Louisville’s Building Safety division at City Hall issues the city’s building, electrical, mechanical and plumbing permits, all filed through the Citizen Self Service (CSS) online portal.

Authority: City of Louisville Building SafetyCode: 2024 I-Codes and 2023 NECPhone: 303-335-4584
Authority
City of Louisville Building SafetyCity Hall, 749 Main Street
Apply / intake
Citizen Self Service (CSS) portal6 application types
Code
2024 I-Codes, 2023 NECI-Codes effective December 6, 2025

Building Safety, on the first floor of Louisville City Hall at 749 Main Street, issues all permits inside the city and its own inspectors cover building, electrical, mechanical and plumbing work. Applications go through the CSS online portal; simple trade and re-roof permits are issued the same or next business day, new homes and commercial projects take 4 to 6 weeks to review, and the permit fee is set by valuation with a 65% plan review fee.

What requires a permit in Louisville?

Most construction in Louisville needs a permit, fences, sheds, re-roofing and re-siding included. The City publishes a project-by-project table, and these are its entries for common home and business projects.

Permit needed

  • Fences, decks, pergolas, sheds and other accessory structures
  • Re-roofing and re-siding
  • Basement finishes, interior remodels, drywall and insulation
  • Additions, sunrooms, studios and detached garages
  • Air conditioners, furnaces, boilers, water heaters and swamp coolers
  • Stand-alone electrical, mechanical or plumbing work
  • Gas lines, fireplaces, hot tubs and irrigation systems
  • Solar PV systems and rooftop units
  • Pools, above or below ground
  • New or resized window and door openings
  • Foundation repair and demolition
  • Dumpsters, roll-offs and storage units on private property

No permit needed

  • Painting the outside of a house
  • An uncovered concrete patio
  • Replacing a window with one of the same size
  • Landscaping

Some projects depend on location. Driveway and sidewalk repairs, sewer or water repairs in the street and dumpsters in the right-of-way go to Public Works first, and retaining walls and playsets may need a call to the Planning Department. A retaining wall under 48 inches from the bottom of the footing to the top, with no surcharge, does not need a building permit; taller walls and any wall with a surcharge need stamped engineered plans. New and upgraded elevators are handled by the Colorado Division of Oil and Public Safety.

Who issues building permits in Louisville?

Building Safety reviews and issues permits, licenses contractors and carries out building, electrical, mechanical and plumbing inspections for property inside Louisville. Chad Root is the Chief Building Official. Land outside the city limits in unincorporated Boulder County comes under the Building Safety and Inspections division of Boulder County.

Louisville Building Safety contacts
DetailInformation
OfficeCity of Louisville Building Safety
AddressCity Hall, First Floor, 749 Main Street, Louisville, CO 80027
Phone303-335-4584
Emailbuilding@louisvilleco.gov
Office hoursMonday to Thursday, 8 a.m. to 4 p.m.; Friday by appointment
Planning Division (zoning, fences, PUDs)303-335-4592
Public Works (taps, right-of-way)303-335-4608

Short on time to read all of this?

Get a free quote →

Louisville permit types and the CSS portal

In the CSS portal, choose Apply, then Permits, then All, and pick one of 6 application types: Residential, Commercial, Minor Permit, MEP Single Trade, Temporary Use or Elevator. Picking the wrong type means submitting again, so email Building Safety first if you are unsure. If the address does not come up, leave out the direction word and type “749 Main” rather than “749 N Main”. The portal was rebuilt on June 20, 2025, and accounts from before that date have to be created again with the same email address.

Louisville review times by permit type
Permit typeReview time
Same-day permits: A/C, furnace, water heater, minor electrical, mechanical or plumbing, sewer or water repair, re-roof, re-sidingSame day or next business day
Fast-tracked permits: gas line, hot tub, fences, decks, demolition, foundation repair, new windows or doors, patios, signs, remodels1 to 2 weeks
Residential: additions, foundations, mobile homes, multi-family, new homes4 to 6 weeks
Commercial4 to 6 weeks
Rooftop units, solar, telecommunication2 to 3 weeks
Construction trailers1 to 4 business days
Other temporary permits1 to 2 weeks

Contractor licences. A contractor or subcontractor has to hold a current Louisville licence before being listed on a permit. Class A, B and C building contractors submit passing ICC test results, electricians and plumbers their state master and contractor licences, and mechanical contractors an ICC journeyman mechanical result. Most licence applications are reviewed the same or next business day. An expired licence can be renewed within one year; after that a new application is needed.

Louisville contractor licence fees
LicenceFee
Building contractor, Class A$175
Building contractor, Class B$116
Building contractor, Class C or Class D (other)$88
Plumbing, mechanical, or combined plumbing and mechanical$116
Solar contractor$88
Electrical contractor registrationNo fee

Louisville permit fees and project charges

The building fee table in use is Exhibit A, Table 4 of the fee schedule City Council approved on December 3, 2024 for 2025. The valuation covers materials, labor and contractor profit, and the City uses its own valuation data per square foot when that gives a higher figure than the contract price.

