Municipal GuideFloridaUnion County · Lake Butler

Union County Building & Trade Permit Guide

How to get a building permit in Union County, FL — Cloudpermit portal, 7–10 day review times, combination permits, flood letters, inspections. 2026 guide.

Jurisdiction: Union County Building DepartmentCode: Florida Building Code, 8th Ed. (2023)Portal: Cloudpermit
Authority
Union County Building Dept.
15 NE 1st St., Lake Butler
Apply Online
Cloudpermit
How-to videos on the county site
Review time
7–10 business days
≤2 days if no review needed
Fun fact
Florida's smallest county
By land area

Union County — Florida's smallest county by land area — runs a modern permitting operation for its size. The Union County Building Department at 15 NE 1st St. in Lake Butler takes applications through Cloudpermit, links the platform's how-to videos right on its website, and publishes its review timelines plainly: allow 7–10 business days for the Building Official to complete any necessary reviews, while permits needing no review may issue in up to 2 business days.

Like several neighboring counties, Union issues combination permits — one permit covers all trades at a site, with documentation of the subcontractors who performed each trade under the general contractor's permit. And in a detail contractors should note before quoting work in town: the City of Lake Butler's building department falls under the direction of the county Building Department, so both jurisdictions run through the same office and inspector, Wilson Whidden.

Applies throughout Union County. Building permitting for the City of Lake Butler falls under the direction of the county Building Department, so city and county projects alike route through the office at 15 NE 1st Street.

📍 All contractors and subcontractors must be licensed with this office before a permit will issue. Union County requires contractor registration with the Building Department itself — including a notarized power of authorization (good for one year) naming anyone else allowed to pay for and pick up permits. No permit issues until all county and state requirements are on file.

What requires a building permit in Union County?

Under the Florida Building Code (§105.1), a permit is required before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of most structures and systems. New for 2026: Florida HB 803 (effective July 1, 2026) created additional building-permit exemptions for certain single-family residential work - notably F.S. 553.79(1)(g), which can exempt qualifying work valued under $7,500 when it involves no electrical, plumbing, mechanical, gas, or structural work, the home is not in a Special Flood Hazard Area, and the owner submits a written exemption request to the Building Official. Ask the permit counter whether your scope qualifies before assuming a permit is needed.

Permit required

  • New homes, additions, and tenant build-outs
  • Structural / load-bearing alterations and demolition
  • Reroofing, window and door replacement, and exterior work
  • Electrical service changes and most wiring alterations
  • Mechanical / HVAC changeouts and boilers
  • Plumbing alterations, repipes, gas, and water heaters
  • Pools and spas (barrier required), signs, and fences
  • Manufactured homes and solar PV systems

Usually exempt

  • Painting, flooring, cabinetry, and cosmetic work
  • Like-for-like minor repairs not altering systems
  • Certain low non-structural fences (confirm limits)
  • Routine maintenance not extending or rerouting systems
Exemptions are narrow and local. Always verify with the permit counter before starting work - unpermitted work risks stop-work orders, doubled fees, and closing/insurance problems.

Who handles permitting in Union County?

The Building Department at 15 NE 1st St. in Lake Butler — phone (386) 496-2676, fax (386) 496-4240, open 8 a.m. to 4 p.m. weekdays — is led by Building Inspector Wilson Whidden and also directs building services for the City of Lake Butler. Planning and zoning review runs through the county under County Coordinator James Williams, CPM, CBC. The county's application checklists route the related agencies clearly: septic through the Health Department (or a sewer and water tap-in receipt from the City of Lake Butler), culverts through FDOT on state roads, and compliance letters from the county or from Raiford, Lake Butler, or Worthington Springs depending on the parcel. All permitting runs through the Cloudpermit.

  • Address: 15 NE 1st St., Lake Butler, FL 32054
  • Phone: (386) 496-2676
  • Hours: Monday–Friday, 8:00 a.m. – 4:00 p.m.

Union County permit types

A building permit is one record among many. the Union County Building Department issues work under separate record types, and filing under the wrong one is a rejection, not a correction — the application is closed and refiled, and the review clock restarts.

