Oceola Township’s Planning & Zoning office at 1577 N. Latson Road, Howell (517-546-3259, ext. 226) issues the land use permit or waiver that every project needs first, usually within one business day; a new house costs $150 under the fee schedule the township adopted on January 6, 2026. The Livingston County Building Department (517-546-3240) then issues the building, electrical, mechanical and plumbing permits and inspects the work. The township office is open only Tuesday to Thursday.
What requires a building permit in Oceola Township?
Oceola describes a land use permit as the permit to legally start a building project in the township, and a waiver as its sign-off for work that needs county review but no township review. The township’s lists are partial; its office asks you to call when a project is not on them.
Land use permit
- New homes
- New commercial and industrial buildings
- Additions to buildings
- In-ground pools
- Garages, attached or detached
- Storage buildings and pole barns
- Decks and porches
- Ground or wall signs
- Ground-mounted solar
Land use waiver ($50)
- Demolitions
- Driveways
- Finished basements
- Roof-mounted solar panels
- Above-ground pools
- Ponds
The county decides the construction-code side. Its project guide treats a shed or storage building under 200 square feet and 10 feet in height as needing no building permit, and a re-roof laid over the existing shingles as needing none; a tear-off re-roof needs one. Oceola’s land use list still covers storage buildings, so check with the township before building even a small one.
What Oceola decides and what the state holds
Oceola controls zoning, site plans, special uses, private roads, flag-lot driveways, land divisions and blight enforcement, and sets its own fees, most recently in the schedule adopted on January 6, 2026. Building, electrical, mechanical and plumbing enforcement is not a township function here: the state’s Statewide Jurisdiction List names Livingston County as the enforcing agency for all four codes in Oceola Township.
Oceola Township building department: who handles permitting
The township’s Planning & Zoning office handles land use and provides consultations to residents, builders, contractors and businesses on whether a project complies with township ordinances. The construction permit office is the Livingston County Building Department in Howell, whose Building Official is Jim Rowell; Oceola’s own pages send building, mechanical, electrical and plumbing questions there.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Oceola Township Planning & Zoning | 1577 N. Latson Road, Howell, MI 48843; (517) 546-3259, ext. 226; zoning@oceolatwp.org; fax (517) 546-6697 |
| Township office hours | Tuesday, Wednesday and Thursday 9:00 a.m.–5:00 p.m.; closed Monday and Friday |
| Township online applications and payments | BS&A Online (Oceola Township) |
| Livingston County Building Department | 2300 E Grand River Ave, Suite 104, Howell, MI 48843; (517) 546-3240; office 8:00 a.m.–5:00 p.m., permits until 4:00 p.m., Monday to Friday |
| County inspection request line | (517) 546-3830 |
Note the two BS&A accounts: Oceola’s township portal takes land use applications and payments, and the county’s separate portal takes building and trade permits and inspection requests.
Oceola Township permit types
Oceola posts a land use permit application, a waiver form, a requirements sheet and applications for site plan review, special use permits and renewals, rezoning, planned unit developments, site condominiums, private roads, signs and variances, along with escrow forms from $500 to $15,000.
Residential permits
- Land use permit. One copy of the construction plans and one site or plot plan showing the property dimensions, adjacent roads, easements, wetlands, lakes and streams, all structures, wells, septic tanks and fields and the distances from buildings to property lines, with building elevations; the application form; a homeowners association’s written approval where one exists; and, for new construction, the meter form.
- Waiver. The waiver form and fee for work on the waiver list, such as a finished basement or roof solar array.
- County building permit. The county wants the township approval, its application, two scaled plan sets (24 by 36 inches minimum) with floor plans, elevations, framing and insulation values, soil erosion and well and septic permits or waivers, proof of ownership and identification; houses over 3,500 square feet and log homes need sealed drawings.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and office land use permits cost $250 and industrial $500, and site plan review for those projects costs $2,000 with a $10,000 escrow. Special use permits are $700 with a $4,000 escrow, and a change that alters an existing building’s footprint is reviewed for $500 plus a $5,000 escrow. The county’s commercial package then needs architect- or engineer-prepared plans, sealed structural calculations, a soil boring report, fire-rated assembly details and electrical, plumbing and mechanical designs; trade permits are bought separately from the building permit.