Not sure this scope needs a permit?

Get a free quote →
Louisville building permit fees (approved December 3, 2024)
Total valuation or itemFee
Up to $500$28, except as the municipal code provides for residential permits
$501 to $2,000$28 for the first $500, plus $4 per additional $100 or fraction
$2,001 to $25,000$82 for the first $2,000, plus $16 per additional $1,000 or fraction
$25,001 to $50,000$400 for the first $25,000, plus $12 per additional $1,000 or fraction
$50,001 to $100,000$700 for the first $50,000, plus $8 per additional $1,000 or fraction
$100,001 to $500,000$1,000 for the first $100,000, plus $6 per additional $1,000 or fraction
$500,001 to $1,000,000$4,000 for the first $500,000, plus $5 per additional $1,000 or fraction
Over $1,000,000$6,000 for the first $1,000,000, plus $4 per additional $1,000 or fraction
In-house plan review65% of the building permit fee
Extra plan review after the permit is issued$150 per hour, 1-hour minimum
Permit needing zoning verification only$28
Re-inspection$200 per hour
After-hours inspection$200 per hour, 2-hour minimum
Lost permit or inspection card$150
Temporary Certificate of Occupancy$175
Work without a permit, first offence2 times the permit fee, $200 minimum
Work without a permit, second offence within 12 months4 times the permit fee, $400 minimum

Use tax is charged on 50% of the valuation: 3.775% for the City of Louisville and 1.185% for Boulder County. For example, a $75,000 project has a $900 permit fee and a $585 plan review fee, and at those rates $1,415.63 of city use tax and $444.38 of county use tax. The example table on the City’s fee page still prints $1,368.75 of city use tax and a $3,298.13 total, which works out at 3.65% of half the valuation rather than the 3.775% stated on the same page; at 3.775% the total is $3,345.01.

Rather talk it over?

Call 1-855-478-4290 →

One residential exception is written into the municipal code (Sec. 15.05.050): an owner or occupant renovating or repairing an existing single-family home needs no building permit when labor and materials total $2,500 or less, the house is not enlarged, no structural member is altered and the work includes no electrical, plumbing or heating.

Impact fees for parks, transportation and library services apply to new homes and to basement finishes and additions that push the home’s finished area into a larger size category above 2,001 sq ft; the first 500 sq ft of an addition is usually exempt. Tap fees are owed only when a project needs a larger water or sewer tap, and a single-family sewer tap is $4,600. If you cancel a project and ask for a refund, the City keeps a $75 administrative fee.

Minor and same-day permits are paid at application. Reviewed permits are invoiced after approval, and the permit is issued about 1 business day after payment. Since September 30, 2026 commercial applicants pay the plan review fee before review starts, and an application is voided if that invoice is unpaid after 10 business days.

Electrical, plumbing, mechanical and gas permits in Louisville

Trade work that is not part of a larger building permit goes on an MEP Single Trade application, and the City’s inspectors inspect it. Louisville enforces the 2023 National Electrical Code, adopted without amendments by Ordinance 1866-2023 (Municipal Code Sec. 15.48.010), and requires GFCI protection on every new outdoor air conditioning unit.

The City’s rules for furnace, A/C, water heater and heat pump permits, dated April 1, 2026, are specific:

  • Only one contractor is allowed on an MEP permit, and each company may pull only the work its licence covers.
  • A furnace, A/C unit or heat pump needs a mechanical licence; a water heater or boiler needs a plumbing licence.
  • Electrical work cannot go on this permit type. A new circuit for a heat pump needs a separate Minor Electrical permit unless the contractor holds a dual mechanical and electrical licence.
  • The contractor, not the homeowner, requests the final inspection, and names the person who will be on site with a direct phone number.
  • A contractor with more than 3 expired permits cannot pull new ones until those are closed out.

Documents and plan-review submissions in Louisville

The City lists the documents for every permit type in its Residential, Commercial, Minor Permit, MEP Single Trade and Temporary Use requirement sheets.

Rather not deal with the building department?

Get a free quote →

New house

  • Stamped building plans
  • Site plan
  • Soils report
  • Water & Sewer Tap Application and Fixture Count Form
  • Site Improvement Worksheet
  • Residential New Build/Addition Checklist (2024 Residential Code Checklist)

Smaller projects

  • Addition or sunroom: stamped plans, site plan, fixture count, and a soils report or open hole inspection
  • Deck: stamped building plans and a site plan
  • Fence: construction plans or the signed Solid Fence Certification Form, plus a scaled site plan
  • Re-roof or re-siding: manufacturer’s specifications
  • Whole-structure demolition: plans, site plan and a copy of the state health department permit

Projects with detailed plans may also need the Energy Rater Checklist, the Foundation Setback Form, the Height Certification Form and the Site Improvement Valuation. Revisions go in with the Resubmittal Form.

