Outside the City of Thomasville, building permits in Thomas County come from the County’s Inspections and Planning department at 227 West Jefferson Street, Thomasville (229-225-4120), including for sites inside Meigs, Ochlocknee, Coolidge and Boston. Every job starts with a Land Use Compliance Form, plan review takes about 5–7 days, and a new house also pays a development impact fee of $1,614.91 when the permit is issued.
What requires a permit in Thomas County?
All residential and commercial buildings in the unincorporated county must meet the building code (County Code Sec. 18-87), and the Building Inspections office handles plan submittals and permits for them. The County publishes separate requirements for:
Permit required
- New homes and residential construction
- Commercial construction, with extra site approvals
- Manufactured home placement or relocation
- Electrical, mechanical and plumbing permits for manufactured homes
- Work by an owner acting as their own contractor
Exempt from the building code
- Non-residential farm buildings used by the owner to store farm tools, equipment or crops, or to house livestock (they can be inspected on request for the scheduled fee)
Utilities may not provide temporary electric, water or gas service for construction until a permit has been issued, or permanent service until the certificate of occupancy is issued (Sec. 18-89).
Short on time to read all of this?
Get a free quote →Who handles permitting in Thomas County?
| Item | Thomas County Inspections and Planning |
|---|---|
| Covers | Unincorporated Thomas County, plus building inside Meigs, Ochlocknee, Coolidge and Boston |
| Office | 227 West Jefferson Street, Thomasville, GA 31799 (P.O. Box 1173) |
| Phone and fax | 229-225-4120 · fax 229-227-1171 |
| Director | Kendall C. Gay, Inspections and Planning Director |
| 911 addressing | Same building, 229-227-3242 |
| Well and septic permits | Thomas County Health Department, same building, 229-226-4241 ext. 7360 |
Inspections and Planning covers building inspections, code enforcement, planning and zoning, and business licences. For a project inside Meigs, Ochlocknee, Coolidge or Boston, the Land Use Compliance Form comes from that city’s City Clerk, and the rest of the process runs through the County office.
City of Thomasville: inside Thomasville city limits, the City’s own Building Department issues building and trade permits.
Pavo and Barwick (both partly in Thomas County): the County’s permit requirements set out the city compliance step only for Meigs, Ochlocknee, Coolidge and Boston and do not mention these two cities. Pavo City Hall lists permits among its services and helps residents with permits for their projects (1010 W. Harris Street, 229-859-2110). No source says who issues building permits in Barwick; contact City Hall before applying.
Contractors: the contractor must hold a Georgia licence and be registered with the County office before the permit is issued. An owner building on their own property needs no contractor licence but must still get the permit and follow the code.
Thomas County permit and impact fees
Building permit and inspection fees are set by the Board of Commissioners (Sec. 18-88), and the schedule is not posted on the County website. All fees, including any impact fee, are collected when the building permit is issued. Plans sent as a PDF are printed in the office for an additional fee, payable when the file is submitted.
New development outside Thomasville also pays a development impact fee under the County’s Impact Fee Ordinance. For each single-family house, apartment, condominium or townhouse it is $1,614.91, made up of parks and recreation, fire, sheriff’s office, EMS and 911 shares plus a 3% administration charge.
Not sure this scope needs a permit?
Get a free quote →Impact fees do not apply to rebuilding the same number of units after demolition or fire, remodeling, replacing a house on the same lot, home additions that do not add a unit, or accessory uses such as decks, patios and pools. Impact fees for office, retail and industrial development have been waived since August 15, 2014.
Electrical, plumbing and mechanical work
Trade work is reviewed with the building permit: the residential plan set must show the electrical plan including the service, the location of the mechanical units and the insulation. Manufactured homes need their own electrical, mechanical and plumbing permits. Building, plumbing, electrical, heating and air contractors and gasfitters licensed under the County code must post a surety bond, and a contractor who fails to correct defective work after notice gets no further permits. Commercial plans need Fire Marshal approval before they are accepted.