Residential permit types

Residential permit types in Union County
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures over the exempt thresholdFull plan review (structural, energy, zoning)Valuation-based
Renovation / alterationStructural or load-bearing changes, layout changes, substantial repairPlan review scaled to scopeValuation-based
ReroofRoof covering replacement and most major roof repairProduct approval review; dry-in and nail-off inspectionsValuation or squares
Solar photovoltaicRooftop or ground-mount PV installation or replacementStructural plus electrical reviewFlat or system-size based
Solar thermalPassive water heating or pool heating systemsPlumbing and structural reviewFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, most wiring alterationsTrade review; filed against the building permitPer-permit minimum or per-device
PlumbingNew piping, repipes, water heaters, fixtures, gas pipingTrade review; filed against the building permitPer-permit minimum or per-fixture
Mechanical / HVACChangeouts that are not like-for-like, ductwork, refrigerationTrade review; filed against the building permitPer-permit minimum or per-unit
Windows and doorsReplacement units and opening protectionProduct approval review for wind-borne debrisValuation or per-opening
Pool and spaIn-ground and above-ground pools, spas, barrier and enclosure workPlan review plus barrier and electrical bondingValuation-based
Fence and accessoryFences, sheds, decks, and carports over the exempt thresholdZoning plus structural where applicableFlat or valuation-based
DemolitionFull or partial demolition of a structureUtility disconnect verification requiredFlat

Commercial permit types

Commercial permit types in Union County
Permit typeWhat triggers itReview pathFee basis
New constructionGround-up commercial, industrial, and multifamilyFull multi-discipline plan reviewValuation-based
Tenant improvementInterior build-outs and suite fit-upsPlan review across affected disciplinesValuation-based
Renovation / alterationStructural, envelope, or system changes to an existing buildingPlan review scaled to scopeValuation-based
Change of useConverting a building from one occupancy classification to anotherZoning, life-safety, and accessibility reviewValuation or flat
ReroofCommercial roof covering replacementProduct approval review plus fire review where applicableValuation or squares
Solar photovoltaicCommercial rooftop, carport, and ground-mount PVStructural, electrical, and often fire reviewValuation or system-size based
ElectricalService, distribution, and branch circuit workTrade reviewValuation or per-device
PlumbingSupply, waste, vent, and gas systemsTrade reviewValuation or per-fixture
Mechanical / HVACRooftop units, ductwork, exhaust, and refrigerationTrade reviewValuation or per-unit
Fire protectionSprinkler, standpipe, alarm, and suppression systemsFire prevention plan reviewValuation or per-device
SignWall, monument, and illuminated signageZoning plus electrical where illuminatedFlat or per-sign
DemolitionFull or partial commercial demolitionUtility disconnect and environmental clearanceFlat or valuation-based

Residential

  • Single-discipline review in most cases
  • Master permit with trades filed against it
  • Owner-builder route exists but carries statutory affidavits
  • Product approval drives roofing and opening protection

Commercial — multi-discipline

  • Concurrent review across building, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Accessibility and life-safety review attach to change of use
  • Impact and concurrency fees can apply on top of permit fees

Solar permits in Union County

Solar is permitted as its own record type in most Florida jurisdictions rather than rolled into a general building permit, and residential and commercial photovoltaic are usually separate records with different document sets. Solar thermal — passive water and pool heating — is a third, distinct record.

A photovoltaic submittal is reviewed on two tracks at once: structural (roof load path, attachment spacing, uplift) and electrical (conductor sizing, rapid shutdown, point of interconnection). A single-line diagram and a signed and sealed structural attachment detail are the two attachments most often missing on a first submittal.

Under Fla. Stat. §163.04, a homeowners' association cannot prohibit a solar collector on a dwelling — HOA architectural approval is not a prerequisite to permit issuance, though it may still be a contractual matter between owner and association.

Utility interconnection runs parallel to the building permit, not inside it. Permission to Operate is issued by the utility after the final electrical inspection clears.

Roofing permits in Union County

A roof covering replacement requires a permit in every Florida jurisdiction. Repairs below the local threshold may not, but the threshold is scope-specific and confirming it with the building department before tear-off is cheaper than an after-the-fact permit.

