Grand Rapids Charter Township (2025 Census estimate 19,442) is not the City of Grand Rapids: it has its own hall at 1836 East Beltline Avenue NE (616-361-7391) and its own zoning, and it uses Cascade Inspection Services of Cascade Charter Township as its building department. Every building, electrical, mechanical and plumbing application is turned in to the township first for review and approval; Cascade then issues the permit, answers fee questions, collects the permit fees and does the inspections. Township charges such as the $200 storm water permit come from a fee schedule the board approved on October 21, 2025.
What requires a building permit in Grand Rapids Charter Township?
The township adopted the State Construction Code in 2001, so the code’s own permit rule applies: building, altering, repairing, moving or demolishing a structure, or changing its use, needs a permit unless the code exempts it. The township’s submittal sheet and fee schedule show the projects and local permits it deals with, from houses and pools to storm water and land divisions.
Through Cascade
- New homes and additions, with decks and porches counted as part of the house
- Pools, with pool and fence specifications
- Accessory buildings, remodels, re-roofs and demolition
- Commercial buildings and alterations
- Electrical, mechanical and plumbing work
Township permits and reviews
- Review and approval of every building application
- Storm water permit ($200)
- Site plan review, special land uses and planned unit developments
- Land divisions, lot line adjustments and combinations
- Private roads and shared driveways
- Mineral mining permits
Height limits and setbacks come from the township zoning ordinance, compiled in March 2024; the submittal sheet asks owners to check height with the township before drawing plans and warns that a deck or porch counts toward the setback of the house.
What the township decides and what the state holds
The state’s Statewide Jurisdiction List shows Grand Rapids Township enforcing all four codes locally, and it does so through Cascade under contract. The township sets its own zoning, planning and storm water fees, keeps the master plan, zoning ordinance and utility atlases, and holds the first review of every application; the building code itself is the state’s and cannot be changed locally. For a parcel inside the City of Grand Rapids, none of this applies: the city runs its own program through its Development Center.
Grand Rapids Charter Township building department: who handles permitting
The township says all applications must be turned in to Grand Rapids Township for review and approval before Cascade Inspection Services issues a permit. Cascade’s Building Inspections department in Cascade Charter Township, where Brian Wilson is Building Official, reviews the code, issues the permit and inspects; the township office answers zoning and site questions, and Cascade answers questions about permit costs and the building code.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Township hall (applications, zoning) | 1836 East Beltline Ave. NE, Grand Rapids, MI 49525; 616-361-7391; fax 616-361-6620 |
| Township hours | Monday to Friday 8 a.m. to 5 p.m. |
| Building and trade permits | Cascade Inspection Services, 5920 Tahoe Dr. SE, Grand Rapids; 616-949-3765 |
| Cascade hours | Monday to Thursday 7 a.m. to 4 p.m.; Friday 8 a.m. to noon |
| Code enforcement | Local for all four trades (state jurisdiction list), carried out by Cascade |
Grand Rapids Charter Township permit types
Cascade keeps a separate set of forms for this township: a building permit application headed “Grand Rapids Township, c/o Cascade Charter Township” and electrical, mechanical and plumbing applications marked the same way. Planning and zoning applications are the township’s own.
Residential permits
- Plans: three complete sets with all elevations, floor plans, the foundation plan and a cross section; reverse prints are not accepted, and some large homes need sealed plans.
- Site plan: the shortest distance from each structure to the lot lines in every direction.
- Pools: include the pool and the required fence specifications with the plans. The township’s swimming pool ordinance (Ordinance No. 3, in effect since October 3, 1966) covers pools more than 2 feet deep: they need a permit and approved plans before construction and a final inspection before use, may not sit in a front yard, and must be at least 7 feet from side and rear lot lines measured from the water’s edge. Electric wiring within 25 feet of the water must run underground in approved conduit and never over the pool, the drain goes to a storm sewer where one exists, and the pool must be enclosed by a fence at least 4 feet high that children cannot easily climb, with self-closing gates latched on the inside.
- Utilities: where township water and sewer are not used, Kent County Health Department well and septic permits come first, and the township warns they can take several weeks.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Plans for every commercial development must be sealed by a Michigan architect or engineer. Commercial sites also go through township site plan review, either by the Site Plan Review Committee ($750 plus a $1,250 escrow) or by township staff ($350), with engineering and legal reviews charged against the escrow. Special land uses, rezonings, planned unit development amendments and plats or site condominiums each carry a $1,500 fee and a $4,500 escrow.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Township review. Every building application is turned in at the township hall for review and approval before Cascade can issue it.
