To get a building permit in Boone, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The City of Boone Building Department at City Hall issues building, demolition, electrical, plumbing and mechanical permits inside city limits, online or on printable forms, and inspects the work itself.

Authority: City of Boone Building DepartmentCode: 2015 IBC and IRC, 2021 UPC and IMC, 2023 NECPhone: 515-433-0633
Authority
Building Department923 8th St, City Hall
$300,000 house
$1,546Plus 25% plan review
No permit
Roofing, siding, windowsAnd sheds under 120 sq ft
Inspections
24 hours’ notice515-433-0633

Inside Boone city limits, the Building Department at City Hall, 923 8th St (515-433-0633), issues building, demolition, electrical, plumbing and mechanical permits under the 2015 International Building and Residential Codes, the 2021 Uniform Plumbing and International Mechanical Codes and the 2023 National Electrical Code. A $300,000 house pays a $1,546 building permit on the city’s valuation table plus plan review at 25%, and re-roofing, siding and window replacement need no permit.

What requires a building permit in Boone?

Boone requires a building permit for all construction in the city except replacing small sections of non-critical items, and its fee rule covers permits to erect, construct, enlarge, alter, repair, move, improve, remove, convert or demolish a building or structure. Electrical, plumbing and heating work each need their own permit.

Permit needed

  • New houses, additions and garages
  • Decks and entry porches
  • Basement finishing
  • Accessory buildings of 120 square feet or more, or smaller ones fixed to a concrete slab
  • Fences (fence permit application)
  • Demolition
  • Signs, priced like a building permit
  • Electrical, plumbing and mechanical work, by licensed contractors
  • Driveway, sidewalk and utility work in the public right of way

No permit

  • Re-roofing (shingling)
  • Siding
  • Window replacement
  • Structures under 120 square feet not fixed to a slab, which must still meet setbacks
  • Small repairs to non-critical items

Fences may be 4 feet high in the required front yard, 6 feet in side yards and 10 feet in rear yards, measured from where the city right of way ends rather than the curb, with a 25-foot sight triangle on corner lots in which nothing may stand over 2½ feet. Property lines must be located before a fence goes in, and the finished side faces the neighbor.

What Boone decides and what the state holds

The Building Department lists the 2015 International Building Code, the 2015 International Residential Code, the 2006 International Energy Conservation Code, the 2021 International Mechanical Code, the 2021 Uniform Plumbing Code and the 2023 National Electrical Code as the city’s adopted codes. Zoning, the fee schedule, cross-connection and backflow rules (City Code chapter 94), rental housing and the downtown design guidelines are local; trade licensing and the statewide energy, fire and accessibility rules are state matters.

Boone building department: who handles permitting

Building Official Dave Ades runs the Building Department, which reviews plans, issues permits and inspects construction, with applications circulating to other city offices as the work requires. The Planning & Zoning Commission and the Zoning Board of Adjustment sit under the department.

Short on time to read all of this?

Get a free quote →
City of Boone Building Department contacts
DetailInformation
OfficeCity Hall, 923 8th St, Boone, IA 50036
Phone515-433-0633 (City Hall main line 515-432-4211)
HoursMonday to Friday, 8:00 am to 4:30 pm
ApplicationsOnline through the city site, or printable forms emailed, mailed or dropped off
Rental registrationRental Code office at City Hall, online registration

The city permits only inside its limits. Rural land around Boone is covered in the Boone County guide, where the county issues zoning permits and posts no building code.

Boone permit types

The Building Department posts building, demolition, electrical, plumbing and mechanical applications both online and as printable PDFs, along with fence, sign, floodplain, excavation license and public right-of-way registration forms. A complete set of plans and specifications goes with a building permit, plus a plot plan showing lot dimensions, the new work and every existing building.

Residential permits

The building permit application asks for the zoning district, lot size and the front, rear and side yards, the valuation of the work and whether sewer, water, electric and gas connections are planned. Small additions may not need full drawings, while larger ones need plan, section, foundation and elevation drawings as the Building Official decides. Basement finishes are checked against a list that includes egress windows in every bedroom, tamper-proof outlets every 6 feet, AFCI bedroom circuits, hard-wired smoke detectors, carbon monoxide detectors outside bedrooms and 7-foot-6-inch headroom. Most residential setbacks are 9 feet at the sides and 30 feet front and rear. Owners may apply for their own work; the code standards are the same as for contractors.

An attached garage is treated as part of the house and must meet the house setbacks; the wall it shares with the house may have only a door, either 1⅜-inch solid-core wood or steel with a 20-minute rating, and is covered on the garage side with 5/8-inch Type X drywall up to the roof sheathing unless the ceiling is drywalled. Window wells in front of egress windows need at least 9 square feet of clear opening and 36 inches from the glass, with a fixed ladder or steps once they are deeper than 44 inches.