Site plans, special uses and rezonings go to the Planning Commission, which meets at 7:00 p.m. at Township Hall on the second Tuesday of the month; in 2026 the August and November meetings moved to the 18th and the 17th. Applications are due about 26 days before each meeting; the 2026 sheet’s last deadline, November 12, 2026, was for the December 8 meeting, so ask the office for the 2027 dates.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Driveway: a Livingston County Road Commission approach permit ($75 residential, $200 commercial or private road) or a waiver; flag-lot driveways also need township approval ($500 plus a $1,000 escrow).
- Land use permit or waiver from Oceola, with connection and meter fees collected at issuance where they apply; water meter packages are priced from the MHOG list.
- Address from the county GIS office for a vacant lot.
- Soil erosion: a Drain Commissioner permit for work within 500 feet of surface water or an acre of disturbance ($275 for over 600 square feet of disturbance, $200 below that), or a $60 waiver for sites farther from water; a 36-inch silt fence is standard unless the inspector waives it.
- Well and septic: county Environmental Health permits ($390 for a soil evaluation, $520 for a new septic system and $390 for a new well), or county sewer and water permits with proof of paid taps.
Oceola Township permit costs and fees
Oceola’s fee schedule was adopted on January 6, 2026, and its land use amounts match the township’s separate land use requirements sheet. The township accepts check, cash or card (3% extra on cards). The county posts its plan review fees and prices trade permits on each form.
| Item | Fee |
|---|---|
| Oceola land use permit: residential dwelling | $150 |
| Oceola land use permit: alteration or addition to a dwelling | $100 |
| Oceola land use permit: accessory structure up to 1,999 sq ft / 2,000 sq ft and up | $100 / $150 |
| Oceola land use permit: in-ground pool; deck or porch | $75 each |
| Oceola land use permit: commercial or office / industrial | $250 / $500 |
| Oceola permanent sign package | $100 |
| Oceola waiver of land use permit | $50 |
| Oceola Zoning Board of Appeals | $700 + $2,000 escrow |
| Oceola land split or combination | $100 per parcel created |
| Oceola bond for a temporary trailer during construction | $2,000 |
| Oceola site plan review (commercial, industrial, multi-family) | $2,000 + $10,000 escrow |
| Oceola special use permit / rezoning | $700 + $4,000 escrow / $2,000 + $5,000 escrow |
| County plan review: new home / addition / deck | $150 each |
| County plan review: finished basement / pole barn / in-ground or above-ground pool | $100 / $75 / $125 |
| County commercial plan review over $5 million | $5,000 + 0.0004 of value above $5 million |
| County trade permits | $30 application + items + $50 final |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the county commercial worksheet: a $6,000,000 building pays $5,000 plus 0.0004 × $1,000,000 ($400), or $5,400, in plan review at application, subject to the county’s valuation check. For a new house, Oceola’s $150 land use permit and the county’s $150 plan review are fixed amounts; any connection and meter fees and the county building permit fee are set for the specific project.
Trade permits and who may pull them
All electrical, mechanical and plumbing permits in Oceola come from the county, on separate applications that each carry a $30 non-refundable application fee and a $50 final inspection. Commercial items show the range: $65 per rooftop mechanical unit and $30 per unit heater, $1 per sprinkler head with a $45 minimum, $30 for a rooftop unit’s electrical connection, $30 for a sign and $8 per fire alarm device; on the plumbing side a toilet is $15, a floor drain $10 and a water distribution pipe from 3/4 inch to 2 inches $35. A typical house rewire or new service draws on the residential lines: $20 for a service up to 200 amps, $8 a circuit and $8 per 25 light fixtures.
Contractors must be registered with the county ($15 per state license) and sign their own trade applications, or name a signer in a notarized letter. A homeowner may apply for residential building and trade permits on their own home with identification, signing the affidavit on each trade form that the work is for their own use and occupancy; the county’s homeowner policy explains the contractor responsibilities an owner-builder takes on. Environmental Health’s online booking for well and septic inspections is set up for contractors, with morning and afternoon windows.
How to apply for a building permit in Oceola Township
Call ext. 226 or email zoning@oceolatwp.org on a Tuesday to Thursday to confirm permit or waiver, setbacks and any HOA approval.
New lots need a Road Commission approach permit or waiver and a county GIS address.
Submit the land use permit or waiver with the plans and site plan, online through Oceola’s BS&A portal or at the office, and pay the fee.