- Zoning Board of Appeals. Variances, appeals and special exceptions cost $350 for a residential use and $750 for a commercial use. The 2026 calendar sets its meetings on the second Tuesday of the month at 7 p.m., with no December 2026 meeting; the first 2027 meeting is January 12, 2027, with documents due by December 8, 2026.
- Planning Commission. Meets on the fourth Tuesday at 7 p.m.; the last 2026 meeting is set for November 24, there is none in December 2026, and the January 26, 2027 meeting has a December 15, 2026 submission date. Meetings are tentative and at the call of the chair.
- Storm water permit. The Storm Water Ordinance (No. 534, adopted September 7, 2021) bars any “development activity” without a township stormwater permit. The permit needs a drainage plan built to the township’s Stormwater Standards Manual, the review fee, any performance guarantee, the easements the plan needs and a maintenance agreement for the storm water controls recorded with the Register of Deeds; attorney and engineer review costs are drawn from the developer’s escrow. The permit covers storm water discharge only and does not replace other approvals.
- Road Commission. A KCRC driveway permit for a public road, or an address permit on a private road (616-242-6920).
- Soil erosion. A KCRC permit when earth is disturbed near water or over an acre; the township sheet lists lakes, streams, creeks, drainage ditches and wetlands within 500 feet, while KCRC’s own pages say within 500 feet of a lake or stream.
Grand Rapids Charter Township permit costs and fees
The township’s fee schedule, approved October 21, 2025 and effective January 1, 2026, does not list building or trade permit fees; for those it says to call Inspection Services at 616-949-3765, and Cascade’s township forms are paid to Cascade. The township’s own charges include:
| Township fee | Amount |
|---|---|
| Storm water permit | $200 |
| Zoning verification letter | $75 |
| ZBA variance, appeal, special exception or interpretation | $350 residential; $750 commercial |
| ZBA or Planning Commission interpretation request | $500 |
| Site plan review | $350 by staff; $750 + $1,250 escrow by committee |
| Private road or shared driveway | $750 + $1,250 escrow |
| Rezoning, special land use, plat or site condominium | $1,500 + $4,500 escrow each |
| Land division or lot line adjustment | $200 per new parcel number |
| Special meeting of the ZBA, Planning Commission or Board | $1,200 |
| Mineral mining permit | $1,500 ($500 renewal) + $2,000 escrow |
Rather talk it over?
Call 1-855-478-4290 →On Cascade’s side, the trade forms for this township start each electrical, mechanical or plumbing permit with a $70 application fee covering one inspection, with $70 for each further visit, and Cascade’s posted building fee schedule (adopted by Cascade in 2021) charges $140 plus $3.50 per $1,000 of value from the ICC valuation table, $175 for a deck and $85 for a re-roof. Worked example on those schedules: a deck permit is $175 to Cascade; if the deck is within 500 feet of a lake or stream, KCRC’s residential soil erosion permit for a deck adds $100, for $275 in all.
Trade permits and who may pull them
Electrical, mechanical and plumbing permits in the township are Cascade permits on township-specific forms, filed with the township’s review in the same way as building permits and paid by check to Cascade Charter Township. Cascade inspects every trade.
- Contractors register with Cascade once ($15 plus a copy of the license); the registration names Grand Rapids Township among the communities it covers and lasts as long as the license. Residential builders and maintenance and alteration contractors carry LARA licenses, and trade contractors state trade licenses.
- Homeowners may file the homeowner affidavit on a trade form only for work they install themselves in the home they live in or are about to occupy.
- Item fees follow Cascade’s charts, for example $10 for an electrical service up to 200 amps and $5 per circuit.
Rather not deal with the building department?
Get a free quote →How to apply for a Grand Rapids Charter Township building permit
Check that the parcel is in the township and not the City of Grand Rapids; the Kent County property search and the township zoning map help.
Call the township at 616-361-7391 about setbacks and height, and file any variance or site plan application by the calendar’s submission date.
KCRC driveway or address and soil erosion permits; Health Department well and septic permits, allowing several weeks.
The Grand Rapids Township building application, trade applications and contractor registration.
Three plan sets, the site plan and the county permits go to 1836 E. Beltline Ave. NE for township review and approval.
