Building permits inside Crowley are issued by the City’s Code Enforcement Department at City Hall, 425 North Parkerson Avenue (337-788-4100), and the City Inspector is the chief building inspector. Apply through the City’s iWorQ permit portal or by email to buildingpermits@crowley-la.com. The City code sets the building fee at $0.45 per square foot under roof for a permit with plan review, so a 2,000 sq ft house pays $900.
What needs a permit in Crowley?
The City’s building application covers erecting, repairing, altering, extending, removing, demolishing or moving a building, additions and accessory buildings. Separate City permits are needed for:
Separate permits
- Electrical work
- Plumbing and gas
- HVAC and mechanical
- Fences
- Signs
- Moving a building
- Sewer taps
No permit
- Minor electrical repairs such as replacing switches, fuses, sockets and receptacles (City code)
- Minor plumbing repairs such as fixing leaks in pipes, traps, drains or faucets, or replacing broken fixtures (City code)
Work in the downtown historic district needs Historic District Commission approval before any work starts or a demolition permit is issued.
Who issues building permits in Crowley?
The City of Crowley permits its own territory through the Code Enforcement Department, which enforces the rules on development, use and maintenance of property. Under the City code, the City Inspector is the chief building inspector and enforcement official; the department lists Marty DeRoussel as City Inspector. Unincorporated land around Crowley is permitted by the Acadia Parish Police Jury, not the City.
| Office | Details |
|---|---|
| Code Enforcement | Crowley City Hall, 425 North Parkerson Avenue, Crowley, LA 70526 |
| Phone | 337-788-4100; permit portal questions 337-788-4101 |
| buildingpermits@crowley-la.com | |
| Office hours | Monday to Thursday, 8:00 a.m. to 4:30 p.m.; Friday, 8:00 a.m. to noon |
| Online | iWorQ Citizen Portal (apply and look up permits) |
Short on time to read all of this?
Get a free quote →Those hours are from the City’s Contact page; its Departments page lists Code Enforcement as open Monday to Friday, 8:00 a.m. to 4:30 p.m.
Electrical, plumbing, gas and HVAC permits in Crowley
Each trade needs its own permit, and the City issues trade permits only to subcontractors who hold a City of Crowley licence. A plumbing permit goes only to the property owner or a licensed plumber. Fees from Chapter 5 of the City code:
| Permit | Fee |
|---|---|
| Electrical, residential | $60 permit, plus a $30 inspection fee and $2 per circuit |
| Electrical, commercial | $125 permit, plus a $45 inspection fee and $2 per circuit |
| Electrical service, change of service, trailer or pole service | $25 |
| Electrical sign | $25, plus $7.50 per transformer or circuit |
| Plumbing | $10 for the first fixture, $3 for each additional fixture |
| Plumbing, each additional inspection | $50 |
| Gas inspection permit | $50, plus $50 for each additional inspection |
| Sewer tap | $200 with no street cut; $450 or $800 with a street cut, plus $100 for a concrete street |
A plumbing permit lapses if the work is not completed within 90 days unless the inspector allows longer, and an electrical installation found defective carries an extra $50 inspection fee.
Not sure this scope needs a permit?
Get a free quote →Crowley building permit fees
Building permit fees are set in Section 5-4 of the City code (last changed by Ordinance No. 1449 in November 2012). The online code is current through Ordinance No. 1554, adopted August 18, 2026, and still shows these rates.
| Item | Fee |
|---|---|
| Construction or alteration, permit with plan review | $0.45 per sq ft under roof |
| Construction or alteration, permit without plan review | $0.20 per sq ft under roof |
| Moving a building (within the city or out of it) | $40 |
| Demolition | $50 |
For a 2,000 sq ft house under roof, a permit with plan review is 2,000 × $0.45 = $900, before trade permits. The code does not say which jobs qualify for the lower rate without plan review. Violations of the building rules carry fines of $200, $500 and $1,000 per day for a first, second and third offense.
Documents for a Crowley building permit
The City’s required-documents sheet, posted in the permit portal, splits the list between the permit office and Planning & Zoning:
Residential
- One complete set of plans: site, foundation and floor plans, building elevations and detail drawings
- Electrical, plumbing and HVAC plans (they may be shown on the floor plan)
- Plot plan with setbacks
- Land clearing permit where protected trees are involved
- Drainage plan and flood elevation certificate
- Stamped and sealed survey
- Contractor’s liability and workers’ compensation insurance and state licence
Commercial
- State Fire Marshal review letter
- One complete set of stamped plans, including survey, site, floor, electrical, HVAC and plumbing plans, details and elevations
- Parking and landscape plans
- Flood elevation certificate
- Grading, drainage and paving plans with drainage calculations
- Storm water control and pollution prevention plan
Rather talk it over?
Call 1-855-478-4290 →The application itself asks for the zoning, flood zone, height in stories and feet, square footage, construction material, valuation, lot size and the front, side and rear setbacks.