Every roof product must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address. A product approval number that has lapsed or is rated below the site wind speed is the single most common reroof rejection.

Reroof inspections are sequenced: dry-in after the underlayment, nail-off on the sheathing fastening, and final. Covering the deck before the dry-in inspection means tearing it back open.

Hurricane mitigation retrofit requirements can attach when an existing roof is replaced, including secondary water barrier and roof-to-wall connection work. These add scope and documents, and they are triggered by the replacement itself.

Under Fla. Stat. §553.7922, jurisdictions run expedited procedures for permits that need no technical review — reroofs, roof repairs, and similar — during a declared state of emergency.

Record types, document sets, and fee structures are set by the Union County Building Department and change without notice. Confirm the current record type against the building department before filing.

Union County building permit cost

Union County's application checklists spell out the documentation that must accompany fees: a Letter of Compliance/Flood Data carries a $75.00 fee when issued by the county Building Department for unincorporated parcels (municipal parcels get theirs from Raiford, Lake Butler, or Worthington Springs), flood-zone projects need the base flood elevation and a Flood Elevation Certification with first-floor elevation before issuance, and commercial buildings must include a copy of their Suwannee River Water Management District permit. Confirm current permit fee amounts with the office at (386) 496-2676.

How Union County permitting works

ComponentHow it works
Letter of Compliance / Flood Data (unincorporated)$75.00, issued by the county Building Department
Flood-zone projectsBFE + Flood Elevation Certification with first-floor elevation before issuance
Commercial buildingsCopy of SRWMD permit required with application
Combination permitOne permit covers all trades; subcontractor verification form required
Requirements and the $75 compliance letter fee per the county's posted application checklists

Union County trade permits

Union County issues combination permits, so trades work under the general contractor's single permit — but the subcontractor verification form must be completed, documenting who actually performed each trade, and every contractor and sub must be licensed with the Building Department before issuance. Plans must meet the State Minimum Plan Requirements in two sets, showing wall sections with material types and sizes, nailing, header sizes, bracing, truss anchors and straps, plus the service panel, smoke detectors, and GFI outlet locations — the county's checklist is unusually explicit about electrical detail on the plans.

Electrical permits

Required for service installations, panel upgrades, solar PV, and most wiring alterations in Union County, filed by a licensed electrical contractor against the master building permit through the Union County Building Department.

Plumbing permits

Required for new plumbing, repipes, water heater changeouts, fixture relocations, and gas piping; fees follow the local schedule with per-permit minimums.

Mechanical (HVAC) permits

Required for HVAC installations and changeouts, ductwork, and refrigeration; specialized systems are permitted and inspected separately.

Miscellaneous & specialty

Roofs, pools and spas, screen enclosures, mobile home set-ups, and demolition are permitted separately. Exterior components need current Florida Product Approval rated for the local wind speed.

How to get a building permit in Union County

Register with the office

All contractors and subcontractors must be licensed with the Union County Building Department before a permit will issue — including insurance certificates made out to the department and, if others will pick up permits, a notarized power of authorization (valid one year).

Gather the compliance documents

Septic permit/letter from the Health Department or a Lake Butler sewer and water tap-in receipt; a culvert permit or FDOT non-permit letter for state roads; the Letter of Compliance — $75 from the county for unincorporated parcels, or from Raiford, Lake Butler, or Worthington Springs in town.

Sort parcels and deeds

A lot split requires a new tax parcel number from the Property Appraiser; a recent purchase requires a copy of the recorded deed; owner-builders sign the disclosure statement with the office.

Submit through Cloudpermit

File the application with two plan sets meeting the State Minimum Plan Requirements, the survey and legal description, the subcontractor verification form, and the recorded Notice of Commencement.

Review & issuance

Allow 7–10 business days where Building Official review is needed; permits requiring no review may issue in up to 2 business days. Flood-zone permits wait on the elevation certification.

Post the address & inspect

Post the 911 address at the road — with house numbers on the home if it sits more than 50 feet back — and request inspections through Cloudpermit through final.

