Inside Cartersville city limits, permits are issued by the City’s Building Department at City Hall, 10 N Public Square, and every permit and application is filed online through the City’s OpenGov portal. A new house is charged the ICC construction rate times its heated square footage times 0.0035, and inspections requested by email are typically done the next business day.
What requires a permit in Cartersville?
The Building Department handles permits, plan review and inspections for residential and commercial construction, and every City department involved must sign off on an application before the permit is issued. The City’s fee ordinance and forms cover:
Building
- New homes and commercial buildings, including shell-only buildings
- Remodels of existing homes and commercial buildings
- Demolition and moving buildings
- Retaining walls over 4 feet measured from the bottom of the footing
- Swimming pools
- Signs
Trades and fire
- Electrical, including temporary power poles and service changes
- Plumbing, water and sewer lines and water heaters
- Mechanical and gas lines, including commercial grease hoods
- Fire sprinkler systems
Demolition permits may need an asbestos report, and properties in a historic district need a Certificate of Preservation before work starts.
Cartersville building department: who handles permitting
The Building Department, part of Planning & Development, reviews plans, issues permits and inspects construction inside the city. All building plans are reviewed by both the Building Official and the Fire Marshal.
| Detail | Information |
|---|---|
| Permit authority | City of Cartersville Building Department |
| Phone | 770-387-5661 (permitting); 770-387-5600 (Planning & Development) |
| Location | City Hall, 10 N Public Square, Cartersville, GA 30120 |
| Hours | Monday–Friday, 8 a.m.–5 p.m. |
| Filing | Cartersville OpenGov portal |
| Commercial plans | plans@cartersvillega.gov |
| Inspections | inspections@cityofcartersville.org |
Short on time to read all of this?
Get a free quote →Cartersville permit types and filing path
All permits and applications are submitted online through the Cartersville OpenGov portal. The Building Department also publishes these forms:
- Authorized Permit Agent Form, for someone pulling permits on a contractor’s behalf.
- Owner Building Permit Affidavit: for owners building for their own or their family’s or business’s use, not for sale or lease. An owner who sells within 24 months of the Certificate of Occupancy cannot pull another owner permit without a state licence. Owners hire licensed electrical, plumbing and HVAC contractors unless they do that work themselves.
- Energy Code Certificate and Final Inspection Sign Off.
- Statement and Schedule of Special Inspections for commercial work that needs them.
- Retaining Wall Application, Swimming Pool Barrier Details and the Vested Interest Acknowledgement and Release Form.
For a demolition, a contractor needs a notarised letter from the owner; an owner acting as contractor brings the recorded warranty deed and photo ID, and must be named on the deed. Zoning needs photos of three sides of the structure, and asbestos testing and removal are the contractor’s responsibility.
Permit fees in Cartersville
Building fees are set in Sec. 17-77 of the City Code, as re-enacted by Ordinance 35-25 on September 18, 2025. The City’s website still links a 2018 fee schedule with lower issuing and re-inspection fees, so use the 2025 figures below when you budget.
| Project | Fee |
|---|---|
| New home | ICC rate for the construction type × heated sq ft × 0.0035 |
| New commercial building | ICC rate for the occupancy and construction type × sq ft × 0.003 |
| Shell-only building | The new-building fee less 20% |
| Remodel, residential or commercial | $6.50 per $1,000 of construction cost, $50 minimum |
| Demolition | $50 |
| Moving a building | $100 |
| Fire sprinkler | $100 |
| Sign | $50 per sign; $100 late fee if installed first |
| Re-inspection | $50 per site visit |
| Reinstating an expired permit | $50 |
Not sure this scope needs a permit?
Get a free quote →For example, the Code’s table rate for a wood-frame (type VB) one- or two-family home is $116.15 per sq ft, so 2,000 heated sq ft gives a building permit fee of about $813, before trade permits.
Electrical, plumbing, mechanical and gas work
Mechanical, electrical, plumbing and fire sprinkler contractors must show both their state licence and a business licence before their permits are issued. Each trade permit carries a $50 issuing fee (from September 2025) plus:
| Permit | Fee |
|---|---|
| Electrical, 200 A service (with temporary) | $65 ($80) |
| Electrical, 400 A service | $95 |
| Electrical, temporary pole only | $50 |
| Electrical, residential repairs or additions | $50 |
| Plumbing, new house | $70 (1 bath) to $125 (6 or more baths) |
| Plumbing, water heater / water or sewer line | $50 each |
| Gas line, residential or commercial | $50 |
| Mechanical, by job value | $50 up to $1,000, rising in steps with value |
Re-inspections for building, plumbing, electrical and mechanical work are $50 each.
