Jones County, Georgia Building Permit Guide

Jones County Planning and Zoning serves both Jones County and the City of Gray and provides an online permitting portal for building, zoning, land-disturbance, sign and related development approvals.

Authority: Jones County Planning and ZoningCode: Georgia State Minimum Standard Codes (2024)
Authority
Jones County Planning and ZoningJones County and City of Gray
Apply
iWorQ online permitting portalOr 166 Industrial Blvd., Gray
New home fee
$0.16 per heated sq ft$0.06 unheated, $12 per bath
Phone
478-986-5117zoning@jonescountyga.org

Jones County Planning & Zoning, at 166 Industrial Boulevard in Gray, issues building, trade, land disturbing and sign permits for both unincorporated Jones County and the City of Gray, with applications through the County’s iWorQ online portal. The posted fee schedule charges a new home $0.16 per heated square foot, $0.06 per unheated square foot and $12 per bathroom.

What requires a permit in Jones County?

County code requires a permit from the building official before anyone builds, enlarges, alters, repairs, moves or demolishes a building, changes its occupancy, or installs or alters electrical, gas, mechanical or plumbing systems. The fee schedule adds that no building permit is needed when construction costs less than $1,000, unless an inspection is needed.

Residential

  • New homes, including homes with mother-in-law quarters and barndominiums
  • Additions, including additions to mobile homes, and renovations
  • Accessory buildings: garages, carports, workshops, pool houses, pole barns, shipping containers
  • Swimming pools
  • Manufactured homes
  • Single trade permits: electrical, plumbing or HVAC

Commercial and site

  • New commercial buildings, additions, renovations and towers
  • Demolition and moving structures
  • Land disturbing and soil erosion permits
  • Signs
  • Driveways onto a county road
  • Zoning compliance and home occupations

Who handles permitting in Jones County?

ItemDetails
Permits and inspectionsJones County Planning & Zoning (County and City of Gray)
Address166 Industrial Blvd., P.O. Box 1359, Gray, GA 31032
Phone478-986-5117
Emailzoning@jonescountyga.org
Online portalJones County iWorQ Citizen Portal
Planning and Zoning DirectorTim Pitrowski
Septic and well permitsJones County Health Department

Short on time to read all of this?

Get a free quote →

Planning & Zoning handles building permits and inspections, zoning, land disturbing permits, signs, stormwater management and floodplain management. It serves the City of Gray as well as the unincorporated county, and keeps separate City forms for rezoning, variances, conditional uses and design review in Gray.

Online portal and forms

The iWorQ Citizen Portal lets you apply for a building permit, search an existing permit and make payments; contractors fill in property and contractor details using the search bars at the top of the application. Paper forms on the Planning & Zoning page include:

  • Residential permit application, covering new homes, additions, renovations, accessory buildings, pools, single trade permits and safety inspection requests.
  • Commercial building permit application.
  • Authorized Permit Agent Form: an original is required when the applicant is not the licensed general contractor or a homeowner acting as their own contractor.
  • Subcontractor affidavit.
  • Mobile home permit application and the affidavit for a used mobile home.
  • Demolition, sign, driveway and site plan forms.

Permit costs and fees in Jones County

The Permit Fee Schedule posted by Planning & Zoning, which covers both the County and the City of Gray, is dated December 1, 2017.

Not sure this scope needs a permit?

Get a free quote →
Jones County permit fees (schedule current as of 12-1-17)
ProjectFee
New site-built home, heated space$0.16 per sq ft
New site-built home, unheated space$0.06 per sq ft
Each full or half bath$12
Manufactured home$0.15 per sq ft, $100 minimum
Barn, garage or shop$0.07 per sq ft
Open-sided pole barn$0.03 per sq ft
Single-use agricultural building$0.02 per sq ft
Office, retail, restaurant or gas station$0.16 per sq ft
Apartments, hotels, convalescent homes$0.18 per sq ft
Factory, warehouse or church$0.06 per sq ft
Swimming pool$50
Single trade permit$30
Demolition$60
Soil erosion control permit$40 per acre
Re-inspection$100

For example, a home with 2,000 sq ft heated, a 500 sq ft garage and porch area, and two full baths and one half bath comes to $320 plus $30 plus $36: $386. Fees are rounded to the nearest dollar and are not refundable, and they double if you apply after construction has started. Inspecting a building whose permit has expired, to issue a Certificate of Occupancy, costs $100. The schedule states that impact fees are not collected. Driveway permits now cost $35 under the County’s 2025 driveway application.

