Skip to main content

Yuba County, California Building Permit Guide

To get a building permit in Yuba County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Yuba County’s Building Department, part of the Community Development and Services Agency in Marysville, handles intake, plan check, permits and inspections for unincorporated Yuba County, with applications through Yuba County Self Service.

Authority: Yuba County CDSA Building DepartmentServes: Unincorporated Yuba CountyPhone: (530) 749-5440
Authority
CDSA Building Department915 8th Street, Suite 123, Marysville
Covers
Unincorporated countyMarysville runs its own permits
Inspections
One business day aheadRequests before 4 p.m.
Intake fee
$190On all permits unless noted

In unincorporated Yuba County, building permits come from the Yuba County Building Department of the Community Development and Services Agency (CDSA), 915 8th Street, Suite 123, Marysville ((530) 749-5440). The department takes applications through Yuba County Self Service, checks plans with ICC-certified staff and inspects the work; simple residential jobs such as a water heater or re-roof can often be permitted over the counter the same day. Inside the City of Marysville, the city’s own department issues permits. County fees are set under Code Section 13.20.200, with a $190 processing fee on most permits.

What requires a building permit in Yuba County?

The Building Department is responsible for permits and inspections for all buildings and structures, existing or new, in the unincorporated county, and asks owners to talk to it before starting construction, repair or alterations so the project meets current building and zoning codes. Its permit page splits work into two groups:

Simple residential permits

  • Re-roofs and minor interior alterations
  • Wood stoves, water heaters and HVAC
  • Electrical service panel changeouts
  • Need only a description, a floor plan, a plot plan of the area or the manufacturer’s installation manual; often issued over the counter the same day

Plan submittal required

  • New construction and additions
  • Alterations and structural changes
  • Patio covers and decks
  • Other structures or situations with unique requirements

The county’s fee schedule shows other work it permits: fences other than masonry over 7 feet tall, masonry fences and retaining walls, pools and spas, solar systems, demolition, cargo container placement, manufactured homes and grading tied to a building permit. A stop work notice doubles the permit fee.

What Yuba County decides and what the state holds

The Building Department works under ordinances adopted by the Yuba County Board of Supervisors. The county sets its own fees (Code Section 13.20.200 for building, 13.20.400 for Environmental Health), its Zoning and Land Development Code and an expedited permitting ordinance for electric vehicle charging stations. The Building Department is the local enforcing authority for the state’s Title 24 building standards, and contractors are licensed by the state.

Yuba County building department: who handles permitting

The Building Department combines building and construction services with code enforcement inside the CDSA. It handles application intake, plan check, permit issuance and inspection for the unincorporated area and sends plans to the other departments, districts and agencies that must review them. Jeremy Strang is CDSA Deputy Director for the Building and Code Enforcement Division, and Rob Garramore is the Supervising Building Official.

Short on time to read all of this?

Get a free quote →
Who issues building permits in Yuba County
PlaceBuilding permits issued byNotes
Unincorporated Yuba CountyYuba County CDSA Building Department915 8th Street, Suite 123, Marysville; (530) 749-5440
City of Marysville (pop. 12,738)City of Marysville Community & Economic Development DepartmentMarysville building permit guide
City of Wheatland (pop. 4,267)Ask the county Building DepartmentThe county building website has a page for City of Wheatland residents

To see how a parcel is zoned, use the county’s Zoning Quick Check (search by address or parcel ID) or its interactive zoning map; if the address may be inside Marysville or Wheatland, ask the Building Department before applying.

Yuba County offices for a building project
DetailInformation
Building Department915 8th Street, Suite 123, Marysville, CA 95901; (530) 749-5440; fax (530) 749-5616; Building@yuba.gov
Public counterMonday to Friday, 8 a.m. to 4 p.m. (the inspections page notes it closes from noon to 1 p.m.)
Environmental Health (septic, wells)Same address; (530) 749-5450; EnvironmentalHealth@yuba.gov; weekdays 8 a.m. to 4 p.m., closed noon to 1 p.m.
SpanishThe inspections page notes Se Habla Español at (530) 749-5440

Yuba County permit types

Applications go through Yuba County Self Service, the county’s online permitting and planning system; the department posts a video on creating an account. A fee estimate form is available, and written fee estimates cost $190 for projects under $1,000,000 in valuation.

