as the state code requires. Storage systems must be 1,320 feet from a dwelling or a city unless a neighbor signs a recorded waiver, and never closer than 200 feet to a dwelling; 150 feet from road rights-of-way, with fencing at least 100 feet back; 100 feet from public drainage systems and wetlands; and 30 feet from side and rear lines. Battery units may not be stacked or exceed 12 feet in height, the site needs a locked security fence with 24-hour emergency contact signs, and the owner files a decommissioning plan with financial security, an emergency response plan worked out with local emergency services, and test reports to the county within 10 days.
What comes before the permit
- Septic permit. Designed by an MPCA-licensed designer and issued before the building permit.
- Bedrooms and bathrooms. An addition triggers a review of the existing system, with 10 months to upgrade, repair, replace or abandon it if needed.
- Hearings. Variances go to the Board of Adjustment, and conditional uses and rezonings to the Planning Commission and County Board; the hearing forms ask whether a septic compliance inspection is done.
- Wetlands. The environmental and watershed staff handle wetland questions before any filling or drainage.
- County roads. Public Works takes road-related permits through its online ePermitting site.
Freeborn County permit fees
The county’s building page and building permit application print no building permit fee; the application asks for the estimated value of the project, so call Environmental Services at 507-377-5186 for the fee on a specific job. The fees printed on the county’s own forms and pages are these:
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Variance (Board of Adjustment) | $400, non-refundable |
| Conditional use permit (Planning Commission) | $400, non-refundable |
| Rezoning petition | $400, non-refundable |
| Well water test: bacteria | $80 |
| Well water test: bacteria and nitrates | $100 |
| Well water test: bacteria, nitrates and lead | $120 |
Hearing fees are paid by check to the Freeborn County Treasurer. When a property with a non-compliant septic system is sold without a certificate, the seller must put money in escrow: 150 percent of a licensed installer’s written estimate, or 110 percent of a signed installation contract. Grants for replacing failing septic systems are income dependent, and the county also runs a septic loan program under a July 2011 ordinance.
Trade permits and who may pull them
Electrical permits are filed with the Department of Labor and Industry, which applies the 2026 National Electrical Code to permits filed on or after August 17, 2026; the county’s septic permit form even has the landowner confirm that the state electrical inspector will be notified of any septic pumps or alarms. Residential building contractors, electricians and plumbers are licensed by the state, and the county keeps no trade license of its own.
- Contractors on the permit. The building application lists up to three contractors with their license or bond numbers.
- Septic contractors. The county posts a 2026 list of sewer system contractors, and system designs carry the designer’s MPCA license number.
- Asbestos. For demolition and renovation, the county posts its 2026 list of licensed asbestos contractors.
How to apply for a Freeborn County permit
Inside Albert Lea or another of the 14 cities, the city handles zoning and its own building-code decision.
Building permit for most construction; agricultural or small structure permit for qualifying farm buildings and sheds up to 200 sq ft.
Get the septic design and permit approved first if the project needs a new or changed system.
Fill in the parcel number, contractors, dimensions, setbacks, value and lot size, and attach plans for review.
File the application at 2020 Pioneer Trail in Albert Lea; permit questions go to the Building Inspections staff by email.
Begin work before the permit lapses and keep it going without a 180-day stop.
Contact Building Inspections to set up each inspection.
Rather not deal with the Freeborn County building department?
Get a free quote →Review, corrections and what causes delay
Plan review comes before the permit, and staff check the zoning district and setbacks and may add conditions of approval. Septic issues are the most common hold-up: the septic permit has to be in place first, and hearing applicants are asked whether a septic compliance inspection has been completed. Variances, conditional uses and rezonings wait for the Board of Adjustment or the Planning Commission and the County Board, and rezoning petitions carry the Planning Advisory Commission’s recommendation to the board. A variance application is complete only with the names and addresses of the owners and anyone else with a legal interest, a site plan showing dimensions, buildings and natural features that bear on the request, and copies of any state and federal permits the project needs, plus a written statement of the situation that makes the variance necessary.
Inspections in Freeborn County
Freeborn County inspects construction under its building permits; requests to set up a building inspection go to the Building Inspections staff at Environmental Services. Septic systems are handled by the environmental staff, and the 2009 permit form records setbacks, tank sizes, drainfield dimensions and pump details, including GPS location, photos or video of the system.
A property with a dwelling or a building that must have a septic system cannot change hands until a compliance inspection is done and a certificate issued, by county staff or a licensed inspection business, and the seller must disclose all known systems in writing. Agricultural buildings exempt from the code are still subject to floodplain and electrical inspection requirements. Electrical work is inspected under the state permit.
Minnesota building code
Freeborn County enforces the State Building Code through its Building Inspections unit, and its land use rules are in the Freeborn County Code of Ordinances, published on Municode, with the SSTS Ordinance No. 4 in effect since April 1, 2009. FEMA’s Community Status Book lists the county as participating in the National Flood Insurance Program since May 3, 1982, with a current flood map dated November 19, 2014.
Minnesota has one State Building Code that applies statewide and overrides local building codes, but enforcement is local: whether a building permit is needed depends on whether the city, township or county enforces the code there. Electrical permits come from the Department of Labor and Industry unless the local government runs its own electrical inspection. Minnesota rules
Want this handled start to finish?
Get a free quote →Freeborn County permit search and official resources
Environmental Services keeps the county’s building, land use and septic permit files, and property details can be looked up in the county’s Beacon parcel viewer, which the small structure form links for finding a parcel number. Public Works takes its road permit applications through its online ePermitting site.
- Freeborn County Environmental Services
- Building information
- Building permit application
- Agricultural and small structure permit application
- Ordinances and hearing applications
- Freeborn County Code of Ordinances (Municode)
- 2026 energy storage systems ordinance
- Board of Adjustment variance application
- Conditional use permit application
- Rezoning petition
- Septic (sewer) resources and applications
- Sanitary Sewage Treatment System Ordinance No. 4
- Well water testing
- Feedlot program
- Public Works
- Minnesota Department of Health well programs
- State electrical permits (DLI)
- FEMA Community Status Book, Minnesota
Inspections are where schedules slip.
Get a free quote →Freeborn County permit FAQs
Does Freeborn County inspect new houses?
Yes. Its Building Inspections unit does plan review and construction inspections under the International and State of Minnesota Building Codes.
Do I need a permit for a small shed?
A one-story storage shed of 200 square feet or less needs a small structure (land use) permit rather than a building permit.
Are farm buildings exempt?
From the building code, if the land is classified agricultural and the building houses only farm implements, livestock or crops; a land use permit is still required.
How long is a building permit good for?
It becomes void if work does not start within 180 days or stops for 180 days.
What does a variance cost?
$400, non-refundable, the same as a conditional use permit or a rezoning petition.
Do I need a septic inspection to sell?
Yes. A compliance inspection and certificate are required at transfer, or the seller must escrow funds for a new system.
Can I get my well water tested?
Yes. Environmental Services tests well water on Mondays, from $80 for bacteria to $120 with nitrates and lead.
Simplify Freeborn County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Minnesota. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Freeborn County sooner?
Let Alliance prepare, file, and track your Freeborn County permits while your crew stays on the job.
More Minnesota permitting guides
Mower County
Read guide →Steele County
Read guide →Waseca County
Read guide →Goodhue County Building Permit Guide
Read guide →Hennepin County Building Permit Guide
Read guide →Houston County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Freeborn County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.