Electrical, plumbing and HVAC permits

Planning & Zoning issues single trade permits for electrical, plumbing or HVAC work at $30 each. Property owners and renters may do their own work, but any hired electrical, plumbing or HVAC contractor must hold a valid Georgia contractor’s licence. On a new home, affidavits from every paid electrical, plumbing and HVAC subcontractor are required before the Certificate of Occupancy is issued; for a pool, the electrician’s affidavit is due before the first (bonding) inspection.

Rather talk it over?

Call 1-855-478-4290 →

Application documents

New home

  • Well permit or public water tap receipt
  • Septic tank permit or sewer tap receipt
  • Approved driveway permit
  • Site plan
  • Copy of the plat, for new lots
  • Original Authorized Permit Agent form, if you are not the licensed general contractor or the owner-builder
  • For a barndominium, one set of plans sealed by a Georgia licensed engineer

Commercial

  • Sewer or septic approval, and water or well approval
  • Plat or survey
  • Site plan with all structures and the paved parking area
  • Approved soil erosion plan if the development is over 1.1 acres
  • Driveway permit from Georgia DOT or the County
  • Structural drawings sealed by an engineer or architect
  • Names, phone numbers, addresses and state licences of all subcontractors

The commercial application also asks for the flood zone designation and whether the project is a Development of Regional Impact.

How to apply: 6-step Jones County process

1. Check zoning first

Planning & Zoning keeps the only official zoning maps; ask for the zoning and lot requirements for the parcel.

2. Line up water, sewer and septic

Get the water tap receipt or well permit, and the sewer tap receipt or septic permit from the Health Department.

3. Get the driveway permit

Pay $35, flag the driveway location and let Public Works decide whether a culvert is needed.

4. Apply online or on paper

Submit through the iWorQ portal or bring the application to 166 Industrial Blvd.

5. Pay the permit fee

Pay through the portal or at Planning & Zoning.

6. Call for inspections

Tell the inspector when each stage is ready, and file the subcontractor affidavits before the Certificate of Occupancy.

Rather not deal with the Jones County building department?

Get a free quote →

Jones County inspections

County code makes the permit holder responsible for notifying the inspector when work is ready. The typical inspections are the footing inspection (after groundwork, before concrete), the framing inspection (after electrical, plumbing and mechanical rough-ins and before anything is covered) and the final inspection when the building is ready to occupy. A failed inspection costs $100 to re-inspect.

Manufactured homes need two or more inspections before power is connected: a health and safety inspection for used homes, a footing inspection for block underpinning, a setup inspection with the home tied down and hookups complete (before underpinning), and a final. Call Planning & Zoning 24 hours ahead, Monday to Friday, 8:00 a.m. to 5:00 p.m.; once the home passes, the office authorises the power company to connect it.

Local Jones County details

Manufactured homes: they are allowed in four county zones (Ag-1, R-R, R-MH and C-1) and only in the R-3 zone in Gray. Only double-wides are allowed in R-R and Gray’s R-3, and those homes need masonry underpinning. A used home also needs photos, a signed compliance affidavit and a $750 letter of credit or cash deposit, refunded when the Certificate of Occupancy is issued.

Pools: a pool must be enclosed by a fence 4 feet high in the county and 5 feet high inside Gray before it is used.

Water and sewer: the County and the City of Gray each run water service; sewer taps are bought at Gray City Hall.

Georgia building code

Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes

Want this handled start to finish?

Get a free quote →

Jones County permit search and official resources

Inspections are where schedules slip.

Get a free quote →

Jones County permit FAQs

Who issues building permits in Jones County and Gray?

Jones County Planning & Zoning, 166 Industrial Blvd., Gray (478-986-5117), for both the unincorporated county and the City of Gray.

How much is a building permit for a new house in Jones County?

$0.16 per heated square foot, $0.06 per unheated square foot and $12 per full or half bath. A 2,000 sq ft home with 500 sq ft unheated and 2.5 baths comes to $386.

Can I apply online?

Yes, through the County’s iWorQ Citizen Portal, which also lets you look up permits and pay.

Do small projects need a permit?

Not if the construction cost is under $1,000, unless an inspection is needed.

Can a homeowner do their own electrical or plumbing work?

Yes. Owners and renters may do their own work; any hired electrician, plumber or HVAC contractor must hold a valid Georgia licence.

What happens if I build before getting a permit?

The permit fee doubles.

How much is a mobile home permit?

$0.15 per square foot, not counting the tongue, with a $100 minimum.

Simplify Jones County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Jones County sooner?

Let Alliance prepare, file, and track your Jones County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Jones County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.