To get a building permit in Thomas Township, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Thomas Township’s Building Department at 249 North Miller Road issues building, electrical, mechanical and plumbing permits for all residential and commercial construction in the township.

Authority: Thomas Township Building DepartmentFees: Schedules effective April 1, 2026Phone: 989-781-0150
Authority
Township Building DepartmentAll four trades are local
Fee schedules
Effective April 1, 20262026/2027 set
Soil erosion
Saginaw CountyFrom $300 for a house lot
Septic permit
$585County Health Department, 2026

In Thomas Township, the Building Department at 249 North Miller Road, Saginaw (989-781-0150), issues building, electrical, mechanical and plumbing permits and makes sure all residential and commercial construction in the township meets the codes. It is part of the township’s Community Development Department with assessing and planning and zoning. The township’s 2026/2027 fee schedules took effect on April 1, 2026, and soil erosion, county drain, well and septic permits come from Saginaw County agencies.

What requires a building permit in Thomas Township?

The township’s permit information page quotes the residential code’s rule: an owner or authorized agent who plans to build, enlarge, alter, repair, move or demolish a building or structure, change its occupancy, or install, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system covered by the code must first apply to the building official and obtain the permit. A permit can be needed whether you do the work yourself or hire a contractor, and the department answers the question by phone at 989-781-0150.

Township permit applications

  • New construction (houses and other buildings)
  • Accessory buildings and decks
  • Roofing
  • Swimming pools
  • Demolition
  • Signs

Trade permit applications

  • Electrical
  • Mechanical, including gas piping
  • Plumbing
  • Contractor registration

New construction carries the township’s tree planting requirements as part of its application packet, and the Building Department keeps a Floodplain Information page.

What Thomas Township decides and what the state holds

On the Bureau of Construction Codes’ Statewide Jurisdiction List (revised November 6, 2026), Thomas Township enforces the building, electrical, mechanical and plumbing codes itself, and Saginaw County has no construction-code program. The state writes the code; the township adopts its fee schedules, registers contractors, sets tree planting requirements for new construction and writes its Zoning Ordinance, administered by its Planning and Zoning Department.

Thomas Township building department: who handles permitting

The Building Department belongs to the township’s Community Development Department, which groups the Assessing, Building and Planning and Zoning departments, together with code enforcement. Its staff work with residents, contractors and developers on residential and commercial projects.

Short on time to read all of this?

Get a free quote →
Thomas Township permit contacts
ItemDetail
OfficeBuilding Department, 249 North Miller Road, Saginaw, MI 48609-4896
Phone989-781-0150; for urgent matters call and leave a voicemail, as email replies are not immediate
Fax989-781-0290
Trades issuedBuilding, electrical, mechanical and plumbing
Related officesPlanning and Zoning, Assessing and code enforcement in Community Development

Thomas Township uses a Saginaw mailing address but is not the City of Saginaw or Saginaw Charter Township; each of those runs its own building department, so a “Saginaw” address alone does not tell you which office permits a parcel. The township has 11,900 residents in the Census Bureau’s 2025 estimate.

Thomas Township permit types and forms

Most applications on the permit information page come with the department’s own checklists or brochures.

Residential permits

  • New construction: the application plus Requirements for Obtaining a Building Permit, a New Construction Plan Review Checklist, an energy code worksheet and changes punch list, the Michigan Uniform Energy Code Contractor Acknowledgement Form and the Tree Planting Requirements.
  • Accessory buildings and decks: an accessory building application with its plan review checklist and brochure, and a separate Building Decks brochure.
  • Roofing: a roofing permit application with the Guide to Roofing brochure and a roofing information handout.
  • Swimming pools: a pool permit application and the Swimming Pool Requirements brochure.
  • Demolition: a demolition application with a demolition checklist.
  • Value of the work: the township’s Construction Cost Determination and Fees sheet is posted with the fee schedule.

Commercial permits

Commercial construction goes through the same Building Department, which reviews it against the building, electrical, plumbing and mechanical codes. Site plans and zoning approvals come from the Planning and Zoning Department under the Zoning Ordinance, and business signs need the township’s sign permit application.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. The Planning and Zoning Department administers the Zoning Ordinance; check setbacks, uses and site plan needs there first.
  • Soil erosion. The Saginaw County Public Works Commissioner issues soil erosion permits in the township when an earth change disturbs more than 1 acre, is within 500 feet of a water of the state such as a lake or stream, a county drain (open or tiled) or a pond over 5 acres, or is any lot in a multi-lot development. The application needs a scaled drawing no larger than 200 feet to the inch, the legal description and proof of ownership.
  • County drains. Culverts, ditch cleaning and utility crossings on a county drain need the Public Works Commissioner’s right-of-way permit; the office maintains about 860 county drains.
  • Well and septic. A building site without public water and sewer needs a well permit and a wastewater permit from the Saginaw County Health Department, which evaluates soil borings first. A site in a regulated floodplain or wetland needs the state permit before the Health Department will issue its own.

