To get a building permit in Plainfield, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

In the Village of Plainfield, Illinois, the Building Department at the Public Works Facility on Coil Plus Drive issues building permits through the village’s Permitting & Licensing Portal.

Authority: Building DepartmentFiling: Permitting & Licensing PortalPhone: 815-439-2937
Office
14400 S. Coil Plus Dr.Public Works Facility
Hours
7:30 a.m.–4:00 p.m.Monday to Friday
Homeowner guides
13 project guidesPatios, decks, fences, pools, roofs, sheds and more
Commercial fees
$0.04 per cu ftFirst 100,000 cu ft; schedule updated June 1, 2025

The Village of Plainfield in Will and Kendall counties issues its own building permits through its Building Department, which works from the Public Works Facility at 14400 S. Coil Plus Drive (815-439-2937, building@goplainfield.com) and is led by Building Official Mark Dudash. Permits are applied for through the village’s Permitting & Licensing Portal, and the department posts “Before You Build” instruction guides for common homeowner projects. The office is open Monday to Friday from 7:30 a.m. to 4:00 p.m. For commercial work the village posts a Schedule of Costs for Development, updated June 1, 2025, that prices new buildings by cubic foot, from $0.04 for the first 100,000 cubic feet, plus a $200 plan review fee.

What requires a building permit in Plainfield?

Plainfield’s Building Department reviews plans, issues building permits and enforces the village’s construction codes inside the village. Its “Before You Build” instruction guides cover the projects homeowners take on most often, and the codes it uses reach every trade: building, electrical, mechanical, plumbing and fire prevention.

Projects with a homeowner guide

  • Brick paver patio
  • Concrete patio
  • Deck
  • Driveway
  • Fence
  • Gazebo or pergola
  • Shed
  • Chicken coop
  • Hot tub
  • Pool, with separate safety barrier guidelines for residential pools
  • Roof
  • Siding

Other work under village codes

  • New houses, additions and remodels (2021 International Residential Code)
  • Commercial buildings and alterations (2021 International Building and Existing Building Codes)
  • Electrical work (2020 National Electrical Code)
  • Heating, cooling and gas piping (2021 mechanical and fuel gas codes)
  • Plumbing (Illinois Plumbing Code with a Village of Plainfield IDPH amendment)

What Plainfield decides and what the state holds

The village picks its codes and amends them; its list of currently adopted codes was last updated March 17, 2026. The 2021 Village of Plainfield Building Code is listed alongside both the building codes and the electrical code, and the mechanical and fuel gas codes carry Village of Plainfield amendments. Two codes come from the state: plumbing follows the 2014 State of Illinois Plumbing Code with its most recent amendments, to which Plainfield adds a village IDPH amendment, and accessibility follows the current Illinois Accessibility Code. State law also requires the department to review plans for energy conservation under the most recent International Energy Conservation Code with Illinois amendments, for both houses and commercial buildings.

Short on time to read all of this?

Get a free quote →

Plainfield building department: who handles permitting

The Building Department handles building permits; Code Enforcement, listed at the same facility, handles complaints about property and code violations. The latest Census estimate places 46,653 residents in the Will County part of the village and 3,390 in the Kendall County part. Land outside the village limits is permitted by the county: the Will County Land Use Department or Kendall County’s Planning, Building and Zoning Department (see the Will County and Kendall County guides).

Plainfield permit contacts
DetailInformation
Building DepartmentPublic Works Facility, 14400 S. Coil Plus Drive, Plainfield, IL 60544; 815-439-2937; building@goplainfield.com
Building OfficialMark Dudash, 815-230-2047
Code Enforcement815-267-7212; codeenf@goplainfield.com; online complaint form
HoursMonday to Friday, 7:30 a.m. to 4:00 p.m.
Village Hall24401 W. Lockport Street, Plainfield, IL 60544; 815-436-7093
Plainfield Fire Protection District, Fire Prevention BureauAdministration / Station 1, 23748 W. 135th Street; 815-436-5335; fireprevention@plainfieldfpd.com; Monday to Friday, 8 a.m. to 3 p.m.
Oswego Fire Protection DistrictAdministration at Station 1, 3511 Woolley Road, Oswego; non-emergency 630-554-2110; Station 4 is at 27100 W. 127th Street, Plainfield, IL 60544

Plainfield permit types

All permit applications start in the Permitting & Licensing Portal. For the most common home projects, the department’s “Before You Build” guides explain the village’s requirements before you file, so read the one for your project first.

