Lowell, Indiana Building Permit Guide

To get a building permit in Lowell, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Town of Lowell’s Building Department at Town Hall, 501 East Main Street, issues improvement location, building and trade permits inside the town, reviews plans, inspects the work and licenses contractors, with fees set by Ordinance 2022-10.

Authority: Lowell Building DepartmentFees: Ordinance 2022-10Phone: 219-696-7794 ext. 223
Authority
Town Building Department501 East Main Street, Lowell
House remodel
$9 per $1,000Of estimated cost, $75 minimum
Processing
Up to 10 business daysWith a complete application
Renewals
Paused to March 1, 2027Current licenses honored

Permits in the Town of Lowell come from the Building Department at Town Hall, 501 East Main Street (219-696-7794, ext. 223), where Tim Henke is the Building Official. Fences, decks, sheds and driveways need an improvement location permit (a deck’s combined zoning and building permit is $75), and under Ordinance 2022-10 a house addition or remodel costs $9 per $1,000 of estimated construction cost, with a $75 minimum.

What requires a building permit in Lowell?

Lowell’s rule is short: any construction inside the town limits must comply with town ordinances, and a needed permit must be bought before construction begins. The department asks owners to call it before building to find out whether a permit is needed, and its forms and fee ordinance show what it permits:

Improvement location permit

  • Fences
  • Decks
  • Sheds
  • Driveways and sidewalks
  • Waterproofing
  • Signs (a $20 sign ILP plus the sign permit)

Building and miscellaneous permits

  • New houses and other new construction
  • Additions, alterations, rehab and remodels
  • Accessory structures, garages, carports and pools
  • Generators, fireplaces, lawn and fire sprinklers
  • Electrical, plumbing and HVAC work
  • Demolition, grade alteration or fill, and curb or street cuts

Driveways must also meet the town’s entrance standards: since Ordinance 2026-09 took effect on June 22, 2026, a two-way entrance or drive may be no more than 36 feet wide (half that for one-way), and the Planning Director sets the width for non-residential drives with more than two lanes.

What Lowell decides and what the state holds

Lowell sets its own permit fees, zoning and subdivision rules (Chapter 155, the Land Use and Development Code), flood hazard rules (Chapter 151), historic preservation rules (Chapter 157) and contractor licensing. The construction standards come from the state, which also requires a Construction Design Release from the Indiana Department of Homeland Security before work starts on a Class 1 structure, a building used by the public, by employees or by three or more tenants, unless 675 IAC 12-6-4 exempts the work.

Lowell building department: who handles permitting

Lowell’s Building Department processes permits, reviews plans, inspects construction, enforces the building code and licenses contractors throughout the town, and it checks each project against the Comprehensive Plan and Zoning Code. The Plan Commission, the Board of Zoning Appeals and the Historic Preservation Commission work alongside it, and a Director of Planning and Development leads the town’s Community Development office. The Lake County Plan Commission handles only unincorporated land outside the town.

Short on time to read all of this?

Get a free quote →
Lowell Building Department
DetailInformation
OfficeTown Hall, 501 East Main Street, P.O. Box 157, Lowell, IN 46356
Phone / fax219-696-7794, ext. 223 / 219-696-7796
Building OfficialTim Henke
Town Hall hoursMonday to Friday, 8:00 a.m. to 4:00 p.m.; townhall@lowell.net
Plan Commission contact219-696-7794, ext. 219
Fee scheduleOrdinance 2022-10, adopted June 13, 2022; the official fee schedule is kept in the Building Department

Lowell permit types

Lowell uses three main applications. The Improvement Location Permit covers fences, decks, sheds, driveways, sidewalks and waterproofing; the Miscellaneous Building Permit covers accessory structures, rehab and remodels, signs, generators, demolition and stand-alone electrical, plumbing and HVAC work; and the New Construction Building Permit Application covers new buildings. Each lists every contractor with a license number, and the miscellaneous form asks for the property tax ID, township, zoning and legal description.

