St. Tammany Parish, Louisiana Building Permit Guide

Everything contractors, builders and developers need to pull a St. Tammany Parish building permit — the fast-growing North Shore, flood elevation and wind design, the municipalities that permit separately, the statewide LSUCC and inspections.

Authority: Permits & InspectionsScope: Unincorporated parishDrivers: Flood and wind
The North Shore
Across Lake PontchartrainSustained growth
Flood and wind both
Lakefront and inlandCriteria vary by site
Eight municipalities
Slidell, Covington, Mandeville and othersMost permit their own
Statewide code
LSUCC 2021 I-CodesNo local variation

Building permits for unincorporated St. Tammany Parish are issued by the parish Department of Permits & Inspections at 21454 Koop Drive, Building B, Suite 1B, Mandeville (985-898-2574). St. Tammany occupies the North Shore of Lake Pontchartrain and is growing: Census estimates put its population at 279,108 in 2025, up about 14,500 since 2020, the second-largest gain of any Louisiana parish.

This guide covers the department and how to reach it, the local conditions that shape a filing here, what permits cost and who may pull them, and how inspections are booked. Rules that apply everywhere in Louisiana are summarized in each section, with a link to the full statewide explanation.

This guide covers unincorporated St. Tammany Parish. The parish contains eight incorporated municipalities: Slidell, Covington, Mandeville, Abita Springs, Madisonville, Pearl River, Folsom and Sun. Most permit their own limits.

⚠️

St. Tammany carries both exposures at once, and they behave differently. The lakefront and eastern parish face storm surge and coastal flood risk, while inland areas face riverine and rainfall flooding along the Bogue Falaya, Tchefuncte and Pearl systems. Wind exposure also varies across the parish. A design developed against a generic parish assumption will be wrong somewhere. Establish flood zone, base flood elevation and design wind criteria for the specific parcel before the envelope is designed.

What requires a building permit in St. Tammany Parish?

Under the LSUCC as administered by the parish, a permit is required before most construction, alteration, demolition, repair, relocation, change of occupancy and trade work begins in unincorporated territory.

Permit required

  • New residential and commercial construction, additions, conversions and tenant improvements
  • Structural and load-bearing alterations, foundations, decks, porches and garages
  • Electrical service changes, panel work, new circuits, solar and EV charging equipment
  • Plumbing alterations, repipes, water heaters, gas piping and sewer connections
  • HVAC installations, change-outs, ductwork and venting
  • Re-roofing, siding, windows, pools, signs, demolition and change of occupancy or use

Typically exempt

  • Painting, wallpapering, tiling, carpeting and cabinet installation
  • Countertop replacement and comparable finish work
  • Minor repairs replacing existing materials in kind with no structural or system change
  • Detached residential accessory structures of 200 square feet or less, outside 130 mph wind regions (R.S. 37:3738), where zoning allows

Exemptions are narrow and local, and an exemption from a building permit is not an exemption from zoning, setbacks, floodplain rules, utility approval or a fire authority review. Confirm scope with the department before work starts rather than after.

Which code edition applies

St. Tammany Parish enforces the statewide LSUCC, as do the municipalities within it. The technical requirements do not change across those boundaries, which is a genuine convenience for a builder working the whole North Shore. Fee schedules, submittal processes, inspection scheduling and the flood and zoning layers do change, and those are the practical differences to establish.

Short on time to read all of this?

Get a free quote →
⚠️ Sustained residential growth makes drainage a permitting question, not just an engineering one. In a parish developing this quickly, stormwater management, detention, servitudes and subdivision drainage requirements frequently determine what can be built on a parcel and in what sequence. On subdivision and larger residential work, treat drainage approval as part of the critical path rather than as a downstream consequence of the site plan.

Every Louisiana parish and municipality enforces the state’s Uniform Construction Code (R.S. 37:3737), adopted by the Louisiana Uniform Construction Code Commission: the 2021 International Codes with Louisiana amendments, in force since 1 January 2023, and the 2020 National Electrical Code, with the 2024 codes taking effect on 1 January 2027. A local government may set more stringent requirements only with the Commission’s approval, and the State Fire Marshal reviews plans for fire and life safety on all but one- and two-family dwellings. How the LSUCC works

Who handles permitting in St. Tammany Parish?

