Skip to main content
Municipal GuideLouisianaEast Feliciana Parish

East Feliciana Parish, Louisiana Building Permit Guide

The East Feliciana Parish Building Department in Clinton issues building permits across the parish, and sites inside a town need that town’s approval first.

Authority: East Feliciana Parish Building DepartmentFiling: MyGovernmentOnline or 12064 Marston St., ClintonPhone: 225-683-8577
Chief Building Official
Jeff Williams
Office hours
Monday–Thursday, 7:30 a.m.–5:30 p.m.
New house fee
$0.48 per sq ft under roof ($704 minimum)
Plan review
At least two weeks

In East Feliciana Parish, building permits are issued by the parish Building Department at 12064 Marston Street, Clinton (225-683-8577), with applications taken online through MyGovernmentOnline. A new house is charged $0.48 per square foot under roof with a $704 minimum, a single “umbrella” fee that covers the trade permits and inspections, and plan review takes at least two weeks. Projects inside Clinton, Jackson, Norwood, Slaughter or Wilson need town approval before the parish permit.

What needs a permit in East Feliciana Parish?

The parish code makes it unlawful to build, enlarge, alter, repair, move or demolish a building, change its occupancy, or install or change electrical, gas, mechanical or plumbing systems without a permit from the parish building official. The Building Department publishes permit sheets for:

Residential

  • New site-built homes, additions and remodels
  • Accessory buildings
  • Mobile homes (a Louisiana licensed electrician is required)
  • In-ground pools and generators
  • Roofs (storm damage roofs carry no fee)
  • Demolition and culverts
  • Solar panels

Commercial and utilities

  • New commercial buildings, additions, renovations and tenant fit-outs
  • Commercial roofs
  • Cell towers and equipment swaps
  • Electrical service poles and gas pressure tests
  • Meter releases: a name change, or power off six months or more (certificate of use)

State law (R.S. 37:3737(I), as re-enacted by Act 881 of 2026) requires every parish that issues permits to permit and inspect roofing, which matches the parish’s $150 residential and $200 commercial roof permits. Separately, R.S. 37:3738 keeps a parish from enforcing the code on a detached residential accessory structure of 200 sq ft or less unless it is in a hurricane-prone region with a design wind speed of at least 130 mph; the parish fee sheet does not set out a size limit, so ask the Building Department about a small shed.

Who issues building permits in East Feliciana Parish?

The Building Department, part of the parish government run by the East Feliciana Parish Police Jury, issues the permits and inspects the work. Jeff Williams is the Chief Building Official. The parish code names the building official as the code enforcement officer for unincorporated land, and the department’s own sheets also cover sites in town limits once the town has signed off.

Short on time to read all of this?

Get a free quote →
Who handles permits in each East Feliciana town
PlaceBuilding permits
Unincorporated parishParish Building Department
Town of Jackson (pop. 3,904)Jackson’s code makes the parish building inspector responsible for codes, permits and inspections in the town; the town also charges $1 per 100 sq ft, and parish fees apply
Town of Slaughter (pop. 975)Town Planning & Zoning approval first; the town then faxes a zoning approval permit to the Police Jury, and the parish issues the permit
Town of Clinton (pop. 1,265), Village of Norwood (pop. 261), Village of Wilson (pop. 357)The parish permit sheets require town approval for sites in these town limits; the towns publish no separate building permit rules (Clinton Town Hall: 225-683-5531)
East Feliciana Parish Building Department
DetailInformation
Address12064 Marston Street, Clinton, LA 70722 (mail: P.O. Box 427)
Phone / fax225-683-8577 / 225-683-3100
HoursMonday to Thursday, 7:30 a.m. to 5:30 p.m.
Online filingMyGovernmentOnline

Electrical, plumbing and mechanical work

On a new house or addition the parish permit is an “umbrella” permit: the electrical, plumbing and mechanical work and all inspections are included in the square-foot fee. Work outside an umbrella permit is permitted separately: an electrical permit costs $125 for a residence and $175 for a commercial building, an accessory building’s electrical and plumbing permits are $125 each, and a gas pressure test is $75.