Residential permits

  • New homes: custom or model homes, production homes in a master-planned tract and factory-built homes each have their own square-footage rows in the new construction table; production and factory-built homes carry no plan check fee in that table, and a master plan costs $570 per unit to process.
  • Additions and remodels: additions to R-2 and R-3 buildings start at $1,850 for up to 200 square feet; a residential remodel is $475 for up to 500 square feet plus $95 for each additional 100 square feet, and a repair or rehabilitation $285.
  • Roofs, windows and HVAC: a re-roof of a single-family home is $190 for roofing material only or $285 with sheathing; window or sliding-door replacement $190; a complete residential HVAC system $142.50.
  • Accessory structures: awnings, patio covers, carports and decks up to 400 square feet are $285, and a prefabricated accessory structure up to 400 square feet $380. The department also posts accessory dwelling unit plans.
  • Manufactured homes: $475 for a foundation and $1,330 for a manufactured home or commercial coach with utility hook-up.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

The new construction table prices complete buildings, including mechanical, plumbing and electrical work, and multi-discipline tenant improvements by occupancy group and floor area, with plan check and inspection shown separately. Every tenant improvement starts at $1,850 for 500 square feet. A commercial, industrial, agricultural or multifamily re-roof is $1,140, and non-residential roof-mounted solar $950.

What comes before the building permit

  • Zoning: check where you can build on the property with the Zoning Quick Check, the zoning map and the Zoning and Land Development Code; an urban lot split (SB 9) carries a $190 building review fee and a $237.50 Environmental Health fee.
  • Environmental Health: septic systems and wells need Environmental Health permits, and it clears building permits through route slips ($190 for a primary building, $95 for an accessory one).
  • Fire safe rules: projects in high and very high fire risk areas pay $190 for a fire safe plan and $190 for fire safe inspections before and after construction; the department links state guidance on fire-resistant (WUI) construction.
  • Grading: the Building Department reviews and inspects small grading with a building permit ($142.50 for under 1 acre, no more than 2 feet of cut or fill and 50 cubic yards).
  • EV chargers: charging stations use the county’s expedited checklist and ordinance.

Septic systems and wells

Yuba County Environmental Health, also in the CDSA, permits septic systems and wells in its Land Use program. Its FY 26/27 fees include $902.50 for a new or replacement conventional septic system, $1,567.50 for a pressure-dosed or engineered system, $2,470 for an engineered system with supplemental treatment, $902.50 for a major repair and $475 for a minor repair that does not involve the leach field. A new domestic water well is $997.50 and an agricultural well $902.50, a well destruction $570, a soil boring or excavation $570 and a soil mantle observation $902.50.

Yuba County building permit fees

Building fees are set under Yuba County Code Section 13.20.200 and posted on the County Administrator’s County Fees page. The general building schedule is labelled FY 26/27, while the new construction table on the same page is labelled FY 25/26. Construction values come from the current ICC valuation table, and the state’s Building Standards Commission and SMIP fees are collected on top. A $190 processing and intake fee applies to all permits unless the schedule says otherwise.

Rather talk it over?

Call 1-855-478-4290 →
R-3 custom or model home, new construction table (FY 25/26)
SizePlan checkInspectionTotal
Up to 1,000 sq ft$1,480$2,960$4,440
Each 100 sq ft from 1,001 to 1,999$37$37$74
2,000 sq ft$1,850$3,330$5,180
Each 100 sq ft over 2,000$27.75$27.75$55.50

Worked example: a 1,500-square-foot custom home is $4,440 plus 5 × $74 ($370), or $4,810 ($1,665 plan check and $3,145 inspection), plus the $190 intake fee: $5,000 before state fees, impact fees and Environmental Health or fire charges.

Selected Yuba County building fees, FY 26/27
ItemFee
Processing / intake fee$190 per permit
Plan check or inspection, hourly (1-hour minimum, then $47.50 per quarter hour)$190
Inspection outside business hours (2-hour minimum)$380 per hour
Re-inspection, residential / non-residential$285 / $475
Water heater replacement (no processing fee)$95
Service or sub-panel up to 200 amps$47.50
Residential solar, roof mount / ground mount$285 / $570
Fence (non-masonry) over 7 ft, up to 100 lin. ft / masonry fence or retaining wall, up to 50 lin. ft$285 / $475
Swimming pool, gunite or vinyl-lined / fiberglass / prefabricated spa$760 / $570 / $95
Demolition or removal$285
Occupancy permit$380
Stop work noticeDouble fee (2 times the permit)
Permit reinstatement, permit under 5 years oldFull cost of the permit

The building schedule also covers residential fire sprinklers: a $190 processing fee, plan check by an outside consultant at actual cost and a $285 inspection. A business license inspection is $190. The County Fees page also links the county’s impact fees and the Planning and Public Works fee schedules, which apply separately.