The parish permits unincorporated territory through its Department of Permits & Inspections, which issues building, electrical, mechanical and plumbing and gas permits. Applications are made through the parish Customer Portal at mypermitnow.org, and the office is open to customers 8am to 4pm Monday to Friday. Contractors working in the unincorporated parish must also register with the department each year. Slidell, Covington, Mandeville, Abita Springs, Madisonville and Pearl River each permit their own limits, and Folsom has adopted the state code for its own limits; for the Village of Sun, confirm with the village who issues building permits. The built environment along the corridors gives little indication of where those boundaries fall.

St. Tammany Parish permitting contact
DetailInformation
AuthoritySt. Tammany Parish Department of Permits & Inspections, 21454 Koop Drive, Building B, Suite 1B, Mandeville, LA 70471 · 985-898-2574 · permits@stpgov.org
JurisdictionUnincorporated St. Tammany Parish
Municipalities insideSlidell, Covington, Mandeville, Abita Springs, Madisonville, Pearl River, Folsom and Sun
FloodCoastal surge on the lakefront, riverine and rainfall flooding inland
WindDesign wind speed and exposure vary across the parish
CodeLSUCC — statewide 2021 I-Codes with Louisiana amendments
Commercial plan reviewState Fire Marshal fire and life-safety review on all but one- and two-family dwellings, plus code review by the local authority or its contracted reviewer
Contractor licensingLouisiana State Licensing Board for Contractors, by classification and value, plus annual registration with the parish ($100 for building, electrical, mechanical and plumbing and gas)

The parish's growth has been residential above all. That produces sustained subdivision development, corridor commercial growth following it, and the infrastructure and drainage pressures that accompany both.

Not sure this scope needs a permit?

Get a free quote →

Because so much of the parish is wooded and low-lying, site work — clearing, fill, drainage, servitudes and access — is frequently the determining factor in what a parcel can carry. Resolve it before design is fixed rather than adjusting the building afterwards.

In 2025, building permits issued in unincorporated St. Tammany Parish authorized 1,007 new privately owned housing units, all of them single-family homes, according to the U.S. Census Bureau Building Permits Survey.

Louisiana’s counties are parishes, governed by a police jury or a home rule charter government, and some large communities, such as Metairie, have no city government and are permitted by the parish. The state sets the code and licenses contractors; the local authority sets fees, submittal requirements, review times, inspections, zoning, floodplain administration and local registration. What the state and the parish each decide

Permit types

Residential permits

Residential work is dominated by subdivision and custom construction across the North Shore, with renovation and elevation work in the older lakefront and Slidell-area communities. Flood elevation, drainage and wind design are the recurring technical questions, and on flood-affected property the substantial improvement threshold determines whether a renovation stays a renovation.

Commercial permits

Commercial development follows the residential growth: corridor retail and service, medical and office space, hospitality and light industrial activity. Larger projects bring drainage, traffic, utility and fire review alongside the building set. The parish charges its own commercial plan review fee, the State Fire Marshal reviews commercial plans for life safety, and the Fire Marshal has also listed St. Tammany Parish among the jurisdictions for which it performs building-code plan review, so confirm with the department which body will review your set against the building code.

Flood elevation and wind design decide most Louisiana projects: in a FEMA Special Flood Hazard Area, base flood elevation, flood-resistant construction and the substantial-improvement rules apply; the state code’s wind provisions include wind-borne debris requirements in wind-borne debris regions; and elevation certificates are permit documents that can delay the certificate of occupancy. Flood, elevation and wind in Louisiana

St. Tammany Parish permit costs and fees

St. Tammany Parish fees mix floor-area and contract-value charges. Residential additions are $300 plus $0.10 per square foot and remodels $100 plus $5 per $1,000 of the executed contract; residential plan review is $50 plus $0.01 per square foot and commercial plan review $150 plus $0.01 per square foot. Commercial trade permits are a percentage of the executed trade contract, and each re-inspection costs $100. Each municipality maintains its own separate schedule.

Rather talk it over?

