Androscoggin County, Maine Building Permit Guide

Androscoggin County does not issue building permits: each city and town does. Here are the code offices of Lewiston, Auburn, Lisbon and Turner and how each takes applications.

Authority: Municipal code officesCounty role: None for permitsLargest city: Lewiston
Authority
City or town code officeTwo cities and 12 towns
Lewiston
(207) 513-3125Mail or email
Auburn
207.333.6601SmartGov portal
Lisbon
207-353-3000 Ext. 108Email or in person

Building permits in Androscoggin County are issued by each municipality, not by the county. The county lists two cities, Auburn and Lewiston, and the Towns of Durham, Greene, Leeds, Lisbon, Livermore, Livermore Falls, Mechanic Falls, Minot, Poland, Sabattus, Turner and Wales. By the Census Bureau’s 2025 estimates the largest are Lewiston (38866), Auburn (25441), Lisbon (9919) and Turner (6127).

This guide covers the code offices of the four largest municipalities and the state office that permits public buildings.

What requires a building permit in Androscoggin County?

Androscoggin County has no county building rules. Maine’s building code is adopted statewide, but whether a permit is needed, what it costs and how it is filed are set by each town, as the examples below show.

Maine’s adopted code applies statewide, but permits are required where the town’s ordinance says so; shoreland zoning applies statewide near water, fees and appeals are local, and code enforcement officers must be certified by the state. Maine rules

Short on time to read all of this?

Get a free quote →

Who handles permitting in Androscoggin County?

Each city and town issues its own building permits through its code office.

Code offices of the four largest municipalities
TownOfficeContact and hours
LewistonPlanning & Code Enforcement, 27 Pine St., 3rd Floor(207) 513-3125; Monday, Wednesday, Thursday 7:45 a.m. - 4 p.m., Tuesday 7:45 a.m. - 5:30 p.m., closed Friday
AuburnPlanning, Permitting & Code, Auburn Hall, 60 Court Street207.333.6601; Monday thru Friday, 8:30am to 4:00pm
LisbonCode Enforcement, Town Offices, 300 Lisbon Street207-353-3000 Ext. 108; Monday through Thursday 7:45 am to 4:30 pm
TurnerCode Enforcement Officer, Town Office, 11 Turner Center Road(207) 225-3414; Mondays and Thursdays 7:30 a.m. to 6:00 p.m.

For public buildings, the Maine State Fire Marshal’s Office Plans Review division (45 Commerce Drive, Suite 1, Augusta; (207) 626-3880) issues the state construction permit, plus accessibility (barrier-free) permits and fire sprinkler permits, on top of the town permit.

Local rules in the largest Androscoggin County towns

Not sure this scope needs a permit?

Get a free quote →

Lewiston

Planning & Code Enforcement issues building, electrical, plumbing and sign permits. Completed applications are mailed to 27 Pine Street or emailed; staff then quote the fee, payable by mail or by credit card by phone. No construction may start until the permit is paid for and issued.

Auburn

Applications, fee payment and inspection requests go through the city’s SmartGov portal. Applications submitted on or after April 7th, 2025 are held to the 2021 building code standards. In the Lake Auburn Watershed, the city’s plumbing inspectors work with the Lake Auburn Watershed Commission on septic and sewer designs.

Lisbon

Lisbon has temporarily suspended online permitting: print the application and email it or deliver it to the codes office in person.

Turner

The Code Enforcement Officer handles building and plumbing permits. The town’s forms include a building permit application that is also required for demolition, a New Home Construction Checklist, a Driveway Entrance Application, and the state HHE-200 (subsurface) and HHE-211 (internal plumbing) applications.

Rather talk it over?

Call 1-855-478-4290 →

Androscoggin County permit costs and fees

Each municipality sets its own fees. Lewiston quotes the fee after reviewing the application. Lisbon’s schedule in effect as of April 10, 2026 charges 2 times the permit fee or $150.00, whichever is greater, for starting work without a permit.

How to get a building permit in Androscoggin County

1. Find the municipality

The code office of the city or town where the parcel is issues the permit.

2. Apply the way that town takes it

Lewiston by mail or email, Auburn through SmartGov, Lisbon by email or in person, Turner at the Town Office.

3. Add plumbing and septic forms

Turner lists the state HHE-200 and HHE-211 forms; in the Lake Auburn Watershed septic designs are reviewed with the Watershed Commission.

4. Public buildings

Also get the State Fire Marshal’s construction permit.

5. Pay and wait for issue

In Lewiston no construction may start until the permit is paid for and issued.

Rather not deal with the Androscoggin County building department?

Get a free quote →

Inspections in Androscoggin County

Inspections are done by the municipal code office. Lewiston schedules them by contacting the office; Auburn takes inspection requests in SmartGov; Turner inspections are by appointment.

Official Androscoggin County permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Does Androscoggin County issue building permits?

No. Building permits are issued by each city and town.

Which code edition does Auburn use?

Applications submitted on or after April 7th, 2025 are held to the 2021 building code standards.

Can I apply online in Lisbon?

Not at present: Lisbon has temporarily suspended online permitting, so email the application or deliver it in person.

Simplify Androscoggin County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build
  • Confirm which town code office or state office has the parcel and the project type
  • Prepare the town application, state plumbing forms and any State Fire Marshal permit
  • Schedule the town’s required inspections and close out the permit

Inspections are where schedules slip.

Get a free quote →

Alliance Permitting is a permit documentation and submission company in Maine. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Androscoggin County sooner?

Let Alliance prepare, file, and track your Androscoggin County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Androscoggin County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.