In unincorporated Page County the zoning and subdivision ordinance requires a building permit before any new construction, and the county says a permit is needed in every case, for homes, equipment and livestock buildings, grain bins and swimming pools alike. Permits come from the Page County Zoning Administrator at the Secondary Roads annex, 210 N. 17th St., Suite A, Clarinda ((712) 542-2510), who is also the County Engineer; Environmental Health issues the $225 septic and $175 well permits.
What requires a permit in rural Page County?
The county’s zoning page is direct: the Page County Zoning and Subdivision Ordinance requires building permits prior to any new construction in the unincorporated county, and a permit is required in any case. Agricultural activity may be exempt from the fees, but farm buildings and other improvements still have to meet the setbacks and other criteria in the ordinance.
Building permit required
- Homes
- Equipment buildings
- Livestock buildings
- Grain bins
- Swimming pools
- Other new construction outside the cities
Separate permits or offices
- Septic systems and wells, permitted by Environmental Health
- Driveway entrances and work in the road right-of-way, permitted by the County Engineer
- Wiring, permitted by the State of Iowa
- Land inside Clarinda, Shenandoah and the other cities
The county warns that building without the permit can bring in the county attorney and lead to construction being shut down or improvements being removed. Complaints about zoning and nuisance violations go to the same office, which investigates and takes enforcement action.
What the county decides and what the state holds
The county’s permit is a land use permit under its zoning and subdivision ordinance: the Zoning Administrator provides and reviews the application forms and issues permits for projects that conform. The county’s web pages name no building code and describe no building inspections, so the permit checks location, use and setbacks rather than construction methods. The rules that reach every rural home in Page County come from Environmental Health: its septic sizing follows the state onsite wastewater rules in chapter 69, and the county’s own environmental ordinance requires an inspection before any rural property is transferred.
Page County building department: who handles permitting
James D. King serves as both Zoning Administrator and County Engineer, so building permits, entrance permits and right-of-way permits are all handled from the Secondary Roads office in the county annex. The office also staffs the Zoning Commission and the Zoning Board of Adjustment, whose members the Board of Supervisors appoints. Environmental Health, run by Coordinator Darin Sunderman from the same 210 N. 17th Street address, handles septic systems, wells, water testing and property-transfer inspections.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Zoning Administrator | Page County Secondary Roads, 210 N. 17th St., Suite A, Clarinda, IA 51632; (712) 542-2510; fax (712) 542-2766; Monday to Friday, 7:00 a.m. to 3:30 p.m. |
| County Engineer (entrances, right-of-way, moving permits) | Same annex office and phone; County Engineer James D. King |
| Environmental Health (septic, wells, transfers) | 210 N. 17th St., Clarinda; (712) 850-1507; coordinator (712) 438-1710; fax (712) 542-5030; Monday to Friday, 8:00 a.m. to 4:30 p.m. |
| Board of Supervisors | 112 E. Main St., Clarinda; (712) 542-5018 |
| Assessor (values new construction) | 112 E. Main St., Clarinda; (712) 542-2516; Monday to Friday, 8:00 a.m. to 4:30 p.m.; Assessor Jason Renander |
| Emergency Management | 210 N. 17th St., Clarinda; 712-850-1040; Coordinator Jill Harvey |
| Electrical permits | The county pages describe no electrical program, so the State of Iowa (DIAL) issues them |
The Engineer’s department also answers petitions and concerns about road condition and drainage, temporary road closures and obstructions in the right-of-way, cleans road ditches to improve drainage and manages roadside vegetation, so a question about a driveway culvert or water along a county road starts there. Its page links Iowa One Call, the state’s call-before-you-dig service, and posts the county’s right-of-way policies and procedures, oversize load permit provisions and the state rule on campaign yard signs (Iowa Code 68A.406).
Cities in Page County
The county’s permit applies to unincorporated land; each city handles construction inside its own limits.
| City | Who handles building permits |
|---|---|
| Clarinda (5,273), the county seat | The city |
| Shenandoah (4,808 here; the city extends into Fremont County) | The city |
| Essex (712), Coin (169), College Springs (169), Shambaugh (158), Braddyville (142) | Each city under its own ordinances |
| Yorktown (59), Northboro (52), Blanchard (29) | Each city under its own ordinances |
Page County permit types
Land use and building permit applications are provided and reviewed by the Zoning Administrator, and the office issues the permit once a project conforms to the ordinance. Appeals of the Administrator’s decisions go to the Zoning Board of Adjustment on the county’s appeal form, and rezonings and ordinance changes go through the Zoning Commission, whose October 8, 2026 agenda is linked on the zoning page, before reaching the supervisors.