Commercial permits

Commercial projects follow the same valuation table, with plan review at 25% of the permit fee. Site plan review costs $225 and covers the Development Director’s and Fire Chief’s review, with any City Engineer fees billed back; planned unit developments cost $400, and condominium developments or conversions $250 plus $25 a unit. In the downtown central business district, renovations and new buildings are reviewed with the Building Official against the Downtown Boone Building Design Guidelines, which favor keeping traditional storefront openings on the sidewalk line.

The city’s Sidewalk Improvement Program reimburses part of the cost when owners voluntarily add missing sidewalks or repair poor ones, in residential areas and downtown, until each fiscal year’s funds run out; sidewalks built as part of new development do not qualify.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. The Planning & Zoning Commission meets on the second Monday at 8:30 am when needed; rezonings ($400), plats and planned unit developments go there. Variances go to the Zoning Board of Adjustment ($100 non-refundable petition, with a list of owners within 300 feet), which met in August, September and October 2026.
  • Floodplain. A floodplain development permit requires the lowest floor, basement included, at least 1 foot above the base flood elevation, certified as built.
  • Right of way. Driveways, sidewalks and utility cuts in the street need a public right-of-way excavation permit, and the city posts an excavation license application and a right-of-way registration form for contractors.

Boone permit costs and fees

Building permit fees follow the valuation table in city code section 157.03, posted by the Building Department as “Building Permit Fees” without an adoption date. Valuation is material plus labor, from the contract price or the Building Official’s known construction costs; up to $100,000 the table lists a fee for each step (for example $20 up to $500, $33 at $1,000, $155 at $10,000, $548.50 at $50,000 and $846 at $100,000).

City of Boone building, trade and planning fees
ItemFee
Valuation $1 to $500$20
$600 to $100,000Stepped table: $100 steps to $2,000 ($23 at $600, $60 at $2,000), then $1,000 steps to $846 at $100,000
$100,001.00 to $500,000.00$846.00 for the first $100,000.00 plus $3.50 for each additional $1,000.00 or fraction thereof
$500,001.00 to $1,000,001.00 (as printed)$2,697.00 for the first $500,000.00 plus $3.00 for each additional $1,000.00 or fraction thereof
$1,000,001.00 and up$4,681.00 for the first $1,000,000.00 plus $2.00 for each additional $1,000.00 or fraction thereof
Plan review25% of the building permit fee
Inspection outside normal business hoursFee sheet: $35.00 per hour, two-hour minimum. Schedule of fees: emergency inspection after normal business hours (7 a.m. to 4 p.m.) $70.00 per hour, one-hour minimum
Re-inspectionFee sheet: $35.00 per hour. Schedule of fees: $35.00 per hour, one-hour minimum
Inspection with no fee listedFee sheet: $35.00 per hour, half-hour minimum. Schedule of fees: $35.00 per hour, one-hour minimum
Added plan review for changes to approved plans$35.00 per hour, half-hour minimum (fee sheet)
Electrical permitService $15; circuits $3 / $4 / $6 (single, double, triple pole); range, dryer, disposal, A/C $4; minimum $10
Plumbing permitWater or sewer service $10; drain, stack, vent or fixture $5; water heater $15; minimum $10
Mechanical permitFurnace or boiler $15; cooling or air handler $8; vent or fan $5; minimum $10
Water tap / sewer tap$250 each
Variance, appeal (Board of Adjustment)$100
Zoning compliance letter$25
Preliminary plat / final plat$300 + $5 per lot / $100
Minor subdivision$200 + $5 per lot
Zoning map amendment / planned unit development / right-of-way vacation$400 each
Site plan review$225
Condominium development or conversion$250 + $25 per unit

Rather talk it over?

Call 1-855-478-4290 →

Worked example: a new house valued at $300,000 pays $846 plus 200 × $3.50, or $1,546, and plan review at 25% adds $386.50, for $1,932.50 before trade permits and tap fees. Neither posted sheet carries an adoption date, and they set different after-hours rates and minimum charges, shown above as each prints them; the fee sheet’s hourly rates also apply “or the total hourly cost to the jurisdiction, whichever is the greatest”. Ask the department which applies.

Trade permits and who may pull them

Boone runs its own electrical, plumbing and mechanical permits and inspections, so electrical permits inside the city come from the city. Licensed contractors pull the trade permits for the work they do: each application grants permission to a named licensed master electrician, plumber or mechanical contractor and asks for the state license number. A contractor with any permit outstanding for more than 30 days is not issued new ones.