How to get a Crowley permit: 6 steps
Confirm the lot is inside Crowley and whether it is in the downtown historic district, which needs commission approval first.
The portal asks for a site plan with every building application; the City posts a site plan template.
File the Building Permit Application in the iWorQ portal, or email it to buildingpermits@crowley-la.com; applications are reviewed in the order received.
The electrician, plumber and HVAC contractor each pull their own permit and must hold a City of Crowley licence.
The permit is void if work does not begin within 6 months, or stops for a year.
Notify the City Inspector’s office (337-788-4100) when work is ready; the permit can be tracked in the portal.
Crowley inspections
The City Inspector and Code Enforcement staff carry out inspections. For electrical work, the City code says the inspector inspects within 24 hours of being notified, and wiring that will be hidden must be inspected before it is covered. Plumbing must stay uncovered until it is inspected, and no water may be turned on except for testing until the final plumbing certificate is issued. The gas supplier may not turn on gas to new or altered piping until the City’s gas certificate is issued.
Extra inspections cost $50 each for plumbing and gas, and an electrical installation found defective adds a $50 fee.
Rather not deal with the building department?
Get a free quote →Local Crowley rules that matter
Downtown historic district: the Downtown Historic District Commission reviews restoration, renovation, demolition and new buildings in the district before a permit is issued. Submit six sets of sketches or drawings showing dimensions, facade details, colors where relevant, setbacks and heights compared with neighboring buildings; the commission’s recommendation goes to a City Council committee.
Fences: the fence permit form limits front-yard fences to 3 feet and side or rear fences to 8 feet. On corner lots nothing over 3 feet may stand in the 30-foot sight triangle at the intersection.
Moving buildings: a moving permit takes at least 3 business days to review, and a building taller than 10 feet 6 inches when loaded needs route approval from the utilities.
Flood zones: the City code (Article V) requires a floodplain development permit in special flood hazard areas, and a new or substantially improved home there must have its lowest floor at or above the base flood elevation, certified by an engineer, architect or land surveyor. The flood maps in force are the FIRM dated November 26, 2010.
Trees and drainage: the residential checklist asks for a land clearing permit where protected trees are involved and a drainage plan for new homes.
Louisiana building code
Every Louisiana parish and municipality enforces the state’s Uniform Construction Code (R.S. 37:3737), adopted by the Louisiana Uniform Construction Code Commission: the 2021 International Codes with Louisiana amendments, in force since 1 January 2023, and the 2020 National Electrical Code, with the 2024 codes taking effect on 1 January 2027. A local government may set more stringent requirements only with the Commission’s approval, and the State Fire Marshal reviews plans for fire and life safety on all but one- and two-family dwellings. How the LSUCC works
Want this handled start to finish?
Get a free quote →Official Crowley permit resources
- Louisiana Department of Health onsite wastewater program
- Louisiana State Fire Marshal review codes and rules
- Louisiana contractor licensing threshold statute, R.S. 37:2150.1
- Louisiana code editions and state amendments, May 20, 2026
- Crowley Code Enforcement permit fee sheet (1999 revision, PDF)
- Crowley council minutes, November 13, 2012 (Ordinance 1449 hearing)
- Crowley City Hall contact page: Code Enforcement hours
- Crowley City Code Enforcement building permit email and applications
- Crowley iWorQ permit portal
- Crowley building permit required documents (PDF)
- Crowley Code of Ordinances (Municode)
- Crowley historic district review procedure (PDF)
- Crowley fence permit application (PDF)
Crowley permit FAQs
Inspections are where schedules slip.
Get a free quote →Who issues building permits in Crowley?
The City of Crowley Code Enforcement Department at City Hall, 425 North Parkerson Avenue, 337-788-4100. Land outside the city is permitted by the Acadia Parish Police Jury.
How much is a building permit in Crowley?
$0.45 per square foot under roof for a permit with plan review, or $0.20 without plan review. A 2,000 sq ft house with plan review pays $900, plus trade permits.
Can I apply online?
Yes. The City’s iWorQ portal takes building permit applications with uploaded plans; you can also email buildingpermits@crowley-la.com.
Can any licensed electrician or plumber work in Crowley?
Trade permits are issued only to subcontractors who hold a City of Crowley licence, and plumbing permits only to the owner or a licensed plumber.
How tall can my fence be?
3 feet in the front yard and 8 feet at the sides and rear, with a 3-foot limit in the corner sight triangle. A City fence permit is required.
Is a permit needed for a new roof in Crowley?
Yes. State law (R.S. 37:3737(I), Act 881 of 2026) has every Louisiana city that issues permits permit and inspect roofing and re-roofing; Crowley’s building application covers repairs, so a re-roof is applied for through Code Enforcement.
How long is a Crowley permit good for?
Work must start within 6 months, and the permit is void if work stops for a year.
Simplify Crowley permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Louisiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Crowley sooner?
Let Alliance prepare, file, and track your Crowley permits while your crew stays on the job.