To get a building permit in Fenton Charter Township, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Fenton Charter Township’s Building Department at 12060 Mantawauka Drive issues building, electrical, mechanical and plumbing permits for the township, and takes applications by email at permits@fentontownship.org.

Authority: Fenton Township Building DepartmentFiling: Email to permits@fentontownship.orgPhone: 810-629-6711
Authority
Township Building Dept.All four codes local
Office hours
Mon–Thu 8–5810-629-6711
Fees
Revised Nov. 1, 2026New schedule for new applications
City of Fenton
Separate officeNot covered by the township

In Fenton Charter Township the township itself enforces the building, electrical, mechanical and plumbing codes. Its Building Department, 12060 Mantawauka Drive (810-629-6711, Monday to Thursday 8 a.m. to 5 p.m.), takes every permit and form by email at permits@fentontownship.org; Stuart Worthing is the Building Official. The Board of Trustees approved a revised Building Department fee schedule with new bond and deposit rules for applications filed from November 1, 2026. The City of Fenton is a separate government with its own building office.

What requires a building permit in Fenton Charter Township?

The Building Department issues and tracks permits for new construction, additions, alterations, repairs and demolitions, and inspects that work. Its forms page shows the jobs it sees most: new houses, additions and alterations, accessory buildings such as garages, sheds and pole barns, decks, swimming pools and demolitions, each with its own checklist. Electrical, mechanical, plumbing and sign work have separate applications.

Building Department permits

  • New homes, with the residential new construction and new build checklists
  • Additions, alterations, remodeling and fire repair
  • Garages, sheds, pole barns and other accessory buildings
  • Decks, porches, gazebos and ramps
  • In-ground and above-ground pools
  • Demolition
  • Electrical, mechanical and plumbing work

Zoning and other township permits

  • Zoning permit for fences, sheds, ponds, soil fill and soil removal that need no building permit
  • Grading plan review for new homes
  • Wetland and drainageway use permit
  • Sign permits
  • Short-term rental annual permit
  • Township sewer and water connection permits

The 2025 schedule lists the zoning permit as the permit “for structures not requiring a building permit”, so a small shed or a fence still goes through the township even when no building permit is needed. Starting regulated work before a permit is issued doubles the permit fee, with a $500 minimum.

What the township decides and what the state holds

The Bureau of Construction Codes’ Statewide Jurisdiction List (revised November 6, 2026) shows the township as the enforcing agency for all four codes; Genesee County has no construction-code program, and the City of Fenton has its own line on the list. The township cannot change the state code, but it sets its own fees, deposits, zoning ordinance, grading rules and sewer and water connection charges through the Board of Trustees.

Fenton Charter Township building department: who handles permitting

The township Building Department handles permits and inspections for every trade. The same office holds the forms for zoning permits, business licenses and garage sale and amplified sound permits, and its staff include a building and enforcement coordinator alongside the Building Official.

Short on time to read all of this?

Get a free quote →
Fenton Charter Township permit contacts
DetailInformation
OfficeBuilding Department, 12060 Mantawauka Drive, Fenton, MI 48430
Phone / fax810-629-6711 / 810-629-9736
ApplicationsEmail to permits@fentontownship.org
HoursMonday to Thursday, 8 a.m. to 5 p.m.
Building OfficialStuart Worthing
Township offices810-629-1537 (same address)
Enforcing agencyFenton Charter Township for building, electrical, mechanical and plumbing (state list)

Parcels inside the City of Fenton go to the city’s own building office at its city hall, not to Mantawauka Drive. Check the tax bill or parcel record if you are not sure which government a lot is in.

Fenton Charter Township permit types

All applications are PDF forms that are filled in and emailed to the Building Department. The forms page pairs most permits with a checklist of what to attach.

Residential permits

  • New houses use the building permit application with the residential new construction checklist, the new build checklist and the grade plan checklist; the township reviews a grading plan for each new home.
  • Additions and alterations have their own checklist, as do accessory structures (garages, sheds, pole barns).
  • Decks use the deck checklist and the deck specification sheet.
  • Pools, in-ground or above-ground, use the swimming pool checklist and carry a refundable deposit.
  • Demolitions follow the township’s demolition requirements sheet.