Alliance handles electrical permit expediting for contractors here. More on this: who pulls the electrical permit.
Rather talk it over?
Call 1-855-478-4290 →Application documents and plan review
Contractors must hold a valid state licence and a current city or county business licence from anywhere in Georgia; homeowners pulling their own permits may be exempt from the business licence requirement. Commercial plans follow the City’s plan review flow chart:
- The design consultant emails digital plans and the application to plans@cartersvillega.gov after an initial conversation with the Building Official.
- The Fire Marshal reviews first and tells the Building Official when the plans are ready.
- The Building Department reviews and sends plans to other City departments as needed; the consultant answers each set of comments.
- Fees are set once plans are approved, and the permit is issued when they are paid. Review time depends on the project’s complexity.
Retaining walls need a site plan and an engineer-stamped wall section, zoning approval and an engineer’s completion letter. Demolitions that disturb over an acre, are within 200 feet of water or include floodplain also need stormwater approval.
Before you file in Cartersville
- Check that the parcel is inside Cartersville city limits and whether it is in a historic district.
- Have the state licence and business licence ready for every contractor on the job.
- For demolition, get the asbestos report and photos of three sides of the building.
- For commercial work, talk to the Building Official before sending plans.
How to apply: 6-step Cartersville process
Check that the parcel is inside Cartersville city limits.
Building, electrical, plumbing, mechanical, gas, sprinkler, demolition, retaining wall or sign permits as the job needs.
Plans, licence copies, affidavits and any asbestos report or Certificate of Preservation.
File each permit in the OpenGov portal; commercial plans also go to plans@cartersvillega.gov.
Answer Fire Marshal and Building comments, then pay the fees to have the permit issued.
Email inspection requests and pass the final before the Certificate of Occupancy.
Rather not deal with the building department?
Get a free quote →Cartersville inspections
Request inspections by email to inspections@cityofcartersville.org with the permit number, project address, inspection type and the date wanted if it is not the next business day; inspections are typically done the following business day. Residential inspections run in this order:
- Temporary power pole and footing
- Rough: framing, mechanical, electrical and plumbing together, with heated-space penetrations sealed and a gas pressure test where gas is supplied
- Firewall for duplexes and townhomes, and a Fire Marshal sprinkler inspection if one is installed
- Insulation, then temporary power (meter, panel and one GFCI outlet)
- Final, covering all trades, landscaping and site work, and required appliances
Before the Certificate of Occupancy, the City needs engineer letters for the foundation and soil compaction where required, and the Georgia Energy Code compliance form.
Local Cartersville details that matter
- Plan review — the Building Official and the Fire Marshal review all building plans, with the Fire Marshal going first on commercial projects.
- Sign-off — every City department involved must approve the application before the permit is issued.
- Historic districts — work on property in a historic district needs a Certificate of Preservation.
- Fee schedule — the September 2025 ordinances doubled the issuing and re-inspection fees to $50; the 2018 PDF on the City site predates them.
Georgia building code
Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes
Want this handled start to finish?
Get a free quote →Cartersville permit search and official resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Georgia state codes
- Permit information
- Building Department
- Cartersville OpenGov permit portal
- Cartersville City Code, Chapter 17 (permit fees, Secs. 17-77 to 17-83)
- Cartersville residential required inspections
- Cartersville plan review flow chart
- Cartersville Owner Building Permit Affidavit
Cartersville permit FAQs
Who handles building permits in Cartersville?
The City of Cartersville Building Department, part of Planning & Development, handles building permits inside the city.
How much is a building permit for a new house in Cartersville?
The ICC construction rate times heated square footage times 0.0035; at the Code’s $116.15 rate for a wood-frame home, 2,000 sq ft is about $813.
Inspections are where schedules slip.
Get a free quote →How much is a remodel permit?
$6.50 per $1,000 of construction cost, with a $50 minimum.
Can a homeowner pull a permit in Cartersville?
Yes, with the Owner Building Permit Affidavit, for a building the owner will use and not sell or lease. Selling within 24 months blocks another owner permit.
How do I request an inspection?
Email inspections@cityofcartersville.org; inspections are typically done the next business day.
Do I need a permit for a retaining wall?
Yes, if it is over 4 feet from the bottom of the footing; it needs an engineer-stamped design and completion letter.
Simplify Cartersville permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Cartersville sooner?
Let Alliance prepare, file, and track your Cartersville permits while your crew stays on the job.
More Georgia permitting guides
Bartow County
Read guide →Catoosa County Building Permit Guide
Read guide →Cedartown Building Permit Guide
Read guide →Chamblee Building Permit Guide
Read guide →Charlton County Building Permit Guide
Read guide →Chatham County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Cartersville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.