Residential permits

  • New one- and two-family homes are charged $9 per $1,000 of value from the ICC Building Valuation Data, with a $75 minimum, plus electrical, plumbing and HVAC permits and a $50 improvement location permit.
  • Additions, alterations and remodels use the estimated construction cost at the same rate, and an addition carries a $25 improvement location permit.
  • Decks have their own permit form, which asks for two copies of the deck plans and two copies of the property survey. The town’s deck guide puts the combined improvement location and building permit fee at $75, says a plans examiner reviews the plans before the permit issues and that foundation and framing inspections follow, and lists what the plans must show: deck size, joist and beam sizes and spacing, posts and footings, lumber grade, guard and stair details and clearance to overhead wires. It sets a minimum footing depth of 36 inches in Lake County, a live load of 40 pounds per square foot, and bars ledger boards on brick or stone veneer.
  • Pools follow the residential swimming pool code and the town’s electrical guidelines for in-ground and above-ground pools.
  • Owner-occupants sign the owner section of the permit affidavit, described under trade permits.

Commercial permits

Commercial, industrial and multi-family buildings of three or more units pay $10 per $1,000 of value with a $150 minimum, and commercial electrical permits carry a $150 interior wiring or build-out charge. Fire sprinkler permits are $50 and are separate from the fire inspection fees in section 11.095 of the town code. Most commercial buildings are Class 1, so the state design release comes before the town permit.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Improvement location permit. The zoning check comes first, at $50 for a new building and $25 for an addition or accessory structure.
  • Site plan and technical review. Site development plans ($300) go to the Plan Commission, and the town’s Technical Review Committee posts its own agendas.
  • Floodplain. The miscellaneous permit includes a floodplain sign-off, and variances from the floodplain standards go to the Board of Zoning Appeals.
  • Zoning relief. Special uses, variances and administrative appeals go to the BZA at $150 each; zone changes go to the Plan Commission at $300.
  • Fees first. Under section 155.161, no final action is taken on any permit or petition until every fee and charge is paid.

Lowell permit costs and fees

Ordinance 2022-10, adopted by the Town Council on June 13, 2022, replaced the building, sign, BZA and Plan Commission fees in Chapter 11 of the Lowell code. “ICC” values come from the International Code Council’s current Building Valuation Data; “ECV” is the estimated construction cost.

Lowell permit fees (Ordinance 2022-10)
ItemFee
One- and two-family or agricultural: new construction$9 per $1,000 (ICC); $75 minimum
One- and two-family: additions, alterations, remodels$9 per $1,000 (ECV); $75 minimum
Multi-family (3+), commercial, industrial$10 per $1,000 (ICC for new, ECV for alterations); $150 minimum
Improvement location permit$50 new building; $25 addition or accessory structure; $20 per sign
Electrical, new residential$100 (100 amp) or $125 (200 amp) plus $100 interior wiring; $0.25 per amp over 200; temporary pole $50
Electrical, residential alterationsService change $100 or $125 ($50 more with miscellaneous wiring); branch circuit or NIPSCO inspection $75
Plumbing$70 plus $5 per fixture (residential); $75 plus $5 per fixture (commercial, multi-family)
HVAC$75 per unit (residential); $100 per unit (commercial)
PoolsAbove-ground $150; temporary or inflatable $50; in-ground $50 plus $7 per $1,000
Fence, deck or shed$50 each
Demolition / re-inspection / certificate of occupancy$25 / $50 / $25 per unit
One-time permit renewal20% of the original fee plus $25 per remaining inspection
Signs$50 plus $0.50 per sq ft
BZA petition / zone change / site plan$150 / $300 / $300

Rather talk it over?

Call 1-855-478-4290 →

Worked example: a $40,000 room addition to a house is 40 × $9, or $360, plus the $25 improvement location permit for an addition, for $385 before the electrical, plumbing and HVAC permits. New homes are priced on the ICC valuation table rather than on the contract price. For a deck, the $50 deck permit and the $25 accessory improvement location permit add up to the $75 the town’s deck guide quotes; the July 2020 improvement location permit form, which predates the ordinance, still prints a $50 fee.

Trade permits and who may pull them

Contractors working in Lowell must hold a town contractor license, and the permit affidavit must be signed by the license holder.