Plan submittal checklist
Residential plans
- Approved Land Use Compliance Form and approved septic or well permits
- Site plan and elevations showing grade and slope
- Floor plan with heated and unheated square footage
- Foundation drawings (slab or crawlspace) and foundation vent calculations
- Electrical plan with service, and mechanical unit locations
- Insulation description and lumber specifications
- Door and window schedule with emergency egress, and stair rise and tread
- Smoke detector locations, wall sections, finish schedule and attic access
Commercial plans add
- Approved soil erosion plan
- Parking plan and driveway approvals
- Landscaping and buffer approval
- Sign application
- Fire Marshal approval
- Public Works approval
- Two complete sets of plans
Rather talk it over?
Call 1-855-478-4290 →Plans are submitted on 36 by 24 inch sheets, or as a PDF that the office prints for a fee. A copy of the survey is needed if the property has been surveyed. Plan review takes about 5–7 days, and it will not be finished until everything on the submittal list is in.
How to apply in Thomas County: 6 steps
Building Inspections staff issue it at the office; in Meigs, Ochlocknee, Coolidge or Boston, bring the form from the City Clerk.
Take the form to the 911-addressing office in the same building, which assigns or verifies the address by GPS.
The Health Department, also in the building, issues well and septic permits; on an existing lot, the existing septic system must be approved for the new building.
Turn in the plan set with the 911 validation and septic approval; plans are not accepted without them.
After approval, the permit is issued to the licensed contractor or homeowner, the forms are signed and all fees are paid.
Utilities are connected for good only after the certificate of occupancy.
Inspections and certificates of occupancy
Building Inspections inspects the work under the adopted codes. A certificate of occupancy is not issued until the board of health has approved the finished water supply and sewage system (Sec. 18-90), and permanent electric, water and gas service cannot be connected before it.
Rather not deal with the Thomas County building department?
Get a free quote →For manufactured homes, the final inspection covers the HUD label, sound floors, walls and roof, working plumbing fixtures and water heater, safe heating with no unvented heaters, a bonded electrical system, an egress window in every bedroom and smoke detectors in each bedroom and the kitchen. The inspector lists any deficiencies for the owner to fix. Once the home passes, the County calls the power company to connect service, and skirting of masonry, metal, vinyl or treated wood must be finished within 30 days.
Local Thomas County details
Manufactured homes: placement needs the Land Use Compliance Form, an application for placement and the manufactured home permit and affidavit, plus proof from the Tax Assessor that the current year’s taxes are paid. Any impact fee is collected with the permit fee.
Zoning: the Land Use Compliance Form records the parcel’s zoning classification and the setbacks that apply under the County’s land use standards ordinance.
Appeals: the County has a Building Inspections Board of Appeals for decisions under the building code.
Georgia building code
Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes
Thomas County permit search and official resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
Want this handled start to finish?
Get a free quote →- Thomas County — Adopted Building Codes Ordinance
- Thomas County — Building Codes
- Thomas County — Building Permit Requirements
- Thomas County — Inspections, Planning, Zoning & Code Enforcement
- Thomas County construction plan submittal information
- Thomas County Development Impact Fee Ordinance
- Thomas County manufactured home placement rules (Chapter 58)
- Thomas County land use standards (zoning) ordinance
Thomas County permit FAQs
Who issues building permits in Thomas County?
Thomas County Inspections and Planning, 227 West Jefferson Street, Thomasville (229-225-4120), for unincorporated areas and for building inside Meigs, Ochlocknee, Coolidge and Boston. The City of Thomasville issues its own permits.
Inspections are where schedules slip.
Get a free quote →How long does plan review take in Thomas County?
About 5–7 days, and only once the plans arrive with the 911 address validation and septic approval.
How much are impact fees on a new house?
$1,614.91 per dwelling outside Thomasville, covering parks, fire, sheriff, EMS and 911, collected when the building permit is issued.
Can a homeowner pull a permit?
Yes. An owner acting as their own general contractor needs no contractor licence but must get the permit and build to code; the permit can be issued to the homeowner.
Do farm buildings need a permit?
Non-residential farm buildings used to store tools, equipment or crops, or to house livestock, are exempt from the building code; the owner can still ask for an inspection for the scheduled fee.
When can the power be turned on?
Temporary construction power needs an issued permit, and permanent service needs the certificate of occupancy.
Simplify Thomas County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Thomas County sooner?
Let Alliance prepare, file, and track your Thomas County permits while your crew stays on the job.
More Georgia permitting guides
This guide is provided by Alliance Permitting for general information about Thomas County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.