Commercial permits

Commercial buildings use the same building permit application, with fees by floor area on the commercial part of the schedule, a refundable deposit, and a grading plan review by the township engineer. New commercial sites go to the Planning Commission for site plan review, which also carries a township engineer review fee. New businesses need a township business license and, where required, a fire and safety inspection.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. Setbacks and uses come from the township zoning ordinance; the Planning Commission hears site plans, special uses and rezonings, and the Zoning Board of Appeals hears variances and appeals.
  • Soil erosion. The forms page carries the Genesee County soil erosion permit application. The Genesee County Drain Commissioner’s Division of Water & Waste Services (G-4610 Beecher Road, Flint; 810-732-7870) issues soil erosion permits and waivers under Part 91, along with “B-permits” for new utility connections.
  • Septic and wells. Where there is no public sewer or water, the Genesee County Health Department (810-257-3603) issues septic and well permits; the perc test needs a street address from the Road Commission first.
  • Driveways and addresses. The Genesee County Road Commission (211 West Oakley Street, Flint; 810-767-4920) issues driveway, right-of-way and address permits through its Oxcart online system.
  • Sewer and water. Lots on public utilities use the township’s sewer and water permit forms and pay township and county connection charges.

Fenton Charter Township permit costs and fees

⚠️ Revised fees from November 1, 2026. The Board of Trustees approved a revised Building Department fee schedule and new bond and deposit requirements that apply to all new applications filed from November 1, 2026 (township notice of October 27, 2026). The new amounts are not posted on the township’s fee page, which still links the schedule effective January 1, 2025; ask the Building Department (810-629-6711) for the figures before you budget.

The table shows the posted schedule so you can see how the fees are built. Residential building fees are charged by floor area, trade permits start from a $75 non-refundable application fee plus item charges and $75 per inspection, and several permits carry a deposit refunded after final approval.

Fenton Charter Township schedule of fees effective January 1, 2025 (being replaced for new applications)
ItemFee (posted 2025 schedule)
New dwelling, addition, remodeling or fire repair$0.50 per sq ft, minimum $100
Accessory building (garage, shed, pole barn)$0.40 per sq ft, minimum $100
Deck; porch, gazebo or ramp; demolition$100 each
Refundable deposit: new build, addition or sunroom / accessory building / porch or deck$350 / $250 / $100
Swimming pool permit plus refundable deposit$100 + $200
Residential grading plan review, initial / detailed$200 / $500
Zoning permit (no building permit needed) / zoning compliance$100 / $100
Electrical, mechanical or plumbing base application$75, plus item fees
Trade rough or additional inspection / required final inspection$75 / $75
Commercial new construction, first story up to 50,000 sq ft$0.50 per sq ft; second and third stories $0.15 per sq ft
Commercial grading plan review by township engineer$500
Work started before the permitBuilding permit fee doubled, minimum $500; trade permit fee doubled

Rather talk it over?

Call 1-855-478-4290 →

Trade item fees are small: on the 2025 schedule an electrical service up to 200 amps was $10, each circuit $5 and each 25 fixtures $6; a furnace, boiler or air conditioner was $30; plumbing fixtures and water heaters were $5 each. A re-application after a permit expires, and a cancellation or transfer, were $100 each, and a general reinspection $50.

Utility connections are separate. The 2025 schedule charges a direct sewer connection of $7,600 for the first residential equivalent unit (REU) and $3,800 for each additional one ($6,000 and $3,000 for indirect connections), a township water capital charge of $2,500 per REU (direct) or $2,000 (indirect), a county tap and meter fee of $3,950 for a meter of 1 inch or less, and a county capital improvement fee of $1,000 per REU set by the Drain Commissioner’s Water & Waste Services; sewer and water connection inspections are $150 each.

Planning and zoning charges sit on the same schedule: a Zoning Board of Appeals variance or appeal is $200, a commercial site plan review $500 plus $500 for the township engineer’s review, a rezoning $700, a special use permit $400 ($125 when approved administratively), a home occupation permit $100, a short-term rental permit $750 a year, and an appeal to the Construction Code / Fire Code Board of Appeals $500. Ask whether any of these changed with the November 2026 revision.

Trade permits and who may pull them

Electrical, mechanical and plumbing permits are township permits here, each on its own application emailed to permits@fentontownship.org, and the township inspects the work. Each trade permit carries a required final inspection; the schedule also lists a special inspection connected with the sale of a building.

  • Electrical fees cover services, circuits, fixtures, fire alarm devices, data outlets and solar, wind turbine and EV charging units by size.
  • Mechanical fees cover furnaces, boilers, air conditioners and heat pumps, gas piping, fireplaces, ducts and commercial equipment, and fire suppression piping at $0.75 per head.
  • Plumbing fees cover fixtures, stacks, water service and distribution piping, sewers, backflow preventers and water heaters.
  • Sewer work. Contractors who connect to township sewer hold a township sewer contractor license ($50 a year on the 2025 schedule).

