In Penobscot County, cities and towns issue building permits, while the state Land Use Planning Commission covers the 40 Unorganized Territories. Here are the offices of Bangor, Orono, Brewer and Hampden.

Authority: Municipal code offices; LUPC in the UTsCounty role: UT addressing and drivewaysLargest city: Bangor
Towns
City or town code officeOrganized municipalities
Unorganized Territories
State LUPC40 UTs
Bangor
207-992-4230Code Enforcement
Brewer
207-989-7790Up to 30 days review

Penobscot County has two permit worlds. In its cities and towns the municipal code office issues building permits. In the county’s 40 Unorganized Territories, building permits come from the state Land Use Planning Commission, while the county’s Unorganized Territory office handles E911 addressing and driveway entrance permits. By the Census Bureau’s 2025 estimates the largest municipalities are Bangor (32518), Orono (12421), Brewer (9636) and Hampden (8078).

This guide covers the four largest municipalities, the Unorganized Territories and the state office that permits public buildings.

What requires a building permit in Penobscot County?

Penobscot County has no county building rules. Maine’s building code is adopted statewide, but whether a permit is needed, what it costs and how it is filed are set by each town, as the examples below show.

Maine’s adopted code applies statewide, but permits are required where the town’s ordinance says so; shoreland zoning applies statewide near water, fees and appeals are local, and code enforcement officers must be certified by the state. Maine rules

Short on time to read all of this?

Get a free quote →

Who handles permitting in Penobscot County?

Unorganized Territories: building permits come from the state Land Use Planning Commission. Its Eastern Regional Office (191 Main Street, East Millinocket, by appointment only) serves southern Penobscot County, and its Northern Regional Office serves portions of northern Penobscot County. The county’s Unorganized Territory office (97 Hammond Street, Bangor, 207-942-8566) assigns E911 addresses, with a site visit, and anyone opening a new driveway on a town way there must complete the county’s Highway Entrance Permit Application.

Code offices of the four largest municipalities
TownOfficeContact and hours
BangorCode Enforcement, City Hall, 73 Harlow Street207-992-4230; Monday through Friday 8 a.m. to 4:15 p.m.
OronoCode Enforcement Office, 59 Main StPortal help 207-889-6909; Mon-Thurs 7:30-5:30
BrewerCode Enforcement, 80 North Main Street207-989-7790; Monday through Friday 8 am to 4 pm
HampdenCode Enforcement Office, Municipal Building, 106 Western Avenue207-862-4000 option 8; Mon to Thurs 7:30am to 6:00pm

For public buildings, the Maine State Fire Marshal’s Office Plans Review division (45 Commerce Drive, Suite 1, Augusta; (207) 626-3880) issues the state construction permit, plus accessibility (barrier-free) permits and fire sprinkler permits, on top of the town permit.

Not sure this scope needs a permit?

Get a free quote →

Local rules in the largest Penobscot County towns

Bangor

Contact the Code Enforcement Office to obtain a permit. The city publishes pre-approved housing plans, two accessory dwelling unit designs and a three-unit and a four-unit building, designed to meet current City of Bangor codes, each with a residential checklist.

Orono

Building, electrical, plumbing, heating and blasting permits, fees and inspection requests go through the town’s online portal. Curb cut and road opening permits are obtained at the Code Office but approved by Public Works, sewer connection or repair permits by the Wastewater Superintendent, and septic applications must be signed by the Site Evaluator or Engineer before submission.

Brewer

Code Enforcement handles all construction permits and certificates of occupancy, with applications through the city’s online portal. Apply about a month ahead, as review can take up to 30 days.

Hampden

Applications go through the town’s online portal; the Code Office issues building and demolition, solar, internal plumbing and subsurface wastewater, home business and flood hazard permits. The town notes that minimum standards in its application forms are out of date after the state code change of 4/7/2025. Projects on or within 300 feet of any waterbody may need a Shoreland Zoning permit even when no building permit is required.

Rather talk it over?

Call 1-855-478-4290 →

Penobscot County permit costs and fees

Each municipality sets its own fees. Brewer charges $0.50 per square foot of finished space and $0.25 per square foot of unfinished space for new construction and remodels (minimum $50, maximum $25,000), plus a non-refundable $20 review fee on all permits since October 11, 2022; base fees are doubled if the permit is pulled after work has started.

How to get a building permit in Penobscot County

1. Organized town or Unorganized Territory?

Towns issue their own permits; the 40 UTs go to the state LUPC.

2. In a UT, get the county pieces

E911 address and, for a new driveway on a town way, the Highway Entrance Permit.

3. Apply in the town portal

Orono, Brewer and Hampden take applications online; Bangor through its Code Enforcement Office.

4. Check shoreland

Hampden: within 300 feet of a waterbody a Shoreland Zoning permit may be needed.

5. Allow time

Brewer review can take up to 30 days.

Rather not deal with the Penobscot County building department?

Get a free quote →

Inspections in Penobscot County

Inspections are done by the municipal code office. Bangor schedules any on-site inspection with you; Orono takes inspection requests through its online portal.

Official Penobscot County permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Who issues building permits in Penobscot County’s Unorganized Territories?

The state Land Use Planning Commission; the county assigns E911 addresses and issues driveway entrance permits there.

How far ahead should I apply in Brewer?

About a month, as review can take up to 30 days.

Does Bangor have pre-approved plans?

Yes: two accessory dwelling unit designs and a three-unit and a four-unit building, each with a residential checklist.

Simplify Penobscot County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →
  • Confirm which town code office or state office has the parcel and the project type
  • Prepare the town application, state plumbing forms and any State Fire Marshal permit
  • Schedule the town’s required inspections and close out the permit

Alliance Permitting is a permit documentation and submission company in Maine. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Penobscot County sooner?

Let Alliance prepare, file, and track your Penobscot County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Penobscot County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.