Thomas Township permit costs and fees

Thomas Township’s fees are set in its 2026/2027 Fee Schedules, effective April 1, 2026, posted on the Fee Schedules page; the permit page also links the township’s Construction Cost Determination and Fees sheet. Call the Building Department at 989-781-0150 to price a specific permit. County agencies charge separately:

Saginaw County permit fees that apply in Thomas Township
ItemFee
Soil erosion, residential 12-month, under 1 acre$300
Soil erosion, residential 12-month, 1 acre or more$300 plus $150 per acre over one
Soil erosion, residential 18-month$400; $400 plus $150 per acre over one
Soil erosion, industrial or commercial$500; $500 plus $200 per acre over one
Residential septic permit (from Oct. 1, 2026)$585
Residential septic permit, tank only$270
Residential Type III well permit$275
Land evaluation (void after 3 years)$400
Soil re-evaluation$145
Septic or well installed without a permitDouble the normal fee

Rather talk it over?

Call 1-855-478-4290 →

Example from the county schedules: a new house on an unsewered lot that disturbs 2 acres, permitted in May, would pay $450 for a 12-month residential soil erosion permit ($300 plus $150 for the one acre over the first), plus $585 for the septic permit and $275 for the well permit. Between January 1 and March 31 the county issues only 18-month residential soil erosion permits, which start at $400.

Trade permits and who may pull them

All three trades are local in Thomas Township: its Building Department issues electrical, mechanical and plumbing permits and inspects the work. The current trade application forms took effect on April 1, 2023, and a permit may be needed whether the owner does the work or hires a contractor.

  • Electrical: the township electrical permit application.
  • Mechanical: the township mechanical permit application, covering heating, cooling and gas piping.
  • Plumbing: the township plumbing permit application; the private well and septic system themselves are Saginaw County Health Department permits, and septic installers must be registered with the Health Department.
  • Contractors: building and trade contractors register with the township on its Contractor Registration Form and work under their state licenses.

How to apply for a Thomas Township building permit

1. Call to confirm the permit

The department answers whether a permit is needed at 989-781-0150.

2. Clear zoning

Setbacks, uses and any site plan with Planning and Zoning.

3. County permits

Soil erosion, county drain, well and septic permits where they apply.

4. Fill in the packet

Use the checklist for new construction, accessory buildings, roofs, pools or demolition.

5. Register and file

Contractor registration, then the building and trade applications.

6. Pay the fees

From the schedules effective April 1, 2026.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

The department reviews new construction against its New Construction Plan Review Checklist, so check the packet against it before filing; the packet also carries the energy worksheet, the contractor’s energy code acknowledgement and the tree planting requirements. County steps take their own time: the Health Department aims to act within ten days of receiving a complete well and septic application, a copy of the recorded deed, the fees and notice that the soil borings are done, but cannot issue a permit on a floodplain or wetland site until the state permit is in hand. Email is answered with a delay, so call 989-781-0150 for anything urgent.

Inspections in Thomas Township

The Building Department inspects building, electrical, mechanical and plumbing work under its permits; the township pages read do not say how inspections are booked, so ask the office at 989-781-0150.

  • Building: inspections under each building permit.
  • Trades: separate inspections under each electrical, mechanical and plumbing permit.
  • Well and septic: the Saginaw County Health Department samples and inspects a new well and inspects the septic system before it is covered.
  • Soil erosion: handled under the Public Works Commissioner’s permit, issued from 111 S. Michigan Avenue, Saginaw (989-790-5258).

Health Department septic permits are valid for two years, and a land evaluation is void after three.

Michigan building code in Thomas Township

FEMA’s Community Status Book lists Thomas Township (community 260603) as participating in the National Flood Insurance Program since January 19, 1983, with flood maps effective August 15, 2023, and the Building Department posts floodplain information for owners.

Michigan enforces one statewide construction code under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230); local units cannot amend it, and enforcement sits with the city, village or township, a county program or the state Bureau of Construction Codes, sometimes split by trade. Michigan rules

Want this handled start to finish?

Get a free quote →

Thomas Township permit search and official resources

Permit and inspection records for township parcels are kept by the Building Department; assessing records sit with the Assessor’s Office in the same Community Development Department. Ask the office at 989-781-0150 about permits on a property.

Thomas Township building permit FAQs

Inspections are where schedules slip.

Get a free quote →

Who issues building permits in Thomas Township?

The township Building Department at 249 North Miller Road, Saginaw (989-781-0150), for building and all three trades.

When did the current fees take effect?

The 2026/2027 fee schedules took effect on April 1, 2026.

Do I need a permit if I do the work myself?

Possibly; the township says a permit may be needed whether you do your own work or hire a contractor, and the department will tell you by phone.

Do I need a soil erosion permit for a new house?

Yes if the earth change is over 1 acre, near water or a county drain, or on a lot in a multi-lot development; the county permit starts at $300.

Who issues septic and well permits?

The Saginaw County Health Department: $585 for a residential septic permit and $275 for a residential well from October 1, 2026.

Is Thomas Township part of the City of Saginaw?

No. It shares the Saginaw mailing address but runs its own building department.

Do contractors register with the township?

Yes, on the township’s Contractor Registration Form.

Simplify Thomas Township permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Michigan. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Thomas Township sooner?

Let Alliance prepare, file, and track your Thomas Township permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Thomas Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.