Not sure this scope needs a permit?
Get a free quote →Residential permits
A rural house needs the zoning building permit, a septic permit after a percolation test or soil analysis, a well permit for a private well, an entrance permit for the driveway, and an E-911 address sign. Environmental Health sizes each septic system under state rules from the soil type and the number of bedrooms, and the tank size is also set by the number of bedrooms, so the house plan’s bedroom count matters before the permit is issued.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial projects use the same zoning permit. Large energy projects have their own documents on the supervisors’ page: it lists a solar zoning memorandum of understanding, a 2026 proposed solar ordinance (final draft) with the Planning and Zoning Commission’s report and recommendation, an item titled Ordinance 2026-1 Solar, and road use, settlement and decommissioning agreements for the Shenandoah Hills project. The page lists these titles without adoption dates, and the documents themselves could not be read, so this guide does not treat any of them as adopted; ask the Zoning Administrator what applies to a solar project.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Septic. A percolation test ($350) or soil analysis and a $225 permit from Environmental Health.
- Well. A $175 permit and a site assessment before drilling.
- Entrance. The County Engineer reviews and approves entrance permits and installs entrances for new driveways or extensions of existing ones.
- Address. The Engineer’s office takes E-911 sign placement requests.
- Subdivision. New roads in a subdivision need the Engineer’s review and approval.
Page County permit costs and fees
Environmental Health prints its fees on its page. The county’s web pages do not show the zoning permit fee, so this guide cannot give it: ask the Zoning Administrator at (712) 542-2510 before filing. The zoning page says agricultural activity may be exempt from fees.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Zoning building permit | Not published on the county pages; ask the Zoning Administrator. Agricultural activity may be fee-exempt |
| Percolation test | $350 |
| Septic permit | $225 |
| Well permit (private, heat pump or monitoring well) | $175 |
| Real estate transfer inspection | $225, paid by the seller |
| Private well water test (coliform and nitrate) | Free through the Grants to Counties program |
| Abandoned well plugging | Materials reimbursed up to $500 per well and $300 per cistern (state grant) |
A worked example from the Environmental Health fees: a new home on an acreage with its own septic system and well pays $350 for the percolation test, $225 for the septic permit and $175 for the well permit, or $750 before the zoning permit fee. Radon test kits are sold year-round for a small fee.
Trade permits and who may pull them
Page County’s pages describe no county electrical, plumbing or mechanical permits. Electrical permits and inspections outside the cities therefore come from DIAL, and plumbers and HVAC contractors work under their state licenses.
- Septic systems. Environmental Health permits and inspects every system replaced or repaired in the county; each needs prior approval and an inspection before it is completely installed and put into use.
- Wells. New private, heat pump and monitoring wells must be permitted before work starts, and the driller must be state-certified to work in Iowa.
- Utilities. Utility lines and other work in a county road right-of-way need a permit from the County Engineer.
- Oversize loads. Overweight and oversize vehicles on county roads need the Engineer’s permit.
Before a septic system is built or rebuilt the owner must obtain the permit from Environmental Health, and in every case a soil analysis or percolation test sets the length of the drain field. For wells the office posts the Application for Non-Public Water Well Construction and the plugging, reconstruction and rehabilitation record forms. Its staff take water samples themselves, mail them to a certified lab, send the owner a copy of the results and recommend how to correct a contaminated well, and they try to trace the source of any unacceptable result.
Page County also administers the state’s Grants to Counties program, which pays for free water tests and offers cost-share help to correct well construction problems that let contaminants into a well and the groundwater.
Rather not deal with the Page County building department?
Get a free quote →How to apply for a Page County building permit
Make sure the site is outside city limits and ask the Zoning Administrator about the setbacks for its district.
Schedule the percolation test or soil analysis with Environmental Health.
Pay $225 for the septic permit and $175 for the well permit before work starts.
File the entrance permit form and E-911 sign request with the Engineer’s office.
Complete the county’s land use application at the annex, 210 N. 17th St., Suite A.
Call Environmental Health for the septic and well inspections, and the state for wiring.