Call 1-855-478-4290 →
How St. Tammany Parish permit fees are structured
Fee componentHow it works
Residential building permitAdditions $300 plus $0.10 per sq ft; remodels $100 plus $5 per $1,000 of the executed contract
Commercial building permitPlan review $150 plus $0.01 per sq ft; electrical permits 1% and mechanical, plumbing and gas permits 2% of the executed contract
Plan reviewPer the adopted fee schedule; State Fire Marshal plan review applies to all but one- and two-family dwellings
Trade permitsElectrical, plumbing and mechanical permits are charged separately
Flood and elevationFloodplain development review and elevation certification where applicable
Re-inspections and revisionsAdditional fees apply for failed inspections, revisions and expired permits
🧮

Need a real number for a specific St. Tammany Parish project? Send us the scope, address and valuation and we will identify the filing path, the reviews it will trigger and the fee categories that will apply.

Fee schedules are revised on each jurisdiction’s own cycle, so ask St. Tammany Parish for the schedule in force on your filing date, and ask separately about plan review, trade, re-inspection and revision charges. How Louisiana permit fees work

Trade permits and who may pull them

Permit required

  • Electrical service installations, panel upgrades, new circuits, solar PV and EV chargers
  • New plumbing, repipes, water heater change-outs, backflow, gas and sewer connections
  • HVAC installation and change-out, ductwork, venting and commercial kitchen exhaust
  • Fire alarm, sprinkler and suppression systems on commercial work

Typically exempt

  • Replacing a fixture, switch, receptacle or light with no alteration to wiring or piping
  • Clearing a stoppage without replacing or rearranging concealed piping
  • Filter, thermostat and routine component service
  • Appliance repair that does not alter the gas, electrical or venting connection

Rather not deal with the St. Tammany Parish building department?

Get a free quote →

The Louisiana State Licensing Board for Contractors requires a commercial licence for projects of $50,000 or more, a residential licence for a new house or duplex of $50,000 or more, a home improvement licence for residential improvement work of $7,500 to under $50,000, and a licence for electrical, mechanical and plumbing work of $10,000 or more. Since 1 January 2026 residential roofing of $7,500 or more needs a roofing or residential licence, and plumbers are also licensed by the State Plumbing Board of Louisiana until its duties pass to the contractor board on 1 January 2027. Contractor licensing in Louisiana

How to apply for a St. Tammany Parish building permit

1. Confirm the parcel is parish, not one of the municipalities

Eight municipalities lie inside the parish, and most permit their own limits.

2. Establish flood zone and base flood elevation first

These are set by the site, drive elevation and construction requirements, and cannot be retrofitted.

3. Fix design wind criteria for the specific site

Exposure varies between the lakefront and inland parish.

4. Treat drainage approval as critical path

Stormwater and detention frequently decide what a parcel can carry.

5. Confirm who performs commercial plan review

The State Fire Marshal for fire and life safety on all but one- and two-family dwellings, and the local authority or its contracted reviewer for the building code.

6. Verify the contractor credential against the scope

Classification and value thresholds decide which licence applies; residential roofing needs one at $7,500 or more.

In Louisiana the approvals that sit ahead of the building permit, such as historic or design review, zoning and subdivision, most often decide timing. Before filing, ask St. Tammany Parish for the current review turnaround, which bodies review commercial plans (the State Fire Marshal and the local authority or its contracted reviewer), and which approvals must be in hand first. Approvals and corrections in Louisiana

Inspections in St. Tammany Parish

Standard checkpoints include foundation, framing, rough-in electrical, plumbing and mechanical, insulation and final, with a certificate of occupancy required before legal occupancy or use. Elevated construction adds elevation verification, and subdivision work adds drainage and erosion control inspection.

Wind-resistive connections and elevation work are the categories most often concealed too early. Sequence framing, strapping and sheathing inspections so the load path stays observable, and keep elevation certification current.

Do not cover work before the required inspection has been approved. Keep the issued permit, the approved plans, energy documentation, product listings, special-inspection reports and your correction responses available on site.

Plan framing, sheathing and roofing inspections so that wind-resistive connections and opening protection can be seen before they are covered, have elevation verified at the required stages, and keep product approvals and elevation documentation on site. Inspections in Louisiana

Want this handled start to finish?

