Norton, Massachusetts Building Permit Guide

To get a building permit in Norton, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Norton’s Building Department at 72 East Main Street issues building, wiring, plumbing, gas and mechanical permits through OpenGov, and a new one- or two-family house costs $50 plus $12 per $1,000 of construction cost.

Authority: Norton Building DepartmentCode: 780 CMR, 10th edition, with the Stretch energy codePhone: (508) 285-0290
Authority
Building Department72 East Main Street, Room 224
Apply online
OpenGovOther departments sign off in the same file
New house fee
$50 + $12 per $1,000Schedule effective January 1, 2019
Energy code
Stretch codeIn force since July 1, 2019

Norton’s Building Department, headed by the Building Commissioner, issues residential and commercial building permits, electrical, plumbing, gas and mechanical permits, certificates of occupancy and certificates of inspection from the Norton Municipal Center at 72 East Main Street. Applications are filed in the town’s OpenGov permit system, and the fee schedule in force since January 1, 2019 charges a new one- or two-family house $50 plus $12 per $1,000 of construction cost.

Norton has enforced the Stretch energy code since July 1, 2019. It also has a six-month demolition delay run by the Historical Commission, the Norton Center Historic District, and a floodplain overlay in which the Building Commissioner serves as the town’s flood administrator. Wetland filings follow the state Wetlands Protection Act, because Norton has no wetlands bylaw of its own.

The Norton department covers the whole town. Mansfield, Attleboro, Taunton and Easton issue their own permits.

What requires a building permit in Norton?

The department’s FAQ quotes the state code’s rule that constructing, altering, repairing, removing or demolishing a structure, changing its use or installing regulated equipment needs a permit, and names dormers, chimneys, woodstoves, decks, roofing, siding, pools, antennae and sheds as common examples. Ordinary repairs are the exception: the FAQ allows rotted deck boards or a few damaged shingles to be replaced without a permit, but not a rebuilt deck or a whole new roof.

Norton permits

  • New houses, additions and foundations
  • Alterations, repairs, decks and demolition
  • Accessory structures and detached garages
  • Sheds of 100 square feet or more, under the town’s own shed rule
  • Pools, with a 48-inch barrier and self-closing, self-latching gates
  • Wood, pellet and coal stoves and fireplace inserts
  • Solar energy systems, sprinklers and fire alarms
  • Signs, tents over 120 square feet and trenches

Local limits worth knowing

  • Sheds sit at least 10 feet from the rear and side lines and no closer to the street than the house
  • Pools sit 10 feet from side and rear lines and 40 feet from the front in R40 and R60, 50 feet in R80
  • Any development in the floodplain overlay needs a permit, fences and sheds included
  • Work may not start until the permit is issued

What the town decides and what the state holds

780 CMR is the state’s code, written by the Board of Building Regulations and Standards, and Norton cannot amend it. Town meeting adopted the bylaws that shape a project locally: Chapter 136 brings in the Stretch energy code, Chapter 39 sets the demolition delay, Chapter 66 creates the Norton Center Historic District, and Chapter 175 is the zoning bylaw with its Floodplain District. Permit fees are approved by the Select Board.

Norton building department: who handles permitting

The Building Department issues all building and trade permits and also carries out annual inspections of restaurants, multi-family buildings, schools and day care centers. The wiring inspector and the plumbing and gas inspector work from the same office. The Planning and Economic Development Department staffs the Planning Board and the Zoning Board of Appeals.

Short on time to read all of this?

Get a free quote →
Norton permit offices (Municipal Center, 72 East Main Street, Norton, MA 02766)
OfficeRoleContact
Building Department, Room 224Building, electrical, plumbing, gas and mechanical permits; occupancy and inspection certificates(508) 285-0290; Building Commissioner Ed Bayly, Jr., (508) 285-0291
Board of Health, Room 203Review and approval of septic designs and installations(508) 285-0263
Conservation CommissionWetlands Protection Act filings; stormwater(508) 285-0275
Planning & Economic Development, Room 235Planning Board and ZBA applications(508) 285-0278

Town Hall is open Monday to Wednesday 8:30 am to 4:30 pm, Thursday 8:30 am to 7:30 pm and Friday 8:30 am to 12:30 pm. The Building Department closes for lunch from noon to 1 pm; its fax is (508) 285-0295.

Permit types

Residential permits

Norton takes permits through its OpenGov portal; an existing OpenGov login works, and public computers at Town Hall are available for anyone without one. A submitted application is only preliminary: the Building Department routes it to the other departments that must sign off, and the town does not treat it as officially submitted until every sign-off is in. The status of each sign-off can be followed in the account.