Louisville’s design criteria under the 2024 codes include a 145 mph wind speed (3-second gust), wind exposure C, a 36-inch frost line and ice and water shield at the eaves of every shingled roof. The same sheet states that all structures must be protected by fire suppression systems and wired to be electric ready.

How to apply: 6 steps in Louisville

1. Check the project table

Look up the job in “Does my project need a permit?” to see whether it needs a permit and which application type it falls under.

2. Confirm your contractors are licensed

Every contractor and subcontractor needs a current Louisville licence and must be listed on the application.

3. Open a CSS account and apply

Choose Apply, Permits, All, select the permit type and enter the address without directional words.

4. Add contacts and upload documents

List the owner, applicant and contractor, then attach the plans, checklists and forms for the permit type.

5. Pay when invoiced

Over-the-counter permits are paid at application; reviewed permits are paid after approval by card or eCheck in the portal, or by check at City Hall.

6. Print the permit and inspection card

Both are issued through the portal and must be kept at the job site with the approved plans.

Louisville construction inspections

Request inspections in the CSS portal: View, My Permits, the permit record, then the Inspections tab. The cutoff for a next-business-day inspection is 4 p.m.; later requests roll to the following business day. Inspectors set their own daily routes, so look up the permit under Today’s Scheduled Inspections and contact the assigned inspector for an arrival window. To cancel, email Building Safety before 8:30 a.m.

A failed or missed inspection is charged a re-inspection fee, and no further inspection can be requested until it is paid. After a missed inspection, such as a mid-roof, the inspector calls the contractor to arrange the visit instead of it being booked online.

Want this handled start to finish?

Get a free quote →

Results appear on the permit’s Inspections tab and are emailed to the contractor or site contact. Certificates of Occupancy and Completion are reviewed within 3 business days of a passed building final. A permit expires 180 days after the last approved inspection, and the City does not reactivate expired permits, although one that only lacks a final may be given a single final inspection at no charge.

Local Louisville filing details that matter

Fire Hardening Code: Chapter 15.70 of the municipal code applies to new construction, accessory structures and the repair or replacement of certain building parts. Roof coverings must be Class A, gutters must be metal with gutter guards, and roof, attic and foundation vents need metal mesh with openings of 1/8 inch or smaller. Siding and eaves must be cementitious, stone, stucco or a Class A composite. Deck surfaces and railings must be Class A, with Class B composite as the stated exception. Emergency Ordinance 1913, in force since January 21, 2026, also bans planting new junipers.

Fences: any fence within 5 feet of a home or commercial building must be Class A rated or made of metal, masonry or stone. Where no Planned Unit Development sets other limits, fences may be up to 4 feet in a front yard and 6 feet elsewhere.

Marshall Fire rebuilds: the City offers a meeting with its Community Development team before filing, a separate rebuild fee form and design criteria for original owners, and use tax credit programs.

Mine hazard zones: the City keeps a Mine Hazard Map for checking whether a lot lies over old mine workings.

Construction hours: 7 a.m. to 8 p.m. Monday to Friday and 8 a.m. to 7 p.m. on Saturday and Sunday.

Colorado building code

Colorado has no statewide building code for private buildings: each city and county decides whether a code applies and which edition, while the state sets electrical and plumbing rules, a minimum energy code on any update, and a wildfire code for the mapped wildland-urban interface. Building codes in Colorado

Official Louisville permitting resources

City of Louisville pages, forms and fee documents used above.

Inspections are where schedules slip.

Get a free quote →

Louisville building permit frequently asked questions

How much does a building permit cost in Louisville, Colorado?

The fee depends on valuation: $28 up to $500 of work, $700 at $50,000 and $900 at $75,000. Plan review adds 65%, and use tax of 3.775% (city) and 1.185% (Boulder County) is charged on half the valuation.

Do I need a permit for a fence in Louisville?

Yes. A fence is a Minor Permit, and any part within 5 feet of a building has to be Class A rated or metal, masonry or stone.

Do I need a permit for a shed or deck?

Yes. Sheds are Minor Permit: Accessory Structure applications and decks are Minor Permit: Deck or Pergola applications with stamped plans and a site plan.

Do I need a permit to replace windows in Louisville?

Not for a like-for-like replacement of the same size. A size change or a new opening needs a Minor Permit: New Window/Door.

How long does plan review take in Louisville?

Same-day permits are issued the same or next business day, fast-tracked permits such as fences, decks and remodels take 1 to 2 weeks, and new homes, additions and commercial projects take 4 to 6 weeks.

How do I schedule an inspection?

Through the CSS portal, on the Inspections tab of the permit. Requests made by 4 p.m. are scheduled for the next business day.

Which codes does Louisville use?

The 2024 International Codes with local amendments, effective for applications submitted on or after December 6, 2025, plus the 2023 National Electrical Code and the City’s Fire Hardening Code.

Simplify Louisville permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Colorado. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Louisville sooner?

Let Alliance prepare, file, and track your Louisville permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Louisville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.