Inspections in Union County

Inspection requests run through Cloudpermit (the county links the platform's 'How to Request Inspections' video on its site) or the office. The county's posted requirements extend to the address itself: the 911 address must be posted at the road, with numbers on the home if it's more than 50 feet from the road — inspectors have to find the site — and the recorded Notice of Commencement must be on file.

Official Union County permitting resources

Frequently asked questions

How long does it take to get a building permit in Union County?

Union County publishes its own answer: up to 2 business days for permits needing no Building Official review, and 7–10 business days where review is required. The compliance-letter and septic steps in front of the application — plus contractor registration if you haven't worked the county before — are what actually stretch schedules, so start those first.

How do I look up a permit in Union County?

Applications filed through Cloudpermit are tracked in the portal — status, messages, and inspection results appear on the applicant dashboard, and the county links Cloudpermit's how-to videos from its Building Department page. For older records, call (386) 496-2676.

How long does Building Official review take in Union County?

The county publishes it plainly: allow 7–10 business days for the Building Official to complete any necessary reviews on permits or submitted plans, while building permits may take up to 2 business days to issue if no review is necessary. That published split makes Union unusually predictable for a rural county.

Who issues permits inside the City of Lake Butler?

The county — the City of Lake Butler's building department falls under the direction of the Union County Building Department, so city and county projects run through the same office at 15 NE 1st St. and the same inspector. City parcels still need their Letter of Compliance from the city, and sewer/water tap-in receipts replace the septic letter.

What is the $75 letter in Union County's checklist?

The Letter of Compliance/Flood Data: for unincorporated parcels it's issued by the county Building Department for a $75.00 fee, while parcels inside Raiford, Lake Butler, or Worthington Springs get theirs from the municipality. Flood-zone parcels additionally need the base flood elevation and a Flood Elevation Certification with first-floor elevation before the permit issues.

Do subcontractors need to register in Union County?

Yes — all contractors and subcontractors must be licensed with the Building Department prior to permit issuance, with insurance certificates made out to the department, and the subcontractor verification form documents who performed each trade under the combination permit.

Do I need a permit to install solar panels in Union County?

Yes. Photovoltaic installations in Union County are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Fla. Stat. §163.04 a homeowners' association cannot prohibit a solar collector, so HOA approval is not a prerequisite to permit issuance. Utility interconnection and Permission to Operate run in parallel with the permit, not inside it.

Does a roof replacement require a permit in Union County?

Yes. A roof covering replacement requires a permit in every Florida jurisdiction, including Union County. Products must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address, and inspections are sequenced — dry-in, nail-off, then final. Some minor repairs fall below the permit threshold, but the threshold is scope-specific.

What is the difference between a residential and a commercial permit in Union County?

Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in Union County runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.

Do trade permits need to be pulled separately in Union County?

Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.

What happens if I file under the wrong permit type in Union County?

The application is rejected rather than corrected. the Union County Building Department closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.

Can I apply for all Union permit types online?

Most record types are filed through counter intake in Lake Butler, but availability varies by permit type and by applicant. Some records still require in-person submittal, and owner-builder filings are frequently restricted to counter submittal regardless of record type.

Simplify Union County permitting with Alliance Permitting

Union County tells you exactly what it wants — registration, compliance letters, two compliant plan sets, verified subs — and issues fast when it gets them. Alliance Permitting is a permit expediter for Union County and handles the registration and document chain and files a package that clears review the first time.

250K+Permits approved
All 50States covered
AI + HumanExpert filing
Done-for-youWe file, you build

Trusted by leading builders and brands - including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.

Contractors and builders choose Alliance for Union County because we deliver:

  • Local expertise - we know the Union County Building Department and the Cloudpermit process.
  • Complete oversight - track every permit and inspection across all your jobs in one place.
  • Error-free submissions - AI pre-checks plus expert review catch issues before they become correction cycles.

Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the building department through issuance - including preparing private-provider documentation where that option is available. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.

Ready to break ground in Union County sooner?

Let Alliance prepare, file, and track your Union County permits while you stay focused on building. Get a free, no-obligation quote today.

This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of July 2026. Permit requirements, fees, and processes change; always confirm current details with the Union County Building Department before filing. This is not legal advice.