Residential permits

  • Outdoor living. Brick paver patios, concrete patios, decks, gazebos and pergolas each have a guide.
  • Fences and driveways. Separate guides for each.
  • Sheds and chicken coops. Accessory structures with their own guides.
  • Pools and hot tubs. A pool guide and a hot tub guide, plus the village’s safety barrier guidelines for residential pools.
  • Roofs and siding. Each has its own guide.
  • New homes, additions and remodels. Reviewed under the 2021 residential code with Plainfield’s amendments and checked for energy code compliance.

Commercial permits

Commercial buildings, additions and alterations are reviewed under the 2021 International Building and Existing Building Codes, the 2021 Village of Plainfield Building Code, the current Illinois Accessibility Code and the commercial provisions of the energy code. Fire protection follows the 2021 International Fire Code with the latest Plainfield or Oswego fire district amendments, and the village’s code list notes that fire protection inspections are required for all commercial, industrial and institutional buildings and for residential buildings of more than two units. The commercial cost schedule adds that buildings of 2,000 sq ft or more must have a fire sprinkler system.

Not sure this scope needs a permit?

Get a free quote →

Fire protection systems go through the fire district as well as the village. In the Plainfield Fire Protection District, a fire alarm, sprinkler or suppression system cannot be installed or modified until the Fire Prevention Bureau has reviewed and approved the design, for new construction, tenant improvements, additions and retrofits alike. Submittals are uploaded on the district’s plan review page with complete plans, calculations and cut sheets: device layouts, voltage-drop and battery calculations and the designer’s NICET certification for alarms; working plans, hydraulic calculations and a flow test no more than 12 months old for sprinklers; and separate lists for underground fire mains and kitchen hood or special suppression systems. Incomplete submittals are returned. Plan review fees are due at submittal, and the bureau gives its current fee schedule on request. Once approved, a permit is issued, followed by rough-in and final inspections. The bureau also issues operational permits for hot work, hazardous materials, open burning and assembly events.

What comes before the building permit

  • Village or county. Confirm the parcel is inside Plainfield; unincorporated Will or Kendall County land goes to that county.
  • Homeowner guide. Read the guide for your project before you apply.
  • Energy design. Plans must show energy code compliance, because the state requires the department to review it.
  • Driveways on county roads. Where a lot fronts a Will County highway, the county Division of Transportation issues the access permit and sorts it by daily traffic: no more than 20 trips for a house or other low-traffic use, no more than 50 for small apartment or office sites, and over 50 for subdivisions and commercial developments.
  • Floodplain. Plainfield participates in the National Flood Insurance Program, so building in a mapped flood hazard area brings floodplain review; ask the department before you design.

Plainfield permit costs and fees

The only fee document on the Building & Code Enforcement page is the Schedule of Costs for Development: Commercial New and Build-outs, updated June 1, 2025. It covers all nonresidential buildings, including commercial, industrial and office buildings. No residential permit fee schedule is posted, so ask the Building Department at 815-439-2937 or building@goplainfield.com for the fee on a house, addition, deck or other home project.

Rather talk it over?

Call 1-855-478-4290 →
Plainfield commercial schedule of costs (updated June 1, 2025)
ItemFee
New nonresidential building: first 100,000 cu ft$0.04 per cu ft
New nonresidential building: 100,001 to 200,000 cu ft$0.02 per cu ft
New nonresidential building: 200,001 to 500,000 cu ft$0.01 per cu ft
New nonresidential building: over 500,000 cu ft$0.006 per cu ft
Commercial build-outs, alterations, conversions, remodeling and structural repairs50% of the cubic content fee, minimum $200
Plan review, each project$200
Electrical or plumbing inspection$50 each
Site inspection$75 each
Re-inspection: rough or final building / all others$60 / $50, doubling each time
Temporary certificate of occupancy$60
Water meter: 1 in / 1.5 in / 2 in / 3 in / 4 in compound$500 / $1,500 / $1,700 / $2,200 / $3,500
Water connection: 1 in / 1.5 in / 2 in / 3 in / 4 in / 6 in meter$3,305 / $3,810 / $4,280 / $4,775 / $5,250 / $6,230
Sewer tap$1,200 per population equivalent (100 gallons a day), minimum 3 per business ($3,600)
Fire sprinkler tap$3,000

Worked example. A new 80,000 cu ft commercial building sits inside the first band: 80,000 × $0.04 = $3,200, plus the $200 plan review fee, for $3,400 before inspections, water and sewer charges. A build-out of an existing 80,000 cu ft space pays half the cubic content fee, $1,600, plus $200 for plan review.

Re-inspection fees are collected at the time of the first certificate of occupancy and double with each repeat. Water meters come with couplings and a remote reader, and the village supplies backflow preventers up to 1 inch (the $70 cost is already in the meter price); owners provide larger backflow devices. In a plaza, each business unit pays its own population-equivalent sewer tap fee.