Electrical, plumbing and mechanical contractors need a Louisiana residential licence for home work, and every contractor (building, electrical, plumbing, mechanical, pool, solar, generator or home improvement) registers with the parish each calendar year for $100. Commercial permits need State Fire Marshal approval before the parish will issue them.

East Feliciana Parish permit fees

The Building Department’s posted fee sheets base residential fees on the area under roof and treat each house or addition permit as an umbrella permit that includes all inspections.

Not sure this scope needs a permit?

Get a free quote →
Residential permit fees
ProjectFee
New site-built house$0.48 per sq ft under roof, $704 minimum
Addition or remodel$0.42 per sq ft, $286 minimum
Accessory building$0.17 per sq ft, $191 minimum, plus $125 each for electrical and plumbing
Roof$150 (storm damage: no fee)
In-ground pool / generator$175 / $150
Mobile home$175
Demolition / culvert$85 / $50
Certificate of use after six months or more without power$125 per meter
Commercial permit fees (umbrella permit, per sq ft under roof)
ItemFee
Permit: new construction / additions and renovations$0.08 ($133 minimum) / $0.15 ($77 minimum)
Plan review: up to 5,000 sq ft$0.11, $191 minimum
Plan review: 5,001–10,000 sq ft / over 10,000 sq ft$0.10 / $0.08, $191 minimum
Plan review: renovations$0.11, $191 minimum
Plan review: additions and remodels / tenant fit-out$0.20 ($115 minimum) / $0.08 ($153 minimum)
Inspections: up to 5,000 sq ft / 5,001–10,000 sq ft$0.34 / $0.32, $612 minimum
Inspections: 10,001–20,000 sq ft / over 20,000 sq ft$0.26 ($615 minimum) / $0.21 ($612 minimum)
Inspections: renovations / additions and remodels / accessory buildings$0.19 ($191 min.) / $0.31 ($248 min.) / $0.15 ($153 min.)
Inspections: tenant fit-out$0.08, $153 minimum
Commercial roof$200
Non-emergency call-out inspection$250 minimum

For example, a 2,000 sq ft house under roof costs $960 ($0.48 × 2,000), which is above the $704 minimum and already includes the inspections. The permit is bought before plan review but only becomes valid once review is finished. Fees are paid by check, money order or cash.

Inside Jackson, the town’s own fee of $1 per 100 sq ft is charged on top of the parish fees.

Rather talk it over?

Call 1-855-478-4290 →

Documents for a new house

Before plan review can begin, any land division and zoning must already be approved by the Police Jury or the town, the 911 address must be issued or confirmed (911 Call Center, 225-683-9007), and the parish must complete a floodplain determination. Bring to permitting:

Required at permitting

  • 911 address
  • Town approval, if the site is in town limits
  • Floodplain elevation, where required
  • Proof of ownership: cash sale, act of donation or succession
  • Survey map of the property
  • State-licensed, parish-registered contractor, or a notarized Affidavit Claiming Exemption from Licensure recorded at the Clerk of Court

Plans (two sets)

  • Foundation and joist layouts
  • Plumbing, electrical and HVAC layouts and roof design
  • Front, rear and side elevations
  • Floor plan with room sizes and uses, doors, windows and cabinets
  • Living and total square footage, window and door schedules
  • Plot plan from a legal plat or survey showing servitudes, building lines, setbacks to each property line and the driveway

Plan review takes at least two weeks. One approved set goes back to be kept at the job site, and the parish keeps the other for six months after the project is finished. A commercial project also needs the State Fire Marshal’s approval before the permit is issued.

How to get an East Feliciana Parish building permit

1. Settle zoning and land division

Any subdivision or zoning approval by the Police Jury or the town comes first; in Slaughter that means the town Planning & Zoning meeting.

2. Get the 911 address and flood determination

The 911 Call Center issues the address and the parish makes the floodplain determination.

3. Register the contractors

Each contractor files the parish’s annual registration ($100), or the owner records a licensure exemption affidavit.

4. Apply and pay

Submit through MyGovernmentOnline or at the Marston Street office with two sets of plans, and pay the fee.