Review, corrections and what causes delay
Permits are issued only for projects that conform to the zoning and subdivision ordinance, so the setbacks and district rules are checked before a permit is granted, and a disputed decision goes to the Board of Adjustment on the county’s appeal form. On the septic side, soils decide the drain field length, and a site that fails the percolation test or soil analysis needs a different design before the permit is issued. Starting work before the permit is issued risks the county shutting down construction or ordering improvements removed.
Inspections in Page County
The inspections the county describes belong to Environmental Health.
- Septic. Every new, replaced or repaired system must be approved first and inspected before it is completely installed and operating.
- Wells. A site assessment before drilling and an inspection once drilling is complete.
- Property transfers. Under the county’s environmental ordinance every rural property is inspected before it is sold; the septic system is checked for compliance and old solid waste dumping sites are identified. The seller arranges the $225 inspection and gives the report to the buyer before or during negotiations. A contaminated well does not have to be fixed, but a septic system with an illegal discharge or other non-compliance must be upgraded.
- Wiring. State electrical inspectors.
The zoning office enforces its permit by responding to complaints of non-compliance; the county’s web pages describe no framing or final building inspection.
Iowa building code
Page County regulates rural building through its zoning and subdivision ordinance and the Environmental Health septic, well and transfer rules; the county’s web pages name no building code and describe no building inspections. FEMA’s Community Status Book lists Page County as participating in the National Flood Insurance Program, with its first flood insurance rate map, dated April 19, 2017, still the current effective map; the county entered the program’s regular phase on June 7, 2019.
Want this handled start to finish?
Get a free quote →Iowa lets most cities and counties adopt the state building code, another code or none (a city of more than 15,000 must enforce at least the state code), but the energy, accessibility, fire, plumbing, mechanical and electrical rules apply statewide. Iowa rules
Page County permit search and official resources
Zoning permits, appeals and enforcement files are held by the Zoning Administrator at the Secondary Roads annex, and septic, well and transfer inspection records by Environmental Health at the same address, so a parcel’s history is a request to those offices. The Engineer’s office also has section corner, aerial photo and bench mark information and right-of-way records for county road projects open to the public. Parcel data is on the county’s GIS and assessment map; the county says it uses GIS to plan new land developments, determine tax valuations and maintain real estate land records. A finished house or barn also reaches the Assessor, who values new construction or improvements fully or partly according to their state of completion on January 1, and real property is revalued every two years. Page County Public Health, at 210 N. 17th St. ((712) 850-1212), offers lead poisoning prevention screenings, and Emergency Management takes Alert Iowa sign-ups for emergency notices.
- Page County Zoning
- County Engineer and Secondary Roads
- Environmental Health
- Board of Supervisors
- GIS
- Assessor
- Emergency Management
- Public Health
- State electrical permits (DIAL)
- FEMA Community Status Book, Iowa
Inspections are where schedules slip.
Get a free quote →Page County permit FAQs
Do I need a building permit in rural Page County?
Yes. The zoning and subdivision ordinance requires a building permit before any new construction outside the cities, from the Zoning Administrator at (712) 542-2510.
Do farm buildings need a permit?
Yes. Equipment and livestock buildings and grain bins need a permit; agricultural activity may be exempt from the fee but must still meet setbacks.
How much is the Page County zoning building permit?
The county pages do not publish that fee. Ask the Zoning Administrator at (712) 542-2510; agricultural activity may be exempt from fees.
Has Page County adopted a solar ordinance?
The supervisors’ page lists an item titled Ordinance 2026-1 Solar and a 2026 proposed solar ordinance (final draft) with no adoption dates, and the documents could not be read. Ask the Zoning Administrator whether a solar ordinance is in force before planning a solar project.
How much is a septic permit in Page County?
$225, plus $350 for the required percolation test.
How much is a well permit?
$175, and the well must be drilled by a state-certified driller.
Do I need an inspection to sell rural property?
Yes. The county’s environmental ordinance requires a $225 inspection of rural property before transfer, arranged by the seller.
Who approves a new driveway entrance?
The County Engineer, who reviews entrance permits and installs entrances for new driveways and extensions.
Who issues electrical permits?
The State of Iowa (DIAL). Page County’s pages describe no county electrical permit.
Simplify Page County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Iowa. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Page County sooner?
Let Alliance prepare, file, and track your Page County permits while your crew stays on the job.
More Iowa permitting guides
Clay County
Read guide →Jasper County
Read guide →Marshall County
Read guide →Pella Building Permit Guide
Read guide →Pleasant Hill Building Permit Guide
Read guide →Plymouth County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Page County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.