Rather not deal with the building department?

Get a free quote →

Contractors hold state trade licenses. An owner planning to do their own electrical, mechanical or plumbing work should ask the Building Department before applying.

How to apply for a Fenton Charter Township building permit

1. Confirm the parcel is in the township

City of Fenton addresses go to the city, not the township.

2. Settle zoning and site work

Check setbacks, ask whether a zoning permit, Planning Commission or ZBA approval is needed, and prepare the grading plan for a new home.

3. Line up county permits

Soil erosion from the Drain Commissioner’s Water & Waste Services, septic and well from the Health Department, and address and driveway permits from the Road Commission.

4. Fill in the township forms

Complete the building permit application and the checklist for your project, plus separate electrical, mechanical and plumbing applications.

5. Email the package

Send applications, plans and checklists to permits@fentontownship.org.

6. Pay fees and deposits

Ask for the fees and deposits that apply to applications filed from November 1, 2026, then pay as the department directs.

7. Build to inspections

Call for each required inspection and get final approval, which releases any refundable deposit.

Review, corrections and what causes delay

Send the whole package at once: each checklist lists what the township wants with the application. New homes also wait on the grading plan review, the county soil erosion permit and either a septic and well permit or the sewer and water connection permits. A permit that lapses must be re-applied for, and on the 2025 schedule that cost $100.

Inspections and certificates in Fenton Charter Township

The township inspects building and trade work on its permits; call the Building Department at 810-629-6711, Monday to Thursday, about booking inspections. Trade permits list a rough or additional inspection and a required final inspection. For new homes the township also checks the final grade against the grading plan; a final grade reinspection was $100 on the 2025 schedule. Deposits on houses, additions, accessory buildings, decks and pools are refunded only after final approval, so close out each permit with its last inspection.

County inspections run alongside the township’s. The Health Department inspects a new septic tank and drainfield before backfilling, and it posts winter restrictions on septic installation (the last notice covered December 15, 2025 to April 15, 2026). Well permit applications must reach the Health Department at least three working days before drilling, and the Drain Commissioner’s staff inspect soil erosion controls and new sewer and water leads.

Want this handled start to finish?

Get a free quote →

Michigan building code in Fenton Charter Township

The township’s building page describes its work as enforcing the Michigan Residential Building Code, and the state list shows it enforcing the building, electrical, mechanical and plumbing codes. FEMA’s Community Status Book lists the Township of Fenton (community 260394) as a participating National Flood Insurance Program community with maps dated September 25, 2009; the City of Fenton is listed separately.

Michigan enforces one statewide construction code under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230); local units cannot amend it, and enforcement sits with the city, village or township, a county program or the state Bureau of Construction Codes, sometimes split by trade. Michigan rules

Fenton Charter Township permit search and official resources

For copies of township permits, plans or inspection results, ask the Building Department or file a public records request with the township under Michigan’s Freedom of Information Act. Septic and well records are held by the Genesee County Health Department, which runs its own record search.

Inspections are where schedules slip.

Get a free quote →

Fenton Charter Township building permit FAQs

How do I submit a permit application in Fenton Township?

Email the completed forms and plans to permits@fentontownship.org, or call 810-629-6711 with questions.

How much is a building permit in Fenton Township?

The posted 2025 schedule charged $0.50 per square foot for houses and additions, minimum $100, but new applications since November 1, 2026 use a revised schedule; ask the department for the current figures.

Do I need a permit for a shed or fence?

Yes, at least a township zoning permit; larger accessory buildings need a building permit charged by floor area.

Who issues electrical and plumbing permits?

The township Building Department, which the state list shows enforcing all four codes here.

Does Fenton Township issue permits in the City of Fenton?

No. The city runs its own building department.

What happens if I start work without a permit?

Under the posted schedule the permit fee is doubled: for building and commercial permits with a $500 minimum, and for electrical, mechanical and plumbing permits with no minimum stated.

Who issues soil erosion permits?

The Genesee County Drain Commissioner’s Division of Water & Waste Services; its application is on the township forms page.

Simplify Fenton Charter Township permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Michigan. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Fenton Charter Township sooner?

Let Alliance prepare, file, and track your Fenton Charter Township permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Fenton Charter Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.