5. Wait for plan review

Allow at least two weeks; then collect the approved plans and the inspection board.

6. Build and call for inspections

Post the board and the 911 number, and request each inspection as the work reaches it.

Rather not deal with the East Feliciana Parish building department?

Get a free quote →

Inspections

The Building Department carries out inspections within 48 hours of a request. The permit board must be visible from the street, the 911 address must be posted, and portable toilet and compaction test results must be on file before any work starts.

The residential sequence runs: base flood elevation (story pole marked and certified, where the site is in a flood zone), construction pole, pre-pour plumbing, pre-pour footings and foundation, an open-wall inspection of framing and electrical, plumbing and HVAC rough-ins, insulation (R-13 walls, R-30 ceilings), a TCI/final once the sanitation and water department approvals are in, and an occupancy inspection, which needs blower door test results on file and must be passed before the Certificate of Occupancy. The Elevation Certificate of Completion is due after the slab is poured and before framing starts, and termite certification and duct test results must be on file before the open-wall inspection.

Commercial buildings follow the same steps without the insulation inspection; their occupancy inspection needs the final State Fire Marshal approval and, for food or drink businesses, Department of Health approval.

Local East Feliciana details

Slaughter: the town Planning & Zoning Committee meets on the second Tuesday of each month at 6:30 p.m., and requests must be in by noon on the Friday before. A new home, shed or addition needs proof of ownership, building plans and a plat map (hand-drawn maps are not accepted); the application fee is $40 and a rezoning is $300. Zoning sets minimum home sizes of 1,900 sq ft in R-1, 1,600 sq ft in R-2 and 1,200 sq ft in R-3.

Jackson: of the town permit fee collected for a building in the town historic district, $0.25 of each $1 goes to the town’s historic district commission.

Septic and reconnections: individual sewage systems are permitted by the Louisiana Department of Health, and the parish sheets send septic approvals to the Health Unit (225-683-4148). A house left without power for two weeks or more that is not on a town sewer needs septic approval before the meter is released, and after six months it also needs a Building Official safety inspection.

Want this handled start to finish?

Get a free quote →

Louisiana building code

Every Louisiana parish and municipality enforces the state’s Uniform Construction Code (R.S. 37:3737), adopted by the Louisiana Uniform Construction Code Commission: the 2021 International Codes with Louisiana amendments, in force since 1 January 2023, and the 2020 National Electrical Code, with the 2024 codes taking effect on 1 January 2027. A local government may set more stringent requirements only with the Commission’s approval, and the State Fire Marshal reviews plans for fire and life safety on all but one- and two-family dwellings. How the LSUCC works

Official East Feliciana Parish permit resources

Inspections are where schedules slip.

Get a free quote →

East Feliciana Parish permit FAQs

Who issues building permits in East Feliciana Parish?

The parish Building Department, 12064 Marston Street, Clinton (225-683-8577). Chief Building Official Jeff Williams oversees permits and inspections, including for sites in the towns once the town approves.

How much is a building permit for a new house?

$0.48 per square foot under roof, with a $704 minimum. A 2,000 sq ft house costs $960, and that fee includes the trade permits and inspections.

Do I need town approval?

Yes, if the site is inside Clinton, Jackson, Norwood, Slaughter or Wilson. In Slaughter the town’s Planning & Zoning Committee and board approve the project and notify the Police Jury.

How long does plan review take?

The parish asks applicants to allow at least two weeks.

Can a homeowner build without a contractor?

Yes, with a signed and notarized Affidavit Claiming Exemption from Licensure recorded at the Clerk of Court. Trade work still needs licensed, parish-registered contractors.

Do I need a permit to replace my roof?

Yes. A residential roof permit is $150 and a commercial one $200; there is no fee for storm damage repairs.

When is the office open?

Monday to Thursday, 7:30 a.m. to 5:30 p.m. Applications can also be filed through MyGovernmentOnline.

Simplify East Feliciana Parish permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Louisiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in East Feliciana Parish sooner?

Let Alliance prepare, file, and track your East Feliciana Parish permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about East Feliciana Parish permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.