For a shed or other small structure the town asks for the online application, the contractor’s Construction Supervisor License and Home Improvement Contractor registration or a signed homeowner waiver, a plot plan with the setbacks, and drawings showing footings, framing and a cross-section. The FAQ says plot plans must be stamped by a Registered Land Surveyor; a mortgage plan is accepted only when the work is far from the setback lines.

Commercial permits

Buildings with three or more units and commercial work pay $100 plus $18 per $1,000 for new construction and additions, and $100 plus $15 per $1,000 for alterations and repairs. The minimum commercial fee is $100 or 1% of the contract, a commercial certificate of occupancy is $100 and a temporary sign may stay up 30 days. The department may ask for contracts to support the stated value, and a temporary occupancy certificate costs $100.

What comes before the building permit

  • Zoning: the Planning Board and Zoning Board of Appeals handle site plans, special permits and variances under Chapter 175; their filing fees changed on January 1, 2019. A zoning determination letter from the Building Department costs $150 for a residential property and $250 for a commercial one.
  • Conservation Commission: work near wetlands is reviewed under the state Wetlands Protection Act and the commission’s written policies, filed with the Town Clerk since 2001. The commission meets on the second and fourth Mondays at 6:30 pm.
  • Board of Health and Title 5: the board reviews and approves every septic design and installation, so a septic lot needs its approval before the house permit.
  • Historical Commission: demolishing 25% or more of a significant building, such as one on the National or State Register, within 200 feet of a historic district or shown on the town’s 1835 to 1875 maps, triggers review and can bring a six-month delay.
  • Floodplain District: the Building Commissioner is the flood administrator, and an applicant must complete the town’s checklist showing every local, state and federal permit the project needs.

Not sure this scope needs a permit?

Get a free quote →

Norton permit costs and fees

The building fee schedule, approved by the Board of Selectmen on November 1, 2018 and effective January 1, 2019, is the one the department still posts; the Select Board agendas for 2026 show no change to it. Fees are non-refundable and non-transferable, and work started without a permit can be charged double and fined.

Norton building permit fees, effective January 1, 2019
PermitResidential (1–2 family)Commercial (3+ units)
New construction and additions$50 + $12 per $1,000$100 + $18 per $1,000
Alterations, repairs, decks$50 + $10 per $1,000$100 + $15 per $1,000
Accessory structures and detached garages$50 + $10 per $1,000$50 + $15 per $1,000
Swimming pools, solar, chimneys, mechanical$50 + $10 per $1,000$50 or $100 base + $15 per $1,000
Demolition$50 + $10 per $1,000$100 + $15 per $1,000
Wood or pellet stove$75$100
Certificate of occupancy$50$100
Minimum fee$50$100 or 1% of contract
Re-inspection$50$75
Foundation only (special permit)$50 + $12 per $1,000$100 + $18 per $1,000
Temporary occupancy / certificate of inspection$50 / $75$100 / $75
Permanent sign / trench / tent over 120 sq ft$75 / $75 / $75$100 / $100 / $150
Temporary sign (30 days) / carnivaln/a$50 / $200
Permit re-issued after 2 years$100$200
After-hours inspection (48 hours’ notice)$225 ($75 an hour, 3-hour minimum)$225

Rather talk it over?

Call 1-855-478-4290 →

The commercial base for pools, solar and sprinklers differs: pools, chimneys and mechanical work start at $50, and solar, sprinkler and fire alarm systems at $100. Worked example: a new house with a construction cost of $350,000 pays $50 plus 350 × $12 = $4,200, so $4,250, plus the $50 certificate of occupancy. A $40,000 kitchen renovation pays $50 plus 40 × $10 = $400, so $450.

Trade permits and who may pull them

The plumbing and gas fee sheet states that all plumbing must be done by a Massachusetts licensed plumber, and the FAQ adds that homeowners may not do their own electrical, plumbing or gas work. The licensed tradesperson, not the owner, asks for the trade inspection, in writing, at least 24 hours ahead.

Norton trade permit fees (approved November 1, 2018)
PermitFee
Residential plumbing or residential gas$45 application fee plus $15 per fixture
Replacement water heater (plumbing and gas)$50 per unit
Commercial plumbing or gas; commercial electrical2% of contract plus $100 base fee
Electrical, single-family dwelling$150
Electrical, multi-family dwelling$100 per unit
Temporary service or service change$75
Additions and renovations; appliance$50; $50
Pool wiring, in-ground / above-ground$100 / $75
Alarm system up to 9 devices$50 per inspection
Annual maintenance (in-house electrician only)$175
Re-inspection, any trade$50

A stove permit needs the manufacturer’s installation instructions, and the unit must be listed to UL 1482 or ANSI/UL 737; pellet stoves must meet ASTM E1509. For building work, a homeowner may act as their own construction supervisor on their own home, and becomes the supervisor of anyone they hire.