  • Electrical: 2023 National Electrical Code; inspected with framing before insulation.
  • Plumbing: 2021 Uniform Plumbing Code; underfloor plumbing is inspected before it is covered, and new water and sewer taps cost $250 each.
  • Mechanical: 2021 International Mechanical Code; heating is inspected with framing.
  • Backflow: testable backflow devices are reported on the city’s test report form under City Code chapter 94.

Rental housing has its own program: units are registered online with the Rental Code office, for $100 for a single-family rental, $115 for a duplex or triplex, and $50 plus $10 a unit for four or more under the 2016 fee schedule; failing to register costs $300, and repeat re-inspections rise from $50 to $300. The Property Protection Program offers grants for disconnecting groundwater and stormwater from the sanitary sewer, using plumbers who carry the city’s pilot program endorsement.

Rather not deal with the building department?

Get a free quote →

How to apply for a Boone building permit

1. Find the zoning district

Call the department for the district and setbacks, or order a $25 zoning compliance letter.

2. Locate lot pins

The owner must find the property pins; estimates are not accepted.

3. Prepare plans

Assemble the plans, specifications and plot plan with distances to every lot line.

4. Apply

File the building permit online or on the printable form with the valuation of the work.

5. Trade and right-of-way permits

Licensed contractors file electrical, plumbing and mechanical permits; street work needs an excavation permit.

6. Call for inspections

Give 24 hours’ notice at 515-433-0633.

Review, corrections and what causes delay

Each application circulates through the city offices whose approval the work needs, so zoning, utility and right-of-way questions can hold a permit. Approval is withheld when there is any doubt about where property lines are. Once issued, a permit is void if work does not start within 60 days or stops for 30 days, and it expires one year after issue.

Inspections in Boone

The Building Department’s required inspections, when they apply, are: concrete (footings, forms, foundation walls, slabs and driveway approaches, before pouring); foundation subsoil drainage before backfill; underfloor plumbing before covering; electrical, plumbing, heating and framing before insulation; an energy inspection after insulation and before wall coverings; and a final when all work is done. A certificate of occupancy is issued only after every inspection has passed. Call at least 24 hours ahead.

Lot pins must be visible at the foundation inspection. Deck posthole footings must be at least 42 inches deep and 8 inches across, decks more than 30 inches above grade need guards at least 36 inches high that stop a 4-inch sphere, and steps with three or more risers need a handrail. Detached garages over 1,000 square feet, and all attached garages, need frost footings 42 inches deep and 12 inches wide; smaller detached garages may sit on a 4-inch reinforced slab. Any detached garage must stand at least 5 feet from the house and 2 feet, measured to the roof overhang, from alley lines and from lot lines of adjoining residential lots, and may be no taller than 16 feet. New driveways must be concrete.

Iowa building code

Boone enforces the 2015 International Building and Residential Codes, the 2006 International Energy Conservation Code, the 2021 International Mechanical Code, the 2021 Uniform Plumbing Code and the 2023 National Electrical Code. FEMA’s Community Status Book lists the City of Boone as participating in the National Flood Insurance Program, with its current flood map effective October 21, 2021.

Want this handled start to finish?

Get a free quote →

Iowa lets most cities and counties adopt the state building code, another code or none (a city of more than 15,000 must enforce at least the state code), but the energy, accessibility, fire, plumbing, mechanical and electrical rules apply statewide. Iowa rules

Boone permit search and official resources

Permit and inspection records for a Boone address are held by the Building Department and can be requested there or under Iowa Code chapter 22 from the city clerk. Planning & Zoning Commission and Zoning Board of Adjustment agendas and minutes are posted on their board pages, and the city code is published online by American Legal Publishing.

Inspections are where schedules slip.

Get a free quote →

Boone building permit FAQs

How much is a building permit in Boone?

It follows the valuation table: $846 at $100,000 of work, and $1,546 for a $300,000 house, plus 25% for plan review.

Do I need a permit to re-roof or replace windows in Boone?

No. Re-roofing, siding and window replacement are exempt, along with structures under 120 square feet that are not fixed to a concrete slab.

Can a homeowner pull a permit in Boone?

Yes, for building work, held to the same code standards as contractors; electrical, plumbing and mechanical permits are pulled by licensed contractors.

How tall can a fence be in Boone?

4 feet in the front yard, 6 feet in side yards and 10 feet in the rear yard, measured from the edge of the right of way.

How long is a Boone permit good for?

Work must start within 60 days and not stop for more than 30 days, and the permit expires one year after it is issued.

Who inspects electrical work in Boone?

The city Building Department, on a city electrical permit under the 2023 National Electrical Code.

Does a detached garage need footings in Boone?

Only if it is over 1,000 square feet; smaller detached garages may use a 4-inch reinforced slab.

Simplify Boone permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Iowa. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Boone sooner?

Let Alliance prepare, file, and track your Boone permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Boone permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.