Get the Drain Commissioner and Environmental Health permits or waivers.
File the building permit application and plan review fee on the county’s BS&A Online or at Suite 104 in Howell.
Each licensed trade, or the homeowner, files the county electrical, mechanical or plumbing application.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The township’s quick turnaround assumes a complete package: the HOA’s written approval where there is one, the meter form for new construction and a site plan with distances to the lot lines. Because the office is closed Mondays and Fridays, plan pickups and questions around those days. If a county permit is voided, expires or passes to a new contractor, the county issues a continuation permit, which needs an updated land use form from Oceola and fresh erosion and health approvals, with fees set case by case.
Inspections and occupancy in Oceola Township
Livingston County inspectors do the building, electrical, mechanical and plumbing inspections on Oceola permits. Use the county’s BS&A Online or its automated line at (517) 546-3830: requests close at midnight for the next available day, cancellations close at 5:00 a.m., and results are usually posted the following day. A failed inspection brings a re-inspection fee that can be paid online, after which the visit can be rebooked.
The certificate of occupancy is the county’s. It follows passed inspections, the township’s zoning compliance where the township requires it, the installer’s certificate for any blown cellulose insulation, Environmental Health’s final approval of the well and septic and payment of every fee; the county asks for about 48 hours and charges $100 for a temporary certificate. County permits lapse after 180 days without work starting or after a 180-day pause, and a written request with $75 buys one 180-day extension.
Michigan building code in Oceola Township
There is no township building code to check in Oceola: the county applies the state codes, and the township’s own controls are its zoning ordinance, engineering standards, anti-blight ordinance and the master plan adopted on October 4, 2022. FEMA’s Community Status Book lists Oceola Township (community 260847) as participating in the National Flood Insurance Program, with maps dated September 17, 2008.
Michigan enforces one statewide construction code under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230); local units cannot amend it, and enforcement sits with the city, village or township, a county program or the state Bureau of Construction Codes, sometimes split by trade. Michigan rules
Want this handled start to finish?
Get a free quote →Oceola Township permit search and official resources
County building and trade permits, inspection results and fees are searchable on the county’s BS&A Online, and copies of past county permit files are requested through the county FOIA portal. For township land use permits and other township records, Oceola takes written FOIA requests on its own form, which is linked from its home page.
- Oceola Township Planning & Zoning
- Oceola fee schedule (adopted Jan. 6, 2026)
- Land use permit requirements
- Land use permit application
- Waiver of land use permit
- Zoning Board of Appeals application
- Oceola Township BS&A Online
- Oceola Township contacts and hours
- Oceola FOIA request form
- Livingston County Building Department
- County residential permit steps
- County commercial permits
- County plan review fees
- County continuation permits
- County inspection line
- County BS&A Online
- Residential soil erosion permits
- Livingston County Environmental Health
- Road Commission permits
- County FOIA portal
- Michigan Statewide Jurisdiction List
Inspections are where schedules slip.
Get a free quote →Oceola Township building permit FAQs
Who issues building permits in Oceola Township?
Livingston County. Oceola issues land use permits and waivers first.
How much is a land use permit for a new house in Oceola?
$150 under the January 6, 2026 fee schedule, plus connection and meter fees where they apply.
Can I apply online?
Yes for both steps: Oceola takes land use applications and payments on its BS&A portal, and the county takes building and trade permits on its own.
Do roof-mounted solar panels need township approval?
A $50 land use waiver; ground-mounted solar needs a full land use permit.
When is the township office open?
Tuesday, Wednesday and Thursday, 9:00 a.m. to 5:00 p.m.
How fast is township review?
Typically one business day for a complete land use application.
Does a finished basement need a permit in Oceola?
Yes: a $50 township waiver, then a county building permit with a $100 plan review, and a septic review if you add a bedroom or bathroom on a private system.
What does a variance cost in Oceola?
$700 plus a $2,000 escrow for review costs.
Simplify Oceola Township permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Michigan. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Oceola Township sooner?
Let Alliance prepare, file, and track your Oceola Township permits while your crew stays on the job.
More Michigan permitting guides
Livingston County
Read guide →Tyrone Township
Read guide →Brighton Charter Township
Read guide →Ogemaw County Building Permit Guide
Read guide →Osceola County Building Permit Guide
Read guide →Oshtemo Charter Township Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Oceola Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.