After township approval, Cascade reviews the code, collects its fees and issues the permit.
Review, corrections and what causes delay
Because the township review comes first, a missing site plan dimension, a height question or a county permit still in process stops the file before Cascade sees it; the township specifically warns that Health Department and soil erosion permits can take several weeks. Commercial projects that need site plan review or a variance must meet the township calendar, where submissions close five to six weeks before each meeting and there are no December meetings.
Inspections and certificates in Grand Rapids Charter Township
Cascade schedules all inspections for township permits. Use Cascade’s BS&A Online portal, call 616-949-3765 and press 1, or text 616-240-4693 with the address, contractor, contact number, access details, date and inspection type. Inspectors work by appointment.
A new house typically goes through pre-pour footing, pre-pour wall, pre-backfill, rough, insulation and final inspections. Before a certificate of occupancy, all building and trade permits must be finaled, energy code compliance documented and, on a private well or septic system, Kent County Health Department approval on file. Each extra inspection is $70 on Cascade’s schedule. Trade permits lapse if work does not start within six months, and any permit that goes six months without an inspection is cancelled without refund.
Michigan building code in Grand Rapids Charter Township
The township adopted the State Construction Code in 2001 and enforces it through Cascade. FEMA’s Community Status Book lists the Charter Township of Grand Rapids (community 260968) as a participating National Flood Insurance Program community, separate from the City of Grand Rapids, with flood maps effective February 23, 2023 and regular program status since February 23, 2024.
Michigan enforces one statewide construction code under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230); local units cannot amend it, and enforcement sits with the city, village or township, a county program or the state Bureau of Construction Codes, sometimes split by trade. Michigan rules
Want this handled start to finish?
Get a free quote →Grand Rapids Charter Township permit search and official resources
Township records, such as zoning approvals, site plans and meeting files, are available through a FOIA request under the township’s posted procedures and guidelines, with copies at 10 cents a page plus labor at the lowest-paid capable employee’s rate. Planning Commission and Board of Zoning Appeals agendas and minutes are on the Planning & Zoning page. Building and inspection records sit with Cascade, which posts monthly permit activity lists.
- Township building inspections page
- Building permit application submittal requirements
- Township fee schedule, effective January 1, 2026
- 2026 meeting and submission calendar
- Planning and zoning, ordinance and maps
- Swimming pool ordinance (Ordinance No. 3)
- Storm Water Ordinance No. 534
- FOIA procedures and cost worksheet
- Grand Rapids Township building permit application (Cascade)
- Grand Rapids Township electrical permit application
- Cascade forms by community
- Cascade Building Inspections and inspection requests
- Cascade building permit fee schedule
- Kent County Road Commission permits
- Statewide Jurisdiction List (Bureau of Construction Codes)
Inspections are where schedules slip.
Get a free quote →Grand Rapids Charter Township building permit FAQs
Is Grand Rapids Charter Township the same as the City of Grand Rapids?
No. They are separate governments with separate permit offices; the township uses Cascade Inspection Services, the city its own Development Center.
Where do I turn in a building permit application?
At the township hall, 1836 E. Beltline Ave. NE, for review and approval; Cascade then issues the permit.
How much is a building permit?
Cascade sets building and trade fees; its posted schedule is $140 plus $3.50 per $1,000 of value, with decks at $175. Township charges, such as the $200 storm water permit, are extra.
How many plan sets do I need?
Three complete sets with elevations, floor plans, foundation plan and a cross section; reverse prints are not accepted.
What does a variance cost?
$350 for a residential use or $750 for a commercial use under the 2026 fee schedule.
When does the Zoning Board of Appeals meet?
On the second Tuesday at 7 p.m.; there is no December 2026 meeting, and the first 2027 meeting is January 12, with documents due December 8, 2026.
Who do I call to book an inspection?
Cascade Inspection Services at 616-949-3765, or text 616-240-4693.
Simplify Grand Rapids Charter Township permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Michigan. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Grand Rapids Charter Township sooner?
Let Alliance prepare, file, and track your Grand Rapids Charter Township permits while your crew stays on the job.
More Michigan permitting guides
Kent County
Read guide →Grandville
Read guide →Kentwood
Read guide →Grand Traverse County Building Permit Guide
Read guide →Gratiot County Building Permit Guide
Read guide →Green Oak Charter Township Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Grand Rapids Charter Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.