Rather not deal with the building department?

Get a free quote →

Trade permits and who may pull them

Plainfield applies the 2020 National Electrical Code with the village’s 2021 building code amendments to electrical work, the 2021 mechanical and fuel gas codes with village amendments to heating, cooling and gas work, and the state plumbing code with the village IDPH amendment to plumbing; the department publishes code highlights for electrical, HVAC and plumbing work. Plumbing must be done by a plumber licensed through the Illinois Department of Public Health, and roofing contractors are licensed by the state through the Illinois Department of Financial and Professional Regulation. The building pages describe no village contractor license or registration rule.

How to apply for a Plainfield building permit

1. Confirm the village has the parcel

Plainfield permits inside its limits; county land goes to Will or Kendall County.

2. Read the guide

Open the “Before You Build” guide for your project, if there is one.

3. Prepare the plans

Draw the work to the 2021 codes and Plainfield amendments, with energy code details.

4. Apply in the portal

Create an account in the Permitting & Licensing Portal and submit the application.

5. Answer review comments

Respond to the Building Department’s plan review, including the energy review.

6. Pay and build

Pay the permit fee and arrange the inspections the permit calls for.

Review, corrections and what causes delay

The department does not post a review time. Energy code review is required by state law, so include the energy details from the start, and use the homeowner guide where your project has one. Call the Building Department at 815-439-2937 during office hours with questions about a pending application.

Inspections and certificates in Plainfield

Inspections of permitted work are arranged with the Building Department. Its page does not set out booking times or inspection stages, so ask how to schedule when the permit is issued, or call 815-439-2937 between 7:30 a.m. and 4:00 p.m. on weekdays. On commercial projects, electrical and plumbing inspections are $50 each and site inspections $75; a failed rough or final building inspection costs $60 to re-inspect and other re-inspections $50, with the fee doubling each time and all of it due when the first certificate of occupancy is issued. A temporary certificate of occupancy is $60.

Fire protection inspections are required for every commercial, industrial and institutional building and for residential buildings of more than two units, under the 2021 International Fire Code as amended by the Plainfield or Oswego fire district. The 2021 International Property Maintenance Code on the village’s list applies to existing buildings, and Code Enforcement at 815-267-7212 takes complaints about suspected violations.

Want this handled start to finish?

Get a free quote →

Illinois building code in Plainfield

The village’s list of currently adopted codes, updated March 17, 2026, names the 2021 International Building, Residential, Existing Building, Swimming Pool and Spa, Mechanical, Fuel Gas, Fire and Property Maintenance Codes and the 2020 National Electrical Code, with village amendments to the property maintenance, electrical and mechanical codes; the 2014 Illinois Plumbing Code with village IDPH amendments; and the current state energy and accessibility codes. FEMA’s Community Status Book lists the Village of Plainfield (community 170771) as participating in the National Flood Insurance Program since November 17, 1982, with flood maps dated February 15, 2019; the village is not in the Community Rating System.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Plainfield building permit FAQs

Where do I apply for a building permit in Plainfield, Illinois?

Through the village’s Permitting & Licensing Portal; the Building Department is at 14400 S. Coil Plus Drive, 815-439-2937.

How much is a commercial building permit in Plainfield?

New nonresidential buildings pay $0.04 per cubic foot for the first 100,000 cubic feet, with lower rates above that, plus a $200 plan review fee; build-outs pay half, with a $200 minimum.

Are residential permit fees published?

No residential fee schedule is posted on the building page; ask the Building Department for the fee on your project.

Is this the Plainfield Building Department in Indiana?

No. This is the Village of Plainfield, Illinois, in Will and Kendall counties.

Does Plainfield have guidance for decks, patios and pools?

Yes. Its Before You Build guides cover decks, patios, pools and more, and it publishes safety barrier guidelines for residential pools.

Which electrical code does Plainfield use?

The 2020 National Electrical Code with Village of Plainfield amendments.

What are the Building Department’s hours?

Monday to Friday, 7:30 a.m. to 4:00 p.m.

How do I report a code violation?

Call Code Enforcement at 815-267-7212 with the address, email codeenf@goplainfield.com or file the online complaint form.

Inspections are where schedules slip.

Get a free quote →

Plainfield permit search and official resources

Your own applications and permits are tracked in the Permitting & Licensing Portal. For other permit records on a property, ask the Building Department at 815-439-2937 or building@goplainfield.com.

Simplify Plainfield permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Plainfield sooner?

Let Alliance prepare, file, and track your Plainfield permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Plainfield permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.