Rather not deal with the building department?

Get a free quote →

How to apply for a Norton building permit

1. Get a stamped plot plan

For a new building or an addition, have a Registered Land Surveyor prepare the plot plan, or ask the department whether a plan on file is usable.

2. Settle zoning and wetlands

Ask for a zoning determination if needed and talk to the Conservation Commission about any work near wetlands or in the floodplain.

3. Line up the Board of Health

On a septic lot, get the septic design approved first.

4. File in OpenGov

Create or use an OpenGov account, choose the permit type and upload drawings, licenses, insurance or the homeowner waiver.

5. Follow the sign-offs

Watch each department’s sign-off in your account; the file counts as submitted only when all are complete.

6. Pay and receive the permit

Pay the assessed fee by check, debit or credit card; no work may begin before the permit issues.

Review, corrections and what causes delay

Under 780 CMR 105.3.1 a permit must be granted or refused within 30 days of filing, and Norton’s FAQ says small jobs can be issued in a day while new houses tend to take close to the full 30 days. Because the department counts a file as submitted only once every sign-off is in, a pending septic approval, Conservation review or zoning question is the usual reason a Norton permit waits.

Inspections in Norton

The FAQ asks for 24 hours’ notice before any inspection, and the plumbing, gas and wiring inspectors need the request in writing from the licensed tradesperson. Questions go to the office at (508) 285-0290. Someone must be home if the inspector has to pass through a furnished house, and the inspector will not enter an unoccupied furnished house or one where only a child is present.

For a house the town lists the footing (continuous keyway), the foundation after the as-built is received, sonotubes before concrete, rough wiring, plumbing and gas passed before the frame inspection, rough HVAC with the frame, rough frame, insulation fully in place, and the trade finals. The final building inspection happens only after every sign-off is recorded and the HERS rater’s certificate is uploaded; failed visits can cost $50.

Building and energy code in Norton

Massachusetts has one State Building Code, 780 CMR, for every city and town; towns cannot rewrite it, though many opt into a stricter energy code. The trades run under their own state codes. Massachusetts rules

Norton enforces the 10th edition of 780 CMR, although the Building Department page still mentions the ninth. The May 15, 2019 annual town meeting adopted the Stretch energy code as Chapter 136 of the general bylaws for residential and commercial buildings, with a sole effective date of July 1, 2019, and the Building Inspector enforces it. The town code shows no adoption of the Municipal Opt-in Specialized code. The Floodplain District in Article XIII of the zoning bylaw was last amended at the May 15, 2023 annual town meeting. FEMA lists Norton as a participating National Flood Insurance Program community with flood maps effective July 16, 2015, and its Community Rating System class 9 earns a 5% flood insurance discount.

Want this handled start to finish?

Get a free quote →

Norton permit search and official resources

OpenGov has a public search page for Norton records, so an issued permit can often be found by address without an account. For older paper files, contact the Building Department or file a public records request with the town.

Inspections are where schedules slip.

Get a free quote →

Norton building permit FAQ

What does a building permit cost in Norton?

Under the 2019 schedule a new house or addition is $50 plus $12 per $1,000 of construction cost, and alterations, repairs and decks $50 plus $10 per $1,000. A $350,000 house therefore pays $4,250 before trade permits.

Does a shed need a permit in Norton?

The town’s shed page asks for a permit application for any shed of 100 square feet or more, with a plot plan showing 10-foot side and rear setbacks. Sheds in the floodplain overlay need a permit whatever their size.

Can a homeowner pull a permit in Norton?

Yes for building work on their own home, signing the homeowner waiver; they then supervise anyone they hire. Electrical, plumbing and gas work must be done by state-licensed tradespeople.

How long does a Norton permit take?

Anywhere from a day for small jobs to close to 30 days for a new house, counted once every department has signed off in OpenGov.

Which energy code applies in Norton?

The Stretch energy code, adopted at the May 15, 2019 town meeting and in force since July 1, 2019.

Can I tear down an old house in Norton?

If the Historical Commission finds it significant and preferably preserved, the demolition permit can be withheld for six months. Demolishing a significant building without following the bylaw blocks any building permit on that lot for two years.

Does Norton have its own wetlands bylaw?

No. The Conservation Commission applies the state Wetlands Protection Act together with local policies on file with the Town Clerk since 2001.

Can I get an inspection after hours?

Yes, with 48 hours’ notice and a $225 fee paid in advance, covering three hours at $75 an hour.

Simplify Norton permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Massachusetts. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Norton sooner?

Let Alliance prepare, file, and track your Norton permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Norton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.