  • License types. General Combination, General Residential and specialty licenses, from electrical, roofing and concrete to fencing, paving and low voltage; the application refers to a list showing which specialties need a test, and asks for the Lake County license holder or test applicant.
  • Requirements. A $5,000 Unified License Bond recorded with the Lake County Recorder, worded to the Lake County Board of Commissioners and the cities and towns in the county; insurance of $500,000 per occurrence or a $1 million umbrella naming the Town of Lowell; workers’ compensation or a state waiver; photo ID; a notarized application and a $100 fee. Bond and insurance must state the scope of work.
  • Plumbers and licensed well diggers holding a valid Indiana license take no test but must register with the town’s licensing division.
  • Renewals in 2026–27. The department has paused all license renewals until March 1, 2027; current licenses are honored until then, provided bonds and insurance stay current.
  • Owner-occupants may do the work on the home they live in or will live in by attesting that they alone will do it. The affidavit warns that using any helper who is not licensed by the Unincorporated Lake County Contractors Licensing Board under Ordinance 1682 violates the licensing ordinance and stops construction.

Rather not deal with the building department?

Get a free quote →

How to apply for a Lowell building permit

1. Call before you build

Ask the Building Department at 219-696-7794, ext. 223, whether the job needs a permit and which form to use.

2. Settle zoning

Check the zoning district, setbacks and driveway width, and file any BZA or Plan Commission petition first.

3. License the contractors

Every contractor listed must hold a current Lowell license, or the owner signs the owner-occupant affidavit.

4. Complete the application

The ILP, miscellaneous or new construction form, with the project cost, contractor license numbers and site plan.

5. File at Town Hall

Submit the package at 501 East Main Street or by mail to P.O. Box 157.

6. Pay before work starts

Fees from Ordinance 2022-10 are paid before the permit is released.

Review, corrections and what causes delay

The town’s forms say permits take up to ten business days to process when all the required information is supplied on time. The checks behind that are the contractor license, the site plan, plan review and, where it applies, the floodplain review. The forms ask for every contractor’s license number and the property’s legal description, a contractor’s bond must be recorded before the license issues, and a petition to the BZA or Plan Commission adds a public hearing at the board’s monthly meeting.

Inspections and certificates in Lowell

The Building Department inspects the work it permits; call ext. 223 at 219-696-7794 about inspection timing. A failed or repeat inspection costs $50. If a permit runs out before the work is finished, the fee ordinance allows one renewal for 20% of the original fee plus $25 for each inspection still needed to finish the project.

The fee ordinance charges $25 per unit for a certificate of occupancy, and the miscellaneous application carries a C.O. fee line. Electrical work that needs a NIPSCO inspection carries its own $75 town fee.

Indiana building code in Lowell

Lowell’s local rules are in its Code of Ordinances, published by American Legal Publishing, and the town also posts its code titles, including Chapter 151 on flood hazard areas, in its online document center. FEMA’s Community Status Book lists the Town of Lowell (community 180137) as participating in the National Flood Insurance Program, with flood maps effective January 18, 2012.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Want this handled start to finish?

Get a free quote →

Lowell permit search and official resources

For the status of a Lowell application or the record of a past permit, contact the Building Department at ext. 223 or Town Hall at townhall@lowell.net. Plan Commission, BZA and Technical Review Committee agendas and minutes, and town ordinances, are posted in the document center.

Inspections are where schedules slip.

Get a free quote →

Lowell building permit FAQs

Do I need a permit for a fence, deck or shed in Lowell?

Yes. Each needs a permit; the fee ordinance charges $50 for the fence, deck or shed permit plus $25 for the accessory-structure improvement location permit, which the deck guide gives as a $75 total for a deck.

How much does a permit for a home remodel cost?

$9 per $1,000 of estimated construction cost with a $75 minimum, so a $40,000 addition is $360 plus a $25 improvement location permit.

How long does a Lowell permit take?

Up to ten business days when the application is complete and every required item is supplied on time.

Can I do the work on my own house?

Yes, if you live in it or will live in it and sign the owner-occupant affidavit; the affidavit says anyone who helps must be licensed by the Unincorporated Lake County Contractors Licensing Board.

Can I renew my contractor license now?

No. Renewals are paused until March 1, 2027, and licenses that are valid now stay valid until then as long as bonds and insurance are current.

How wide can my driveway entrance be?

No more than 36 feet for two-way traffic, or half that for one-way, under Ordinance 2026-09.

When do the Plan Commission and BZA meet?

The Plan Commission meets at 7:00 p.m. on the second Thursday of the month. The BZA’s page gives the same Thursday at 6:00 p.m., although the town calendar lists its December 2026 meeting on December 3.

Simplify Lowell permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Lowell sooner?

Let Alliance prepare, file, and track your Lowell permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Lowell permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.