Get a free quote →

St. Tammany Parish permit search and official resources

Permit records sit with the authority that issued them. In Louisiana that is usually straightforward, because the LSUCC has applied statewide since 2023 and the permitting authority for a given parcel is generally stable — but records predating the statewide code, or predating a municipal incorporation or annexation, may sit elsewhere. If you are buying, refinancing or renovating, ask the St. Tammany Parish Department of Permits & Inspections what it holds for the parcel and whether any permit was closed without a final inspection.

On flood-exposed property the record question is sharper than usual. Prior elevation certificates, floodplain determinations and any history of substantial damage or improvement all bear on what a new project will be required to do, and they are worth obtaining before design rather than during review.

🔍

The technical code is statewide; almost everything else is local. Confirm the current edition and any state amendments with the Louisiana Uniform Construction Code Commission — the 2021 codes have applied since 1 January 2023 (the energy code since 1 July 2023), and the 2024 codes take effect on 1 January 2027 — and confirm fees, portals, submittal requirements, review turnaround and the flood and historic layers with the local department for your filing date. One call to each settles a question that otherwise costs a correction cycle.

These are the primary sources behind this guide. Codes, fee schedules and portal procedures change, and in Louisiana a jurisdiction’s own published packet can lag a code change by months — the adopted ordinance governs, not an un-updated handout. Confirm the position for your filing date.

Frequently asked questions

Does the parish permit inside Slidell or Covington?

No. Slidell, Covington, Mandeville, Abita Springs, Madisonville and Pearl River each permit their own limits, and Folsom has adopted the state code for its own limits. For the Village of Sun, confirm with the village. The parish covers unincorporated territory.

Inspections are where schedules slip.

Get a free quote →

Are flood requirements uniform across the parish?

No. The lakefront and eastern parish face storm surge and coastal flooding while inland areas face riverine and rainfall flooding. Establish the position for the specific parcel.

What most often delays a subdivision project here?

Drainage. Stormwater management, detention, servitudes and subdivision drainage requirements frequently determine what can be built and in what sequence.

Can this jurisdiction impose stricter requirements than the state code?

Only with the state’s approval. Parishes and municipalities must enforce only the Uniform Construction Code (R.S. 37:3737), but a local government that finds the state minimum standards do not meet its needs may set more stringent requirements with the approval of the Louisiana Uniform Construction Code Commission (R.S. 37:3748). What does vary locally is zoning, flood and elevation requirements, historic review, fees, portals and inspection scheduling.

Who reviews my commercial drawings?

On commercial work, usually both. The Office of State Fire Marshal reviews plans for fire and life safety on every building except one- and two-family dwellings (R.S. 40:1574), and the local authority, or a reviewer it contracts with, reviews against the Uniform Construction Code. Establish both routes before you submit.

Does small roofing work still need a licence?

On residential work of $7,500 or more, yes. From 1 January 2026 anyone roofing a residential structure for $7,500 or more must hold the Board’s Residential Roofing or Residential Construction classification (R.S. 37:2156.4, Act 422 of 2025).

Simplify St. Tammany Parish permitting with Alliance Permitting

St. Tammany is a growth parish carrying two different flood exposures and a drainage constraint that decides projects. The technical code is settled statewide; what needs work here is the site.

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Trusted by leading builders, developers, and national contractors — 21+ years of filing in the jurisdictions we write about.

Contractors and builders choose Alliance for St. Tammany Parish because the work is done by people who have stood at the counter:

  • We confirm parish versus municipal jurisdiction across the North Shore.
  • We establish flood zone, elevation and wind criteria for the specific parcel.
  • We treat drainage and detention approval as critical path on subdivision work.
  • We test flood-affected renovation against the substantial improvement threshold.
  • We sequence inspections so connections and elevation work stay observable.

Alliance Permitting is a permit documentation and submission company in Louisiana. We prepare your paperwork, file it correctly and coordinate with the building department through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in St. Tammany Parish sooner?

Let Alliance prepare, file, and track your St. Tammany Parish permits while your crew stays on the job.