Rather not deal with the Yuba County building department?

Get a free quote →

Trade permits and who may pull them in Yuba County

Electrical, plumbing and mechanical work in the unincorporated county is permitted and inspected by the Building Department. New buildings in the occupancy table include mechanical, plumbing and electrical work in the complete-building fee; stand-alone trade work has its own items, such as panels, motors, grease interceptors and piping, and apparatus replacement charged from a quarter-hour minimum.

Only the property owner, a licensed contractor or an authorized agent of the owner or contractor can sign for a building permit, and the application asks for the contractor’s license number. Contractors are licensed by the state’s Contractors State License Board, and owner-builders may pull permits for their own property.

How to apply for a Yuba County building permit

1. Confirm the jurisdiction and zoning

Make sure the parcel is outside Marysville and check its zoning with the Zoning Quick Check.

2. Create a Self Service account

Register in Yuba County Self Service using the county’s how-to video.

3. Gather the information

Have a detailed description, the address or assessor’s parcel number, the legal owner’s name, address and phone, the contractor’s license number, the valuation and the plans.

4. Submit and pay intake

Apply online; simple residential jobs can often be issued over the counter the same day at 915 8th Street.

5. Clear the other reviews

The department sends plans to the departments, districts and agencies that review them; answer each set of corrections.

6. Pay fees and receive the permit

Pay the plan check, inspection and state fees (the department’s menu includes an online payments page).

Review, corrections and what causes delay

Plans go out to other departments, districts and agencies as part of the review, and each reviewer’s comments have to be answered before the permit is issued. Plan changes are charged at $190 an hour with a one-hour minimum, and deferred submittals and application renewals are $190 each. Projects valued over $1,000,000 pay $570 for a fee estimate.

Yuba County building inspections

Active permit holders request inspections in Yuba County Self Service at least one business day ahead. A request received before 4 p.m. is scheduled for the next business day; one received after 4 p.m. goes to the day after that. The department does not call back or send a confirmation. To learn the approximate two-hour window, call (530) 749-5440 with the permit number; inspectors are generally available Monday to Friday from 8 to 9 a.m. and 3 to 4 p.m.

Want this handled start to finish?

Get a free quote →

ICC-certified inspectors check work at each stage against the state codes, county ordinances and engineering designs, following the department’s field inspection guidelines. A residential re-inspection costs $285 and a non-residential one $475, inspections outside business hours are $380 an hour with a two-hour minimum, and fire safe inspections are made before and after construction. A duplicate or replacement job card is $47.50.

California building code in Yuba County

The Building Department enforces Title 24 as the local enforcing authority and posts a page on the county’s adoption of the new California codes. FEMA’s Community Status Book lists unincorporated Yuba County (community 060427) as participating in the National Flood Insurance Program, with a current flood map dated February 18, 2011, and in the Community Rating System at class 7 (a 15% flood insurance discount).

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Yuba County building permit FAQs

Does Yuba County issue permits in Marysville?

No. The county covers the unincorporated area; Marysville’s Community & Economic Development Department issues permits inside the city.

Where is the Yuba County Building Department?

915 8th Street, Suite 123, Marysville, CA 95901; (530) 749-5440. The public counter is open weekdays 8 a.m. to 4 p.m.

Can I get a re-roof or water heater permit the same day?

Often, yes. Simple residential jobs need only a description, floor or plot plan or installation manual and can often be issued over the counter.

How much is a re-roof permit?

$190 for roofing material only on a single-family home, or $285 with sheathing, plus the $190 intake fee.

How do I schedule an inspection?

Request it in Yuba County Self Service at least one business day ahead; before 4 p.m. means the next business day.

How much is a septic permit?

Environmental Health charges $902.50 for a new or replacement conventional system and $1,567.50 for a pressure-dosed or engineered one.

Who can sign for a permit?

The property owner, a licensed contractor, or an authorized agent of the owner or contractor.

How do I get old permit records?

Submit a public records request through the county’s request page linked from the Building Department.

Inspections are where schedules slip.

Get a free quote →

Yuba County permit search and official resources

Applications and inspection requests run through Yuba County Self Service; older building records are requested through the county’s public records request.

Simplify Yuba County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Yuba County sooner?

Let Alliance prepare, file, and track your Yuba County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Yuba County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.